Oregon Bulletin

June 1, 2012

Department of Energy, Energy Facility Siting Council, Chapter 345

Rule Caption: Rules implementing the Council’s regulatory authority for siting energy facilities and other matters.

Adm. Order No.: EFSC 1-2012

Filed with Sec. of State: 5-15-2012

Certified to be Effective: 5-15-12

Notice Publication Date: 3-1-2012

Rules Amended: 345-001-0005, 345-001-0010, 345-001-0050, 345-011-0020, 345-011-0050, 345-015-0014, 345-015-0085, 345-015-0110, 345-015-0120, 345-015-0160, 345-015-0180, 345-015-0190, 345-015-0220, 345-015-0230, 345-015-0240, 345-015-0300, 345-015-0310, 345-020-0011, 345-020-0016, 345-020-0040, 345-021-0000, 345-021-0010, 345-021-0050, 345-021-0055, 345-021-0090, 345-022-0020, 345-023-0005, 345-023-0030, 345-023-0040, 345-024-0015, 345-024-0550, 345-024-0560, 345-024-0570, 345-024-0590, 345-024-0600, 345-024-0610, 345-024-0620, 345-024-0630, 345-024-0640, 345-024-0680, 345-024-0710, 345-024-0720, 345-026-0080, 345-026-0170, 345-027-0020, 345-027-0023, 345-027-0028, 345-027-0030, 345-027-0050, 345-027-0060, 345-027-0070, 345-027-0080, 345-027-0090, 345-027-0100, 345-027-0110, 345-027-0210, 345-027-0220, 345-027-0230

Subject: In this rulemaking, the Energy Facility Siting Council (Council) has reviewed Chapter 345 Divisions 1, 11, 15, 20, 21, 22, 23, 24, 26 and 27. The proposed amendments make corrections, modify procedures to increase efficiency and make minor word changes. The Council has corrected cross-references, conformed the rules to changes in Oregon statutes that have occurred since the last review, and clarified procedures based on knowledge gained from recent energy facility siting experience.

Rules Coordinator: Kathy Stuttaford—(503) 373-2127

345-001-0005

Uniform and Model Rules

(1) Except as described in this rule, the Council adopts and incorporates by reference in this chapter the following rules from the Attorney General’s Uniform and Model Rules (January 2012): OAR 137-001-0005 through 137-001-0100, 137-002-0010 through 137-002-0060, 137-003-0001 through 137-003-0092, and 137-005-0010 through 137-005-0070.

(2) Notwithstanding the provisions of OAR 137-003-0055(1), following the issuance of notice of a contested case, the Department of Energy shall enter into the record the substance of any significant contact between a Council member and any Department staff from that point forward, concerning facts in the record.

(3) In any conflict between the model rules and Council rules, the Council shall apply its own rules.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.490
Hist.: NTEC 1, f. 12-16-71, ef. 1-1-72; NTEC 6, f. 11-19-73, ef. 12-11-73; EFSC 13, f. & ef. 6-11-76; EFSC 5-1978, f. & ef. 5-9-78; EFSC 4-1981, f. & ef. 3-25-81; EFSC 10-1981, f. & ef. 12-28-81; EFSC 6-1986, f. & ef. 9-12-86; EFSC 2-1992, f. & cert. ef. 8-28-92, Renumbered from 345-010-0026; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 2-2000, f. & cert. ef. 11-20-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-001-0010

Definitions

In this chapter, the following definitions apply unless the context requires otherwise or a term is specifically defined within a division or a rule:

(1) “Adjusted to ISO conditions” as defined in ORS 469.503(2)(e).

(2) “Analysis area” means the area or areas specifically described in the project order issued under 345-015-0160(1), containing resources that the proposed facility may significantly affect. The analysis area is the area for which the applicant shall describe the proposed facility’s impacts in the application for a site certificate. A proposed facility might have different analysis areas for different types of resources. For the purpose of submitting an application for a site certificate in an expedited review granted under OAR 345-015-0300 or OAR 345-015-0310, the analysis areas are the study areas defined in this rule, subject to modification in the project order.

(3) “Applicant” as defined in ORS 469.300 or, if an application has not been submitted, a person who has submitted, or intends to submit, a notice of intent or a request for expedited review.

(4) “Associated transmission lines” as defined in ORS 469.300.

(5) “Average electric generating capacity” as defined in ORS 469.300.

(6) “Background radiation” means the direct radiation (gamma) and concentrations of potential radionuclide contaminants in construction materials and the environment in the vicinity of the plant not associated with the nuclear operation and retirement of the facility. Background shall be determined as follows:

(a) For direct radiation, the results of any background measurements taken prior to operation of the facility shall be provided and 6 to 10 measurements shall be taken in areas in the vicinity of the site with materials and/or geological formations representative of the site that have not been affected by the operation and retirement of the facility. Background shall be calculated at the average and at the 95% confidence level.

(b) Environmental samples shall be taken for soil, sediment, water, and other materials present at the facility site that could have been affected by facility operations and retirement. Measurements for these samples shall be calculated at the average and 95% confidence levels, based on 6 to 10 measurements. Background environmental samples shall be taken at locations on site or in the immediate vicinity of the site which are unaffected by plant operations. Background shall be calculated at the average and 95% confidence levels, based on 6 to 10 measurements at each location.

(c) For construction material such as concrete, asphalt, block, brick and other materials used to construct the buildings and systems at the site, representative samples of materials unaffected by site operations shall be selected and surveyed. Six to ten samples of each material shall be taken to determine the level of naturally occurring and artificially induced concentrations of naturally occurring radioactivity present. Measurements shall include direct radiation (beta-gamma and alpha), wipes and qualitative and quantitative laboratory analyses. Concentrations of fission and activation products from historical fallout shall be characterized as well.

(d) All measurements shall be made using appropriate instruments, properly calibrated, and in sufficient number to determine compliance with requirements.

(7) “Base load gas plant” as defined in ORS 469.503(2)(e).

(8) “Carbon dioxide equivalent” as defined in ORS 469.503(2)(e).

(9) “Certificate holder” means the person to whom a site certificate has been granted by the Council pursuant to this chapter.

(10) “Chair” means the chairman or chairwoman of the Energy Facility Siting Council.

(11) “Committed firm energy and capacity resources” means generating facilities or power purchase contracts that are assured to be available to the energy supplier over a defined time period. Committed firm energy and capacity resources include existing generating facilities, existing power purchase contracts and planned generating facilities that sponsors have made firm commitments to develop.

(12) “Construction” as defined in ORS 469.300.

(13) “Corridor” means a continuous area of land not more than one-half mile in width and running the entire length of a proposed transmission line or pipeline. “Micrositing corridor” is defined below in this rule.

(14) “Council” means the Energy Facility Siting Council established under ORS 469.450.

(15) “Council Secretary” means the person designated by the Director of the Oregon Department of Energy to serve as secretary to the Council.

(16) “Department” means the Office of Energy or the Department of Energy created under ORS 469.030.

(17) “Direct cost” means the discounted sum of all monetary costs to the ultimate consumer over the lifetime of the facility or resource plan or resource strategy.

(18) “Energy facility” means an energy facility as defined in ORS 469.300, including a small generating plant for which an applicant must have a site certificate according to OAR 345-001-0210.

(19) “Energy supplier” means:

(a) A retail electric utility, a federal power marketing agency, or a local gas distribution company, or

(b) A person or public agency generating electric energy for its own consumption, lawfully purchasing electric energy directly from a generator for its own consumption, or transmitting or distributing natural or synthetic gas from an energy facility for its own consumption.

(20) “Existing corridor,” as used in ORS 469.300 and ORS 469.442, means the right-of-way of an existing transmission line, not to exceed 100 feet on either side of the physical center line of the transmission line or 100 feet from the physical center line of the outside lines if the corridor contains more than one transmission line.

(21) “Facility” as defined in ORS 469.300 or a small generating plant for which an applicant must have a site certificate according to OAR 345-001-0210 together with any related or supporting facilities.

(22) “Facility substantially similar to the proposed facility” means:

(a) A facility that uses the same fuel and substantially similar technology, that has substantially the same in-service date, and that has a direct cost not substantially greater than that of the proposed facility; or

(b) A facility that is demonstrated to provide as good a mix of reliability, compatibility with the power system, strategic flexibility, environmental impact and direct cost as the proposed facility taking into account reasonable trade-offs among such factors.

(23) “Fossil fuel” means natural gas, petroleum, coal and any form of solid, liquid or gaseous fuel derived from such materials that is used to produce useful energy.

(24) “Fossil-fueled power plant” as defined in ORS 469.503(2)(e).

(25) “Fuel chargeable to power heat rate” means the net heat rate of electric power production during the first twelve months of commercial operation. A fuel chargeable to power heat rate is calculated with all factors adjusted to the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate using the formula, FCP = (FI - FD)/ P, where:

(a) FCP = Fuel chargeable to power heat rate.

(b) FI = Annual fuel input to the facility applicable to the cogeneration process in British thermal units (higher heating value).

(c) FD = Annual fuel displaced in any industrial or commercial process, heating, or cooling application by supplying useful thermal energy from a cogeneration facility instead of from an alternate source, in British thermal units (higher heating value). (d) P = Annual net electric output of the cogeneration facility in kilowatt-hours.

(26) “Generating facility” as defined in ORS 469.503(2)(e).

(27) “Greenhouse gas” as defined in ORS 469.503(2)(e).

(28) “Gross carbon dioxide emissions” as defined in ORS 469.503(2)(e). The Council shall measure the gross carbon dioxide emissions of a fossil-fueled power plant on a new and clean basis. For nongenerating energy facilities that emit carbon dioxide, the Council shall measure the gross carbon dioxide emissions as described in OAR 345-024-0620(1).

(29) “High efficiency cogeneration facility” means an energy facility, except coal and nuclear power plants, that sequentially produces electrical and useful thermal energy from the same fuel source and under average annual operating conditions:

(a) Has a nominal electric generating capacity of less than 50 megawatts and the fuel chargeable to power heat rate value is not greater than 5550 Btu per kilowatt-hour (higher heating value); or

(b) Has a nominal electric generating capacity of 50 megawatts or more and the fuel chargeable to power heat rate value is not greater than 6000 Btu per kilowatt-hour (higher heating value).

(30) “Land use approval” means a final quasi-judicial decision or determination made by a local government that:

(a) Applies existing comprehensive plan provisions or land use regulations to a proposed facility;

(b) Amends a comprehensive plan map or zoning map to accommodate a proposed facility;

(c) Amends comprehensive plan text or land use regulations to accommodate a proposed facility;

(d) Applies the statewide planning goals to a proposed facility; or

(e) Takes an exception to the statewide planning goals adopted by the Land Conservation and Development Commission for a proposed facility.

(31) “Local government” as defined in ORS 469.300.

(32) “Micrositing corridor” means a continuous area of land within which construction of facility components may occur, subject to site certificate conditions.

(33) “Mitigation” means taking one or more of the following actions listed in order of priority:

(a) Avoiding the impact altogether by not taking a certain action or parts of an action;

(b) Minimizing impacts by limiting the degree or magnitude of the action and its implementation;

(c) Partially or completely rectifying the impact by repairing, rehabilitating or restoring the affected environment;

(d) Reducing or eliminating the impact over time by preservation and maintenance operations during the life of the action by monitoring and taking appropriate corrective measures;

(e) Partially or completely compensating for the impact by replacing or providing comparable substitute resources or environments; or

(f) Implementing other measures approved by the Council.

(34) “Natural gas” means gas as defined in ORS 520.005.

(35) “Natural gas fired facility” means an energy facility that is intended to be fueled by natural gas except for infrequent periods when the natural gas supply is interrupted, during which an alternate fuel may be used. Such alternate fuel use shall not exceed 10 percent of expected fuel use in British thermal units, higher heating value on an annual basis.

(36) “Net carbon dioxide emissions” as defined in ORS 469.503(2)(e).

(37) “Net electric power output” means the electric power produced or capacity made available for use. Calculation of net electric power output subtracts losses from on-site transformers and power used for any on-site electrical loads from gross capacity as measured or estimated at the generator terminals for each generating unit.

(38) “New and clean basis” means the average carbon dioxide emissions rate per hour and net electric power output of the energy facility, without degradation. The site certificate holder shall determine the new and clean basis:

(a) By a 100-hour test at full power that the site certificate holder completes during the first 12 months of commercial operation of the energy facility, unless the Council specifies a different testing period for a non-base load power plant (or power augmentation) or a nongenerating energy facility. A 100-hour test performed for purposes of the certificate holder’s commercial acceptance of the facility may suffice in lieu of testing after beginning commercial operation;

(b) With the results adjusted for the average annual site condition for temperature, barometric pressure and relative humidity and use of alternative fuels unless the Council specifies that the results for a non-base load power plant (or power augmentation) or a nongenerating energy facility be adjusted for the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate;

(c) Using a rate of 117 pounds of carbon dioxide per million Btu of natural gas fuel (higher heating value); and,

(d) Using a rate of 161 pounds of carbon dioxide per million Btu of distillate fuel (higher heating value), if such fuel use is proposed by the applicant.

(e) Notwithstanding subsection (a) and including subsections (b) through (d), for a facility that employs major power generating equipment that has previously been used, the new and clean basis shall mean average carbon dioxide emissions rate and net electric power output for the first use of the equipment at the site, as determined by historical data from the previous usage or by testing on site.

(39) “Nominal electric generating capacity” as defined in ORS 469.300.

(40) “Non-base load power plant” means a fossil-fueled generating facility that is limited by the site certificate to an average number of hours of operation per year of not more than 6,600 hours. For a non-base load power plant designed to operate at variable loads, the facility’s annual hours of operation are determined by dividing the actual annual electric output of the facility in megawatt-hours by the facility’s nominal electric generating capacity in megawatts. The Council shall assume a 30-year life for the plants for purposes of determining gross carbon dioxide emissions, unless the applicant requests and the Council approves a shorter operational life in the site certificate. If the Council approves a shorter operational life, the certificate holder shall operate the facility for no longer than the approved operational life or, before the expiration of the approved operational life, shall request an amendment of the site certificate to extend the operational life.

(41) “Nongenerating facility” as defined in ORS 469.503(2)(e).

(42) “Office of Energy” and “Office” mean the Oregon Office of Energy and the Oregon Department of Energy.

(43) “Offset” as defined in ORS 469.503(2)(e).

(44) “Offset funds” means the amount of funds determined by the Council to satisfy the applicable carbon dioxide emissions standard pursuant to OAR 345-024-0560(3), 345-024-0600(3) or OAR 345-024-0630(2) and (4).

(45) “Owner” means owner or lessee under a capital lease.

(46) “Permit” means any permit, license, certificate or other approval required by federal law, state statute, state administrative rule or local government ordinance.

(47) “Person” as defined in ORS 469.300.

(48) “Power augmentation” means technologies that increase the capacity and the heat rate of the plant above the capacity and heat rate of the base load gas plant. These include, but are not limited to, duct burning and some forms of steam augmentation.

(49) “Project order” as defined in ORS 469.300.

(50) “Qualified organization” means an organization that:

(a) Is exempt from federal taxation under section 501(c)(3) of the Internal Revenue Code as amended and in effect on December 31, 1996;

(b) Either is incorporated in the State of Oregon or is a foreign corporation authorized to do business in the State of Oregon;

(c) Has in effect articles of incorporation that:

(A) Require that offset funds received under OAR 345-024-0710(3) are used for offsets ;

(B) Require that decisions on the use of the offset funds are made by a decision-making body composed of seven voting members of which three are appointed by the Council, three are Oregon residents appointed by the Bullitt Foundation or an alternative environmental nonprofit organization named by the body, and one is appointed by the applicants for site certificates that are subject to OAR 345-024-0550, OAR 345-024-590, and OAR 345-024-0620 and the holders of such site certificates; and

(C) Require nonvoting membership on the decision-making body for holders of site certificates that have provided funds not yet disbursed under OAR 345-024-0710(3);

(d) Has made available on an annual basis, beginning after the first year of operation, a signed opinion of an independent certified public accountant stating that the qualified organization’s use of funds pursuant to ORS 469.503 conforms with generally accepted accounting procedures except that the qualified organization shall have one year to conform with generally accepted accounting principles in the event of a nonconforming audit;

(e) Has to the extent applicable, except for good cause, entered into contracts obligating at least 60 percent of the offset funds to implement offsets within two years after the commencement of construction of the facility; and

(f) Has to the extent applicable, except for good cause, complied with OAR 345-024-0710(3).

(51) “Related or supporting facilities” as defined in ORS 469.300. The Council interprets the terms “proposed to be built in connection with” as meaning that a structure is a related or supporting facility if it would not be built but for construction or operation of the energy facility. “Related or supporting facilities” does not include any structure existing prior to construction of the energy facility, unless such structure must be significantly modified solely to serve the energy facility.

(52) “Reviewing agency” means any of the following officers, agencies or tribes:

(a) Department of Environmental Quality.

(b) Water Resources Commission and the Water Resources Director through the Water Resources Department.

(c) Fish and Wildlife Commission through the Department of Fish and Wildlife.

(d) State Geologist.

(e) Department of Forestry.

(f) Public Utility Commission.

(g) Department of Agriculture.

(h) Department of Land Conservation and Development.

(i) Pacific Northwest Electric Power and Conservation Planning Council.

(j) Office of State Fire Marshal.

(k) Department of State Lands.

(l) State Historic Preservation Office.

(m) Any other agency identified by the Department of Energy.

(n) Any tribe identified by the Legislative Commission on Indian Services as affected by the proposed facility.

(o) The governing body of any incorporated city or county in Oregon within the study area as defined in OAR 345-001-0010 for impacts to public services.

(p) Any special advisory group designated by the Council under ORS 469.480.

(q) The federal land management agency with jurisdiction if any part of the proposed site is on federal land.

(53) “Significant” means having an important consequence, either alone or in combination with other factors, based upon the magnitude and likelihood of the impact on the affected human population or natural resources, or on the importance of the natural resource affected, considering the context of the action or impact, its intensity and the degree to which possible impacts are caused by the proposed action. Nothing in this definition is intended to require a statistical analysis of the magnitude or likelihood of a particular impact.

(54) “Site” as defined in ORS 469.300. “Energy facility site” means all land upon which an energy facility is located or proposed to be located. “Related or supporting facilities site” means all land upon which related or supporting facilities for an energy facility are located or proposed to be located.

(55) “Site boundary” means the perimeter of the site of a proposed energy facility, its related or supporting facilities, all temporary laydown and staging areas and all corridors and micrositing corridors proposed by the applicant.

(56) “Site certificate” as defined in ORS 469.300.

(57) “Special nuclear material” means plutonium, uranium-233 or uranium enriched in the isotope 233 or in the isotope 235.

(58) “Strategic flexibility” means the value of a resource as part of a strategy to manage variance in costs or risks caused by future uncertainty.

(59) “Study area” means an area defined in this rule. Except as specified in subsections (f) and (g), the study area is an area that includes all the area within the site boundary and the area within the following distances from the site boundary:

(a) For impacts to threatened and endangered plant and animal species, 5 miles.

(b) For impacts to scenic resources and to public services, 10 miles.

(c) For land use impacts and impacts to fish and wildlife habitat, one-half mile.

(d) For impacts to recreational opportunities, 5 miles.

(e) For impacts to protected areas described in OAR 345-022-0040, 20 miles.

(f) The distance stated in subsection (a) above does not apply to surface facilities related to an underground gas storage reservoir.

(g) The distances stated in subsections (a) and (d) above do not apply to pipelines or transmission lines.

(60) “Substantial loss of steam host” means the thermal energy user associated with a high efficiency cogeneration facility has made such long-term changes in its manner and magnitude of operation as to result in the loss of one or more work shifts for at least a year, accompanied by at least a 30 percent resultant reduction in the use of thermal energy.

(61) “Substantial loss of fuel use efficiency” means an increase in the fuel chargeable to power heat rate at a high efficiency cogeneration facility to greater than 7000 Btu per kilowatt-hour (higher heating value), or reduction of the fraction of energy output going to the thermal energy user associated with the facility to less than 20 percent, as a result of a substantial loss of steam host. Substantial loss of fuel use efficiency does not include efficiency losses due to equipment wear or condition.

(62) “Surface facilities related to an underground gas storage reservoir” means structures or equipment adjacent to and associated with an underground gas storage reservoir that are proposed to be built in connection with an underground gas storage reservoir and include, but are not limited to:

(a) Facilities such as stripping plants, main line dehydration stations, offices, warehouses, equipment shops, odorant storage and injection equipment and compressors;

(b) Pipelines, such as gathering lines and liquid collection lines; and

(c) Roads and road maintenance equipment housing at the reservoir site.

(63) “Thermal power plant” as defined in ORS 469.300.

(64) “Total energy output” means the sum of useful thermal energy output and useful electrical energy output.

(65) “Underground gas storage reservoir” as defined in ORS 469.300.

(66) “Useful thermal energy” means the verifiable thermal energy used in any industrial or commercial process, heating or cooling application;

(67) “Utility” as defined in ORS 469.300.

(68) “Vice-chair” means the vice-chairman or vice-chairwoman of the Energy Facility Siting Council.

(69) “Waste disposal facility” as defined in ORS 469.300.

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.300-570, 469.590-619 & 469.992
Hist.: EFSC 1-1980, f. & ef. 2-28-80; EFSC 1-1981, f. & ef. 1-19-81; EFSC 2-1981, f. & ef. 1-19-81; EFSC 8-1981, f. & ef. 10-29-81; EFSC 4-1982, f. & ef. 5-3-82; EFSC 4-1986, f. & ef. 9-5-86; EFSC 7-1986, f. & ef. 9-18-86; EFSC 2-1992, f. & cert. ef. 8-28-92; EFSC 1-1993, f. & cert. ef. 1-15-93; Renumbered from 345-079-0025, 345-100-0025, 345-111-0020 & 345-125-0025; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2009, f. & cert. ef. 11-24-09; EFSC 1-2012, f. & cert. ef. 5-15-12; EFSC 1-2012, f. & cert. ef. 5-15-12

345-001-0050

Public Records Availability and Fees for Copying

(1) All public records of the Council that are retained by the Department of Energy are available for public inspection and copying at the Department during usual business hours, except for records that the Department has determined to be exempt or conditionally exempt from disclosure in accordance with ORS Chapter 192. Except as protected under ORS 357.875, any permanent record of the Council kept by the State Archivist can be inspected at the State Archive building, subject to applicable rules of the Secretary of State, Archives Division.

(2) To inspect Council records a person shall submit to the Department a written request containing the following information:

(a) Name, address, e-mail address and telephone number of the person requesting the record.

(b) A specific description of the record requested.

(3) After receiving a request to inspect a Council record, the Department shall notify the requesting person whether the record is stored on or off the premises of the Department or is kept by the State Archivist.

(4) If the requested record is stored on the premises of the Department, the person who requested the record may inspect it on the premises without charge.

(5) If the requested record is stored off the premises of the Department, the Department shall charge for the staff time necessary to make the record available for inspection on the premises of the Department.

(6) A person who is receiving a copy of a public record or information from a public record shall pay for the Department’s actual cost for:

(a) Staff time necessary to locate and handle the records, to delete material exempt from disclosure and to supervise the inspection by the requester;

(b) Producing the copy or the information; and

(c) Other supplies or services necessary to furnish the copy or information.

(7) The person requesting copies of records shall pay the fees described in section (6) in advance, except that government agencies or parties in proceedings before the Council need not pay before delivery of the copies.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.560
Hist.: EFSC 2-1992, f. & cert. ef. 8-28-92; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-011-0020

Agendas for Regular Meetings

(1) The Council Secretary shall prepare an agenda for each regular Council meeting after consulting with the chair. On the agenda, the Secretary shall specify all matters scheduled to come before the Council at the meeting and shall identify the proponent of agenda items scheduled at the request of a member of the public as described in OAR 345-011-0035.

(2) On the agenda, the Secretary may include a consent calendar, identifying items that the Secretary considers to be routine, such as minutes of previous meetings and personnel recognitions, which will be acted upon without public discussion. However, if a Council member objects to an item on the consent calendar, it will be removed from the consent calendar and placed on the regular agenda for discussion.

(3) The Secretary shall include on each agenda a notice that time will be reserved at each meeting for the presentation of concerns by interested citizens who wish to address the Council regarding any item within the Council’s jurisdiction except matters that are closed to public comment as specified in the notice. The chair shall establish the duration of the time for public comment and may lengthen or shorten it at the Council meeting as the length of the meeting and timing and duration of other Council business dictate.

(4) The Secretary shall send the agenda to Council members by regular mail or email at least one week before a regular meeting and shall include draft minutes of previous meetings, as available. The Secretary shall send the agenda to each person or organization on the Council’s general mailing list by regular mail or email. The “general mailing list” is the list of persons who have requested all Council meeting and facility siting mailings.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 192.640, 469.460 & 469.470
Hist.: EFSC 7-1980, f. & ef. 10-9-80; EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-011-0050

Council Files

The Council Secretary shall maintain minutes of all Council meetings, Council committee meetings and other records of the Council.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 192.640 & 469.460
Hist.: EFSC 7-1980, f. & ef. 10-9-80; EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0014

Contested Case Notices

(1) The Department shall issue notices for Council contested case proceedings as provided in OAR 137-003-0001 and shall include in the notices:

(a) A date by which persons must request party or limited party status.

(b) The date of the pre-hearing conference.

(c) The time and place of the hearing.

(2) In addition to the requirements of section (1), for a contested case notice on a proposed order as described in OAR 345-015-0230 or following a Council decision to grant a contested case hearing under OAR 345-015-0310, the Department shall include in the notice a statement that participation as a party or limited party in the contested case proceeding and the opportunity to raise any issue are subject to the limitations described in OAR 345-015-0016.

(3) The Department shall send a contested case notice by registered or certified mail to the following persons:

(a) For a contested case notice on a proposed order as described in OAR 345-015-0230, to the applicant and to all persons who commented in person or in writing on the record of the public hearing described in OAR 345-015-0220.

(b) Following the Council’s decision to grant a contested case proceeding on a proposed order on an application for a site certificate for a special criteria facility, to the applicant and to all persons who commented in person or in writing on the record of the public hearing on the proposed order described in OAR 345-015-0320.

(c) Following a Council decision to grant a contested case proceeding on a proposed site certificate amendment under OAR 345-027-0070, 345-027-0080 or 345-027-0090, to the certificate holder and to all persons who requested a contested case proceeding as described in OAR 345-027-0070(6) or 345-027-0080(5).

(d) For Council contested case proceedings described under OAR 345-029-0070, 345-029-0100 or 345-060-0004, to persons who have an interest or represent a public interest in the outcome of the proceeding.

(4) The Department shall request that the applicant notify the hearing officer and the Department, by the date described in subsection (1)(a), of any issues the applicant desires to raise in the contested case proceedings described in subsections (3)(a) and (b).

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 183.415, 469.085, 469.370, 469.405, 469.440, 469.605, 469.615 & 469.992
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0085

Hearing Officer’s Proposed Contested Case Order

(1) The hearing officer shall allow any party, including any limited party, to propose site certificate conditions that the party believes are necessary or appropriate to implement the policy of ORS 469.310 or to meet the requirements of any other applicable statute, administrative rule or local government ordinance. Parties shall submit proposed site certificate conditions to the hearing officer in writing according to a schedule set by the hearing officer.

(2) In a contested case proceeding on an application for a site certificate or on a proposed site certificate amendment, any party or limited party may present evidence relating to the appropriateness, scope or wording of any other party’s proposed site certificate conditions and may present written proposed findings of fact, briefs and other argument concerning proposed conditions.

(3) After the hearing in a contested case proceeding on an application for a site certificate or on a proposed site certificate amendment, the hearing officer shall issue a proposed contested case order stating the hearing officer’s findings of fact, conclusions of law, and recommended site certificate conditions on the issues in the contested case. The hearing officer shall serve the proposed order on all parties and limited parties. In the proposed order, the hearing officer shall include recommended resolutions of objections to the local land use record, if any. The hearing officer’s recommendations are part of the decision record for the application but are not part of the Council’s order.

(4) After the hearing in a contested case proceeding on any matter other than an application for a site certificate or proposed site certificate amendment, the hearing officer shall issue a proposed order stating the hearing officer’s findings of fact and conclusions of law. The hearing officer shall serve the proposed order on all parties and limited parties.

(5) Parties and limited parties may file exceptions to the proposed order within the time set by the hearing officer, not to exceed 30 days after the hearing officer issues the proposed order. A party filing exceptions shall serve a copy of the exceptions on all other parties and limited parties. In an exception, the party shall specifically identify the finding of fact, conclusion of law or, in contested case proceedings on an application for a site certificate or a proposed site certificate amendment, recommended site certificate condition to which the party excepts and shall state the basis for the exception.

(6) Parties and limited parties may file responses to exceptions within the time set by the hearing officer, not to exceed 15 days after the time set for filing exceptions. A party filing responses to exceptions shall serve a copy of the responses to exceptions on all other parties and limited parties.

(7) After the period for filing responses to exceptions, the Council shall issue a final order. The Council may adopt, modify or reject the hearing officer’s proposed order.

(8) Following a contested case proceeding on an application for a site certificate, the Council, in its final order, shall either grant or deny issuance of a site certificate. If the Council grants issuance of a site certificate, the Council shall issue a site certificate. The site certificate becomes effective upon execution by the Council and by the applicant. However, for purposes of identification, the Department may refer to a site certificate by the date of the Council action.

(9) Following a contested case proceeding on a proposed site certificate amendment, the Council, in its final order, shall either grant or deny issuance of an amended site certificate. If the Council grants issuance of an amended site certificate, the Council shall issue an amended site certificate. The amended site certificate becomes effective upon execution by the Council and by the applicant. However, for purposes of identification, the Department may refer to a site certificate by the date of the Council action.

(10) The Council shall issue a site certificate or amended site certificate in duplicate counterpart originals and each counterpart, upon signing, will have the same effect.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 183.415, 469.370, 469.405, 469.440, 469.605, 469.615 & 469.992
Hist.: EFSC 8-1980, f. & ef. 10-31-80; EFSC 6-1986, f. & ef. 9-12-86; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-015-0053; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0110

Public Notice of a Notice of Intent

(1) After receiving a notice of intent (NOI), the Department of Energy shall issue a public notice of the NOI by:

(a) Sending notice by mail or email to persons on the Council’s general mailing list as defined in OAR 345-011-0020 and any special mailing list set up for the proposed project.

(b) Sending notice by mail to the owners of property whose names and addresses the applicant has supplied as required by OAR 345-020-0011.

(c) Except as provided in subsection (d), publishing notice in a newspaper of general circulation available in the vicinity of the proposed facility; and

(d) If the energy facility is a transmission line or a pipeline or has, as a related or supporting facility, a transmission line or pipeline that, by itself, is an energy facility under the definition in ORS 469.300, publishing notice in one or, if possible, two newspapers of general circulation in the vicinity of the proposed facility.

(2) In the public notice of the NOI, the Department shall include the following information:

(a) A description of the proposed facility.

(b) The location of the site of the proposed facility.

(c) The date when the applicant expects to submit an application for a site certificate.

(d) A brief description of the Council’s review process, including an explanation of the difference between the informational meetings described in OAR 345-015-0130 and 345-015-0190(10) and the public hearing described in OAR 345-015-0220.

(e) An explanation that the applicant may choose to meet the Council’s land use standard, OAR 345-022-0030, by obtaining local land use approval from the affected local government and that, if the applicant chooses to obtain local land use approval, any person interested in land use issues should participate in that affected local government’s land use process if it is not yet complete.

(f) The date, time and location of any informational meeting on the NOI that the Department has scheduled or an explanation of how interested persons may request an informational meeting. If the Department has scheduled an informational meeting, the Department shall state in the notice that public comments on the NOI may be given in person at the meeting.

(g) A explanation that written comments on the NOI must be submitted by a specified date and may be submitted by regular mail, email or fax.

(h) The name, address, email address and telephone number of the Department’s project officer to contact for additional information.

(i) If the applicant has identified one or more proposed corridors in Exhibit D of the NOI, as required by OAR 345-020-0011(1)(d):

(A) An explanation that the corridor proposed by the applicant in the NOI is subject to change and that the applicant may propose adjustments to the proposed corridor(s) in the application;

(B) An explanation that the applicant may present adjustments to the proposed corridor(s) at the informational meeting; and

(C) An explanation that, in selecting one or more corridors for analysis in the application for a site certificate, the applicant shall consider public comments on the corridor(s) proposed in the NOI and on any corridor adjustments the applicant presents at the informational meeting.

(3) If the Department learns that an applicant has applied for local land use approval, the Department shall post a notice of the local land use proceeding on its website.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.330
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0120

Memorandum on a Notice of Intent

The Department of Energy shall prepare a memorandum to accompany the copies of the notice of intent (NOI) distributed as described in OAR 345-020-0040. In the memorandum, the Department shall:

(1) Request comments from the reviewing agency by a specified date.

(2) Request the following information:

(a) The name, address and telephone number of the agency contact person assigned to review the application.

(b) Comments on aspects of the proposed facility that are within the particular responsibility or expertise of the reviewing agency.

(c) Recommendations regarding the size and location of analysis area(s).

(d) A list of studies that should be conducted to identify potential impacts of the proposed facility and mitigation measures.

(e) If the applicant has identified one or more proposed corridors in Exhibit D of the NOI as required by OAR 345-020-0011(1)(d), a discussion of the relative merits of the corridors described in the NOI and recommendations, if any, on the selection of a corridor.

(f) A list of statutes, administrative rules and local government ordinances administered by the agency that might apply to construction or operation of the proposed facility and a description of any information needed for determining compliance.

(g) A list of any permits administered by the agency that might apply to construction or operation of the proposed facility and a description of any information needed for reviewing a permit application.

(h) For tribes affected by the proposed facility, a list of tribal codes that the tribe recommends to the Council for its review of the application and specific information regarding the proposed facility or study areas described in the NOI that is necessary for determining compliance with those tribal codes.

(3) State the date, location, agenda and purpose of any informational meeting that the Department has scheduled on the NOI and encourage the recipient to attend and participate in the informational meeting.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.330
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0160

Project Order

(1) Following the review of a notice of intent or, in the case of an expedited review, following receipt of a preliminary application for a site certificate, the Department of Energy shall send a project order to the applicant establishing the following:

(a) All state statutes and administrative rules containing standards or criteria that must be met for the Council to issue a site certificate for the proposed facility, including applicable standards of Divisions 22, 23 and 24 of this chapter.

(b) All local government ordinances applicable to the Council’s decision on the proposed facility.

(c) All application requirements in OAR 345-021-0010 applicable to the proposed facility.

(d) All state and local permits necessary to the construction and operation of the proposed facility and the name of each agency with the authority to issue such permits.

(e) Any other data and information that must be included in the application for a site certificate to allow the Council to determine whether the proposed facility will comply with applicable statutes, administrative rules and local government ordinances.

(f) The analysis area(s) for the proposed facility.

(g) Public concerns that address matters within the jurisdiction of the Council that the applicant shall consider and discuss in the application for a site certificate, based on comments the Department has received in writing or at any informational meeting held under OAR 345-015-0130.

(h) If the applicant has identified one or more proposed corridors in Exhibit D of the notice of intent as required by OAR 345-020-0011(1)(d), any adjustments to the corridor(s) that the applicant shall evaluate in the corridor selection assessment described in OAR 345-021-0010(1)(b).

(i) If the applicant chooses to demonstrate need for a proposed electric transmission line, natural gas pipeline, or liquefied natural gas storage facility under the economically reasonable rules, OAR 345-023-0030 and OAR 345-023-0040, any alternatives to construction and operation of the proposed facility that the applicant must evaluate in the application in addition to the alternatives described in OAR 345-021-0010(1)(n)(F) or (G).

(j) Except in the case of an expedited review granted under OAR 345-015-0300 or 345-015-0310, the expiration date of the notice of intent, according to OAR 345-020-0060(1).

(2) In determining the application and study requirements to be included in the project order, the Department shall consider the size and type of proposed facility and significant potential impacts of the proposed facility.

(3) The Council or the Department may amend the project order at any time.

(4) The project order is not a final order.

(5) Except in the case of an expedited review granted under OAR 345-015-0300 or 345-015-0310, the Department shall, to the extent practicable, issue the project order within 140 days following the date of submission of the notice of intent.

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.330 & 469.370
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0180

Agency Memorandum on a Site Certificate Application

The Department of Energy shall prepare a memorandum to accompany the copies of the preliminary application distributed as described in OAR 345-021-0050. In the memorandum, the Department shall:

(1) Request the recipient to return comments or recommendations described in OAR 345-021-0050(2) to the Department by a specified date;

(2) Describe the matters to be covered in the comments or recommendations as set forth in OAR 345-021-0050(2) and (4);

(3) Explain that the recipient’s written comments, recommendations and reports are part of the decision record for the application for a site certificate;

(4) State that the reviewing agency must comment in person or in writing on the record of the public hearing described in OAR 345-015-0220 to preserve the right to participate in the contested case proceeding as a party, limited party or interested agency and the right to appeal the Council’s final decision; and

(5) For any special advisory group designated by the Council under ORS 469.480, request that the special advisory group recommend to the Council the applicable substantive criteria and explain that, as required by ORS 469.504(5), if the special advisory group does not recommend applicable substantive criteria by the specified date, the Council may either determine and apply the applicable substantive criteria or determine compliance with the statewide planning goals under ORS 469.504(1)(b)(B) or (C).

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.350 & 469.504
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0190

Determination of Completeness

(1) Until the Department of Energy determines the application to be complete, it is a preliminary application. Within 60 days after receipt of a preliminary application for a site certificate, the Department shall notify the applicant whether the application is complete. In the notification, the Department shall:

(a) State that the application is complete and state the date of filing;

(b) State that the application is incomplete, describe any information needed to complete the application to the extent known to the Department at the time of the notification, ask the applicant to submit the needed information by the deadline described in section (4) and estimate the additional time the Department will need to make a determination of completeness; or

(c) Explain the reasons why the Department cannot determine completeness and estimate the additional time the Department will need to make a determination of completeness.

(2) If the Department does not notify the applicant as described in section (1), the application is deemed complete and filed 60 days after receipt of the preliminary application. Otherwise, the application is complete as determined under section (5) and the date of filing is the date determined under section (6).

(3) If the Department finds that the applicant did not give adequate consideration to public concerns about the corridors the applicant identified in Exhibit D of the notice of intent or corridor adjustments presented at the informational hearing described in OAR 345-015-0130, the Department may find the application incomplete and notify the applicant as described under section (1)(b).

(4) The Department may specify a date by which the applicant must submit additional information needed to complete the application. If follow-up requests for additional information are needed, the Department may specify dates by which the applicant must submit the information. At the request of the applicant, the Department may allow additional time for submission of the information. If the applicant does not submit the information by the deadline specified by the Department, including any allowed extension, the Council may reject the application. The rejection of an application is subject to appeal under ORS 469.403(3).

(5) An application is complete when the Department finds that the applicant has submitted information adequate for the Council to make findings or impose conditions on all applicable Council standards. The Department may find that the application is complete without requiring the applicant to submit all information described under OAR 345-021-0000 and 345-021-0010. The Department shall notify the applicant when the Department finds that the application is complete and, if needed, shall request the application supplement described in OAR 345-021-0055.

(6) The date of filing is the date the Department receives the application supplement described in OAR 345-021-0055 or, if no supplement is needed, the date the Department notifies the applicant that the application is complete.

(7) The Department shall inform the public that the application is complete by publishing notice in a newspaper of general circulation available in the vicinity of the proposed facility. In addition, the Department shall send notice by mail or email to persons on the Council’s general mailing list as defined in OAR 345-011-0020 and any special mailing list set up for the proposed facility and to the property owners listed in Exhibit F of the application.

(8) In notices described in section (7), the Department shall include the following information:

(a) A description of the proposed facility.

(b) The location of the site of the proposed facility

(c) The date of filing.

(d) A description of the procedure for review of the application, including the date, time and location of any informational meeting that has been scheduled on the application and an explanation of the difference between the informational meeting and the public hearing described in OAR 345-015-0220.

(e) Addresses of locations where the public may review copies of the application.

(f) The name, address and telephone number of the Department of Energy project officer to contact for more information.

(g) If the applicant has elected to seek local land use approvals pursuant to ORS 469.503(2)(a), a statement of the status of the land use approvals, and the name, address and telephone number of the local governments(s) making or having made the land use determination.

(h) If the proposed facility is an energy facility that must comply with a carbon dioxide emissions standard adopted by the Council, a statement of the applicant’s proposed means of compliance with the applicable carbon dioxide emissions standard.

(9) After a determination that an application is complete, the applicant shall submit additional information to the Department if the Department identifies a need for that information during its review of the application. Submission of such information does not constitute an amendment of the application.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.350
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0220

Public Hearing on the Draft Proposed Order

(1) After the issuance of the draft proposed order described in OAR 345-015-0210, the Council or its hearing officer shall conduct at least one public hearing on the draft proposed order in the vicinity of the site of the proposed facility. The public hearing is not a contested case hearing. If there is more than one public hearing, the “close of the record of the public hearing” means the close of the record of the final public hearing.

(2) The Department of Energy shall, at least 20 days before the hearing:

(a) Submit notice for publication in a newspaper of general circulation available in the vicinity of the proposed facility.

(b) Send notice by mail or email to persons on the Council’s general mailing list as defined in OAR 345-011-0020 and to any special mailing list set up for the proposed project, including a mailing list made up of those persons listed in Exhibit F of the site certificate application as updated by the applicant upon the request of the Department.

(3) In the notices described in subsections (2)(a) and (2)(b), the Department shall include:

(a) The date, time and location of the public hearing(s).

(b) A description of the facility and the facility’s general location.

(c) The name, address, email address and telephone number of the Department’s project officer to contact for additional information.

(d) The addresses of locations where the public may inspect copies of the complete application and, if the application is available online, the website where the application can be found.

(e) The website where the draft proposed order can be found.

(f) The deadline for the public to submit written comments to be included in the record of the public hearing and a statement that such comments should be submitted to the presiding officer in care of the Department’s project officer.

(g) A statement that to raise an issue on the record of the public hearing, a person must raise the issue in person at the public hearing or in a written comment submitted after the date of the notice and received by the Department before the deadline.

(h) A statement that failure to raise an issue in person or in writing on the record of the public hearing with sufficient specificity to afford the decision maker an opportunity to respond to the issue precludes consideration of the issue in a contested case.

(i) A statement that to raise an issue with sufficient specificity, a person must present facts that support the person’s position on the issue.

(j) A statement that the Council will not accept or consider any further public comment on the site certificate application or on the draft proposed order after the close of the record of the public hearing.

(4) During the public hearing, the Department shall explain the application process, including the means and opportunities for the general public to participate in the process. The Department may provide this explanation by a written handout.

(5) At the commencement of the public hearing, the presiding officer shall state that:

(a) A person who intends to raise any issue that may be the basis for a contested case must raise the issue in person at the hearing or in a written comment submitted to the Department of Energy before the deadline stated in the notice of the public hearing.

(b) A person who intends to raise any issue that may be the basis for a contested case must raise the issue with sufficient specificity to afford the Council, the Department of Energy and the applicant an adequate opportunity to respond, including a statement of facts that support the person’s position on the issue.

(6) At the public hearing, any person may present information regarding the pending application without administration of an oath. The presiding officer shall record all presentations made during the public hearing. The presentations are part of the decision record for the application and may be rebutted in the contested case proceeding.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0230

Council Review and the Office of Energy’s Proposed Order

(1) Following the close of the record of the public hearing conducted under OAR 345-015-0220, the Council shall review the draft proposed order. In accordance with ORS 469.370(3), when the Council meets to review a draft proposed order, the Council does not permit the applicant, reviewing agencies or the public to comment on any issue that may be the basis for a contested case.

(2) Following the Council’s meeting to review the draft proposed order, the Department of Energy shall issue a proposed order in accordance with ORS 469.370(4), taking into consideration the comments of the Council, any public comments made at a public hearing, written comments received before the close of the record of the public hearing, and agency consultation. In the proposed order, the Department shall recommend either granting a site certificate with conditions or denying a site certificate for the proposed facility.

(3) Following issuance of the proposed order, the Department shall issue a contested case notice, as described in OAR 345-015-0014. In addition, as required under ORS 469.370(4), the Department shall issue a public notice of the proposed order and shall send the notice by mail or email to persons on the Council’s general mailing list as defined in OAR 345-011-0020 and to any special mailing list set up for the proposed project, including a mailing list made up of those persons listed in Exhibit F of the site certificate application as updated by the applicant upon the request of the Department.

(4) After the conclusion of the contested case proceeding, the Council will take final action on the site certificate application, as described in OAR 345-015-0085.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0240

The Decision-Making Record

The decision-making record on an application for a site certificate includes the decision record for the Department of Energy’s proposed order and the record of the contested case proceeding.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0300

Request for Expedited Review of Small Capacity Facilities

(1) In accordance with ORS 469.370(10), any person proposing to construct and operate an energy facility with an average electric generating capacity of less than 100 megawatts who chooses to request expedited review of an application for a site certificate shall submit to the Department of Energy a request for expedited review as described in section (2) with the fee required by the fee schedule established under ORS 469.441, payable to the Oregon Department of Energy. If the proposed energy facility has, as a related or supporting facility, a transmission line or pipeline that, by itself, is an energy facility under the definition in ORS 469.300, the proposed energy facility is not eligible for expedited review.

(2) In the request for expedited review, the applicant shall include:

(a) A description of the facility and the proposed site;

(b) The applicant’s name and address;

(c) A schedule stating when the applicant expects to submit a preliminary application for a site certificate;

(d) A list of all statutes, rules and ordinances applicable to the facility;

(e) A statement indicating whether the applicant intends to satisfy the Council’s land use standard, OAR 345-022-0030, by obtaining local land use approval pursuant to ORS 469.504(1)(a) or by seeking a Council determination pursuant to ORS 469.504(1)(b); and

(f) The reason and justification for any request for exception to an analysis area as provided under section (3).

(3) In an expedited review granted under this rule, the Department shall issue a project order following the applicant’s submission of a preliminary application for a site certificate. For the purposes of submitting the preliminary application, the analysis areas are the study areas as defined in OAR 345-001-0010, unless the applicant requests an exception in the request for expedited review and the Department approves the exception. The Department may, in the project order, modify the analysis areas. The Department may request additional information from the applicant, as provided in OAR 345-015-0190, before determining the application complete. Submission of the site certificate application and the Department’s review of the application in all other respects are the same for expedited review as for other site certificate applications.

(4) The Council hereby grants any request for expedited review from an applicant proposing a facility meeting the definition in section (1) if the Department determines that the request satisfies the requirements of section (2). The Department shall notify the applicant of its determination.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 2-2000, f. & cert. ef. 11-20-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-015-0310

Request for Expedited Review of Special Criteria Facilities

(1) Any person who proposes to construct and operate a special criteria facility, as defined in section (2), and who chooses to request expedited review of an application for a site certificate shall submit to the Department of Energy a request for expedited review as described in section (3) with the fee required by the fee schedule established under ORS 469.441, payable to the Oregon Department of Energy.

(2) “Special criteria facility” means a facility that meets the criteria stated in ORS 469.373(1).

(3) In the request for expedited review, the applicant shall provide documentation that the proposed facility is a special criteria facility, as defined in section (2), and:

(a) A description of the facility and the proposed site.

(b) The applicant’s name and address.

(c) A schedule stating when the applicant expects to submit an application for a site certificate.

(d) A list of all statutes, rules and ordinances applicable to the facility.

(4) Within 14 days after receiving the request for expedited review, the Department shall determine, on a preliminary, non-binding basis, whether the proposed facility qualifies for expedited review under this rule and shall notify the applicant. The Department may decide, on a preliminary, non-binding basis, that the proposed location of associated transmission lines or new natural gas pipelines outside of existing rights of way imposes no significant impact. The Department shall provide to the applicant a mailing list of persons including but not limited to the agencies listed in ORS 469.373(4).

(5) After the Department has made the determination described in section (4), the applicant may submit a preliminary application for a site certificate, as described in OAR 345-021-0000 and 345-021-0010. The applicant shall submit an original and two printed copies of the preliminary application to the Department. Upon a request by the Department, the applicant must submit printed copies of the preliminary application for members of the Council. In addition to the printed copies, the applicant shall submit the full preliminary application in a non-copy-protected electronic format acceptable to the Department. The applicant shall send a copy of the application to persons on the mailing list described in section (4). The applicant shall provide additional copies of the application to the Department upon request and copies or access to copies to any person requesting copies.

(6) Within 30 days after receiving a preliminary application for a site certificate, the Department shall issue a project order. In the project order, the Department may make changes to the analysis areas. The project order is not a final order. The Council or the Department may amend the project order at any time.

(7) Within 30 days after receiving a preliminary application for a site certificate, the Department shall either:

(a) Notify the applicant that the application is complete or

(b) Notify the applicant that the application is not complete and describe the information needed to complete the application, to the extent known to the Department at the time of the notification.

(8) If additional information is needed to complete the application, the applicant shall submit the information to the Department. If follow-up requests for additional information are needed, the Department may specify dates by which the applicant must submit the information. The Department may specify the dates by which the applicant must submit additional information needed to complete the application. At the request of the applicant, the Department may extend the deadline for submission of the information. If the applicant does not submit the information by the deadline specified by the Department, including any allowed extension, the Council may reject the application. The rejection of an application is subject to appeal under ORS 469.403(3).

(9) An application is complete when the Department finds that the applicant has submitted information adequate for the Council to make findings or impose conditions on all applicable Council standards. The Department may find that the application is complete without requiring the applicant to submit all information described under OAR 345-021-0000 and 345-021-0010. The Department shall notify the applicant when the Department finds that the application is complete and, if needed, shall request the application supplement described in OAR 345-021-0055.

(10) The date of filing is the date the Department receives the application supplement described in OAR 345-021-0055 or, if no supplement is needed, the date the Department notifies the applicant that the application is complete.

(11) After a determination that an application is complete, the Department may require additional information from the applicant if the Department identifies a need for that information during its review of the application. Submission of such information does not constitute an amendment of the application.

(12) In the notification to the applicant that the application is complete, as described in section (7)(a) or (9), the Department shall instruct the applicant send a copy of the notice described in section (13) and a copy of the application supplement, if any, to specified persons including but not limited to the agencies listed in ORS 469.373(4).

(13) The Department shall prepare a notice that:

(a) States that the application is complete and specifies the date of filing,

(b) Requests the agency reports as described in OAR 345-015-0200,

(c) Includes the statements required by ORS 469.373(4)(a) and (b).

(14) At the time specified in section (15), the Department shall issue a public notice, including but not limited to:

(a) A description of the proposed facility and the general location of the energy facility,

(b) The date, time and location of a public informational meeting on the application,

(c) A statement that the application has been filed,

(d) Addresses of locations where the public may review copies of the application, and

(e) The name of a Department of Energy representative to contact and the telephone number at which people may obtain additional information.

(15) At least 14 days before the meeting described in section (16), the Department shall:

(a) Submit the notice described in section (14) for publication in a newspaper of general circulation available in the vicinity of the proposed facility, and

(b) Send the notice described in section (14) by mail or email to persons on the Council’s general mailing list as defined in OAR 345-011-0020 and to any special mailing list set up for the proposed project, including a mailing list made up of those persons listed in Exhibit F of the site certificate application.

(16) The Department shall hold a public informational meeting on the application.

(17) Within 90 days after the date of filing, the Department shall issue a draft proposed order including, but not limited to:

(a) A description of the proposed facility,

(b) A list of the permits, licenses and certificates that are addressed in the application and that are required for the construction or operation of the proposed facility,

(c) A list of the statutes, rules and local ordinances that are the standards and criteria for approval of any permit, license or certificate addressed in the application and that are required for the construction or operation of the proposed facility, and

(d) Proposed findings regarding compliance with the applicable standards and criteria for approval of a site certificate and specifying conditions that are required for the facility to comply.

(18) The Council shall review the draft proposed order. In accordance with ORS 469.370(3), when the Council meets to review a draft proposed order, the Council does not permit the applicant, reviewing agencies or the public to comment on any issue that may be the basis for a contested case.

(19) After the Council’s review as described in section (18), the Department shall issue a proposed order.

(20) At the time specified in section (21), the Department shall issue a public notice, including but not limited to:

(a) A description of the facility and its general location.

(b) The name of a Department of Energy representative to contact and the telephone number at which people may obtain additional information.

(c) A statement that the Department has issued a proposed order and that copies of the application and proposed order are available for inspection at no cost and will be provided at reasonable cost.

(d) The date, time and location of a public hearing on the proposed order.

(e) A statement that the record for public comment on the application will close at the conclusion of the hearing and that failure to raise an issue in person or in writing prior to the close of the record with sufficient specificity to afford the decision maker an opportunity to respond to the issue precludes consideration of the issue in a contested case or by a court on judicial review of the Council’s decision.

(f) A statement that to raise an issue with sufficient specificity, a person must present facts that support the person’s position on the issue.

(g) A statement that the hearing is the only opportunity for the public to make a factual record for review and that persons having objection to the proposed order must appear at the hearing in person or in writing and present factual evidence, including any expert testimony, and legal argument.

(21) At least 20 days before the hearing described in section (22), the Department shall:

(a) Submit the notice described in section (20) for publication in a newspaper of general circulation available in the vicinity of the proposed facility, and

(b) Send the notice described in section (20) by mail or email to persons on the Council’s general mailing list as defined in OAR 345-011-0020 and to any special mailing list set up for the proposed project, including a mailing list made up of those persons listed in Exhibit F of the site certificate application.

(22) The Council shall hold at least one public hearing on the proposed order in the area affected by the proposed facility according to the procedures described in OAR 345-015-0320.

(23) Before the conclusion of the hearing described in section (22), the applicant may either:

(a) Request an opportunity to present additional written evidence, arguments or testimony regarding the application, or

(b) Request a contested case hearing on the application. Not later than 7 days after making a request in the public hearing, the applicant shall submit the request to the Council in writing, including evidence sufficient to show good cause for the contested case hearing.

(24) Except as described in section (27), following the close of the record of the public hearing, the Department shall issue a draft final order for the Council. In preparing the draft final order, the Department shall take into account the entire record, including the summary prepared by the hearing officer described in OAR 345-015-0320.

(25) Except as described in section (27), within six months after the date of filing, the Council shall make its decision on the record and the draft final order. The Council shall:

(a) Grant the site certificate,

(b) Grant the site certificate with conditions,

(c) Deny the site certificate, or

(d) Determine that the proposed facility is not a special criteria facility as defined in section (2) and is not eligible for expedited review under this rule.

(26) The Council shall issue a site certificate for the proposed facility if the Council determines that the proposed facility, with any required conditions to the site certificate, will comply with:

(a) The requirements for expedited review as specified in this rule.

(b) The standards adopted by the Council pursuant to ORS 469.501(1)(a), (c) to (e), (g), (h) and (L) to (o).

(c) The requirements of ORS 469.503(3).

(d) The requirements of ORS 469.504(1)(b).

(27) If the applicant requests a contested case hearing as described in section (23)(b), the Council, after considering the request in a public meeting, may grant the request if the Council finds that the applicant has shown good cause for a contested case hearing.

(28) If the Council grants the request for a contested case hearing, the Department shall issue a notice of a contested case on the proposed order as described in OAR 345-015-0014. The Council shall then consider the application under the same contested case procedures used for a nonexpedited application for a site certificate.

(29) If, as described in section (25), the Council determines that the proposed facility is not a special criteria facility and is not eligible for expedited review under this rule, then the Council shall consider the application under the same review procedures used for a nonexpedited application from the point of the applicant’s submission of an application. The Department shall treat the application before the Council at the time of the determination as a preliminary application for the purpose of review under OAR 345-015-0190, except that within 30 days after the Council’s determination, the Department shall determine whether the application is complete. The Department shall notify the applicant as described in OAR 345-015-0190(1) and the Department shall issue an amended project order that includes the Council standards that were not applicable under expedited review. For the purpose of the land use standard, the applicant must obtain a Council determination as described under OAR 345-022-0030(2)(b), and the Council shall apply the applicable substantive criteria in effect on the date the application was originally submitted under section (5).

(30) The applicant may withdraw its request for expedited review under this rule at any time and request that the Council consider its application under the same review procedures used for a nonexpedited application. After such a request, the Department shall treat the application as a preliminary application for the purpose of review under OAR 345-015-0190 as described in section (29). For the purpose of the land use standard, the applicant must obtain a Council determination as described under OAR 345-022-0030(2)(b), and the Council shall apply the applicable substantive criteria in effect on the date the application was originally submitted under section (5).

[ED. NOTE: Exhibits referenced are available from the agency.]

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.370
Hist.: EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-020-0011

Contents of a Notice of Intent

(1) The applicant shall, to the extent reasonably practicable, include in the notice of intent (NOI) the information described in the following subsections. If the applicant proposes alternative sites, the applicant shall describe each alternative separately. The applicant shall designate the information with the appropriate exhibit label identified in the following subsections.

(a) Exhibit A. Information about the applicant and participating persons, including:

(A) The name and address of the applicant including all co-owners of the proposed facility, the name, mailing address, email address and telephone number of the contact person for the NOI, and if there is a contact person other than the applicant, the name, title, mailing address, email address and telephone number of that person.

(B) The contact name, mailing address, email address and telephone number of all participating persons, other than individuals, including but not limited to any parent corporation of the applicant, persons upon whom the applicant will rely for third-party permits or approvals related to the facility, and persons upon whom the applicant will rely in meeting any facility standard adopted by the Council.

(C) If the applicant is a corporation, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the officer responsible for submitting the NOI;

(ii) The date and place of its incorporation;

(iii) A copy of its articles of incorporation and its authorization for submitting the NOI; and

(iv) In the case of a corporation not incorporated in Oregon, the name and address of the resident attorney-in-fact in this state and proof of registration to do business in Oregon.

(D) If the applicant is a wholly owned subsidiary of a company, corporation or other business entity, in addition to the information required by paragraph (C), it shall give the full name and business address of each of the applicant’s full or partial owners.

(E) If the person submitting the NOI is an association of citizens, a joint venture or a partnership, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the person responsible for submitting the NOI;

(ii) The name, business address and telephone number of each person participating in the association, joint venture or partnership and the percentage interest held by each;

(iii) Proof of registration to do business in Oregon;

(iv) A copy of its articles of association, joint venture agreement or partnership agreement and a list of its members and their cities of residence; and

(v) If there are no articles of association, joint venture agreement or partnership agreement, the applicant shall state that fact over the signature of each member.

(F) If the applicant is a public or governmental entity, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the person responsible for submitting the NOI; and

(ii) Written authorization from the entity’s governing body to submit an NOI.

(G) If the applicant is an individual, the individual shall give his or her mailing address, email address and telephone number.

(H) If the applicant is a limited liability company, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the officer responsible for submitting the NOI;

(ii) The date and place of its formation;

(iii) A copy of its articles of organization and its authorization for submitting the NOI; and

(iv) In the case of a limited liability company not registered in Oregon, the name and address of the resident attorney-in-fact in this state and proof of registration to do business in Oregon.

(b) Exhibit B. Information about the proposed facility, including:

(A) A description of the proposed energy facility, including as applicable:

(i) The nominal electric generating capacity and the average electrical generating capacity, as defined in ORS 469.300.

(ii) Major components, structures and systems, including a description of the size, type and configuration of equipment used to generate electricity and useful thermal energy.

(iii) Methods for waste management and waste disposal, including, to the extent known, the amount of wastewater the applicant anticipates, the applicant’s plans for disposal of wastewater and storm water, and the location of disposal.

(iv) For thermal power plants:

(I) A discussion of the source, quantity and availability of all fuels proposed to be used in the facility to generate electricity or useful thermal energy.

(II) Methods for disposal of waste heat.

(v) For transmission lines, approximate transmission line voltage, load carrying capacity and type of current.

(vi) For pipelines, approximate operating pressure and delivery capacity in thousand cubic feet per day.

(vii) For surface facilities related to underground gas storage, estimated daily injection and withdrawal rates, horsepower compression required to operate at design injection or withdrawal rates, operating pressure range and fuel type of compressors.

(viii) For facilities to store liquefied natural gas, the approximate volume, maximum pressure, liquefication and gasification capacity in thousand cubic feet per hour.

(B) A description of major components, structures and systems of each related or supporting facility.

(C) The approximate dimensions of major facility structures and visible features.

(c) Exhibit C. A description of the location of the proposed energy facility site and the proposed site of each related or supporting facility and all areas that might be temporarily disturbed during construction of the facility, including the approximate land area of each.

(d) Exhibit D. If the proposed energy facility is a pipeline or a transmission line or has, as a related or supporting facility, a transmission line or pipeline that, by itself, is an energy facility under the definition in ORS 469.300, identification of at least two proposed corridors, as defined in OAR 345-001-0010, or identification of a single proposed corridor with an explanation of why alternate corridors are unlikely to better meet the applicant’s needs and satisfy the Council’s standards. The applicant shall include an explanation of the basis for selecting the proposed corridor(s) and, for each proposed corridor, the information described in subsections (e), (g), (i), (j), (k), (n) and (p) that is available from existing maps, aerial photographs, and a search of readily available literature.

(e) Exhibit E. Identification of all federal, state and local government permits related to the siting of the proposed facility, a legal citation of the statute, rule or ordinance governing each permit, and the name, address, email address and telephone number of the agency or office responsible for each permit. For each permit, the applicant shall provide a preliminary analysis of whether the permit should or should not be included in and governed by the site certificate.

(f) Exhibit F. A list of the names and mailing addresses of all owners of record, as shown on the most recent property tax assessment roll, of property located within or adjacent to the site boundary as defined in OAR 345-001-0010. In addition to incorporating the list in the NOI, the applicant shall submit the list to the Department of Energy in electronic format acceptable to the Department for the production of mailing labels. Property adjacent to the site boundary means property that is:

(A) Within 100 feet of the site boundary where the site, corridor or micrositing corridor is within an urban growth boundary;

(B) Within 250 feet of the site boundary where the site, corridor or micrositing corridor is outside an urban growth boundary and not within a farm or forest zone; and

(C) Within 500 feet of the site boundary where the site, corridor or micrositing corridor is within a farm or forest zone.

(g) Exhibit G. A map or maps showing:

(A) The proposed locations of the energy facility site, all related or supporting facility sites and all areas that might be temporarily disturbed during construction of the facility in relation to major roads, water bodies, cities and towns, important landmarks and topographic features.

(B) The proposed locations of the corridors the applicant has identified under subsection (d) in relation to major roads, water bodies, cities and towns, important landmarks and topographic features.

(C) The study area(s) for the proposed facility as defined in OAR 345-001-0010.

(D) The topography of the study area(s) including streams, rivers, lakes, major roads and contour lines.

(E) All protected areas in the study area as defined in OAR 345-001-0010 for impacts to protected areas.

(F) The location of any potential waters of the state or waters of the United States that are on or adjacent to the site.

(G) For energy generation facilities, the approximate locations of any other energy generation facilities that are known to the applicant to be permitted at the state or local level within the study area as defined in OAR 345-001-0010 for impacts to public services.

(h) Exhibit H. If the proposed facility is a non-generating energy facility for which the applicant must demonstrate need under OAR 345-023-0005, identification of the rule in Division 23 of this chapter under which the applicant intends to demonstrate need and a summary statement of the need and justification for the proposed facility.

(i) Exhibit I. A statement indicating whether the applicant intends to satisfy the Council’s land use standard, OAR 345-022-0030, by obtaining local land use approval under ORS 469.504(1)(a) or by seeking a Council determination under ORS 469.504(1)(b).

(j) Exhibit J. Identification of significant potential environmental impacts of construction and operation of the proposed facility on the study areas, including those impacts affecting air quality, surface and ground water quality and availability, wildlife and wildlife habitat, threatened and endangered plant and animal species, historic, cultural and archaeological resources, scenic and aesthetic areas, recreation, and land use.

(k) Exhibit K. Information about significant potential adverse impacts of construction and operation of the proposed facility on the ability of communities in the study area to provide the services listed in OAR 345-022-0110.

(l) Exhibit L. Information about anticipated water use during construction and operation of the proposed facility, including:

(A) A description of each source of water and the applicant’s estimate of the amount of water the facility will need from each source.

(B) If a new water right is required, the approximate location of the points of diversion and the estimated quantity of water to be taken at each point.

(C) For operation, the source of cooling water and the estimated consumptive use of cooling water, based on annual average conditions.

(m) Exhibit M. If the proposed facility would emit carbon dioxide, an estimate of the gross rate of carbon dioxide emissions, a table listing all the factors that form the basis for calculating the estimate, and a statement of the means by which the applicant intends to comply with the applicable carbon dioxide emissions standard under OAR 345-024-560, 345-024-600, or 345-024-630.

(n) Exhibit N. Identification, by legal citation, of all state statutes and administrative rules and local government ordinances containing standards or criteria that the proposed facility must meet for the Council to issue a site certificate, other than statutes, rules and ordinances identified in Exhibit E, and identification of the agencies administering those statutes, administrative rules and ordinances. The applicant shall analyze and describe any problems the applicant foresees in satisfying the requirements of any such statute, rule or ordinance.

(o) Exhibit O. A schedule stating when the applicant expects to submit a preliminary application for a site certificate.

(p) Exhibit P. Evidence of consultation with the Legislative Commission on Indian Services to identify each appropriate tribe to consult with regarding the proposed facility’s possible effects on Indian historic and cultural resources.

(2) Documents prepared in connection with an environmental assessment or environmental impact statement for the proposed facility under the National Environmental Policy Act of 1970, if any, may contain some of the information required by section (1) of this rule. The applicant may copy relevant sections of such documents into the appropriate exhibits of the NOI. The applicant may otherwise submit full copies of those documents and include, in the appropriate exhibits of the NOI, cross-references to the relevant sections of those documents. The applicant may use such documents only to avoid duplication. The applicant shall include additional information in the NOI as needed to meet the requirements of section (1) of this rule.

(3) The applicant shall include a table of contents in the NOI identifying the location of each exhibit required by this rule. The applicant shall submit an original and two printed copies of the NOI to the Department and shall prepare and distribute additional copies of the NOI as required by OAR 345-020-0040. Upon a request by the Department, the applicant must submit printed copies of the NOI for members of the Council. In addition to the printed copies, the applicant shall submit the full NOI in a non-copy-protected electronic format acceptable to the Department.

(4) The applicant or the applicant’s representative shall attend all public informational meetings on the NOI as described in OAR 345-015-0130 to discuss the proposed facility and to answer questions from the public. If the applicant has identified one or more proposed corridors in Exhibit D of the NOI as required by section (1)(d), the applicant may present adjustments to the proposed corridor(s) at any public informational meeting. An adjustment is any change that is outside the boundaries of the corridors proposed in the NOI and may include an entirely new corridor.

[ED. NOTE: Exhibits referenced are available from the agency.]

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.330
Hist.: EFSC 13, f. & ef. 6-11-76; EFSC 2-1991(Temp), f. & cert. ef. 6-5-91; EFSC 1-1992(Temp), f. & cert. ef. 3-4-92; EFSC 2-1992, f. & cert. ef. 8-28-92; EFSC 5-1995, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-020-0016

Amendment of Notice of Intent

(1) The applicant may amend the notice of intent (NOI). The applicant shall submit the original and two printed copies of the amended NOI to the Department of Energy. Upon a request by the Department, the applicant must submit printed copies of the amended NOI for members of the Council. In addition to the printed copies, the applicant shall submit the full amended NOI in a non-copy-protected electronic format acceptable to the Department.

(2) The Department shall inform the public, in the manner described in OAR 345-015-0110, of any amendment that:

(a) Significantly changes the proposed site boundary or location of the proposed energy facility or related or supporting facility;

(b) Changes the proposed fuel type, significantly increases the generating capacity of the proposed energy facility, increases the voltage of a proposed transmission line, or significantly increases the capacity or operating pressure of a proposed pipeline;

(c) Increases water consumption or disposal by more than 5 percent;

(d) Changes the source of water; or

(e) Significantly changes the means of compliance with the carbon dioxide standard, if applicable.

(3) The applicant shall distribute copies of the amended NOI in the manner described in OAR 345-020-0040.

(4) Submission of an amended NOI does not extend the expiration date of the NOI. The applicant, however, may petition the Council to extend the duration of the NOI as provided in OAR 345-020-0060.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.330
Hist.: EFSC 5-1995, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-020-0040

Distribution of a Notice of Intent

(1) After receiving the notice of intent (NOI), the Department will prepare the memorandum described in OAR 345-015-0120 and, in coordination with the applicant, determine a distribution date and compile a distribution list. The applicant shall distribute copies of the NOI to the persons on the distribution list on or before the distribution date. The Department shall include the reviewing agencies as defined in OAR 345-001-0010 on the distribution list and may include additional persons.

(2) The applicant shall attach the memorandum from the Department described in OAR 345-015-0120 to the copies of the NOI distributed according to section (1).

(3) The applicant shall provide additional copies of the NOI to the Department upon request and copies or access to copies to any person requesting copies.

(4) The distribution described in section (1) may be done by courier delivery or mailing of printed copies or, with the approval of the Department, any form of electronic delivery.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.330
Hist.: EFSC 2-1991(Temp), f. & cert. ef. 6-5-91; EFSC 1-1992(Temp), f. & cert. ef. 3-4-92; EFSC 2-1992, f. & cert. ef. 8-28-92; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-96; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-021-0000

General Requirements

(1) Except for facilities that the Council has determined exempt as described in OAR 345-015-0350 to 345-015-0370 or for which a separate site certificate is not required according to ORS 469.320(5), a person shall not construct or expand a facility unless the Council has granted a site certificate or an amendment to an existing site certificate.

(2) As used in this division, “energy facility” includes an electric power generating plant with an average electric generating capacity of less than 35 megawatts produced from wind energy for which a person has elected to apply for a site certificate under ORS 469.320(8).

(3) An applicant shall not submit an application for a site certificate before the Department of Energy has issued a project order for the proposed facility as described in OAR 345-015-0160. The applicant may submit a draft application before the issuance of a project order. The applicant must submit the application before the expiration of the notice of intent.

(4) For an expedited review granted under OAR 345-015-0300 or OAR 345-015-0310, section (3) does not apply and the applicant may submit an application for a site certificate any time after the Department determines the request for expedited review satisfies the requirements for expedited review as described in those rules.

(5) If the applicant submits a written request for waiver or modification of requirements in OAR 345-021-0010 to the Department, the Department may waive or modify those requirements that the Department determines are not applicable to the proposed facility.

(6) For any state or local government agency permits, licenses or certificates proposed by the applicant to be included in and governed by the site certificate, the applicant shall include within the site certificate application all information that would otherwise be required by the state or local government agency in an application for such permit, license or certificate.

(7) For any federally-delegated permits that are needed for construction or operation of the proposed facility, the applicant shall submit to the Department one copy of each federally-delegated permit application. The applicant may submit the site certificate application before submitting a copy of a federally-delegated permit application if the applicant submits a schedule of the date by which the applicant intends to submit the federally-delegated permit application. The Department may not find the site certificate application to be complete before receiving copies of all federally-delegated permit applications and a letter or other indication from each agency responsible for issuing a federally-delegated permit stating that the agency has received the permit application, identifying any additional information the agency is likely to need from the applicant and estimating the date when the agency will complete its review and issue a permit decision.

(8) If the proposed facility is a non-generating facility for which the applicant must demonstrate need under OAR 345-023-0005, in addition to the application for a site certificate described in OAR 345-021-0010, the applicant shall submit to the Department three copies of each energy resource plan or combination of plans on which the applicant relies to demonstrate need under OAR 345-023-0020, unless the applicant chooses to incorporate copies of the plan(s) as part of the application for a site certificate. The applicant shall submit the plan(s) to the Department with the site certificate application. The Department may not find the site certificate application to be complete before receiving copies of the plan(s). The plan or plans described in this section are part of the decision record for the Department’s proposed order, described in OAR 345-015-0230.

(9) The applicant shall submit an application for a site certificate to the Department with 25 percent of the fee the Department determines necessary for review of the application under ORS 469.421(3), payable to the Oregon Department of Energy. The applicant shall pay the balance of the fee periodically, as specified by the Department.

(10) Until the Department determines the application to be complete as described in OAR 345-015-0190 or 345-015-0310, it is a preliminary application. For the purpose of determining the applicable substantive criteria under ORS 469.504(1)(b)(A), the date the preliminary application is received by the Department is the date the application is submitted.

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.350, 469.370 & 469.421
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-95; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 2-2000, f. & cert. ef. 11-20-00; EFSC 2-2001(Temp), f. & cert. ef. 9-17-01 thru 3-10-02; Administrative correction 3-14-02; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-021-0010

Contents of an Application

(1) The project order described in OAR 345-015-0160(1) identifies the provisions of this rule applicable to the application for the proposed facility, including any appropriate modifications to applicable provisions of this rule. The applicant shall include in its application for a site certificate information that addresses each provision of this rule identified in the project order. The applicant shall designate the information with the appropriate exhibit label identified in the following subsections. If the same information is required in each of several exhibits the applicant may provide the required information in one exhibit and include appropriate references in the others. For the purpose of submitting an application for a site certificate in an expedited review granted under OAR 345-015-0300 or OAR 345-015-0310, the applicant shall include information that addresses all provisions of this rule. In such expedited reviews, analysis areas addressed in this rule are the study areas defined in OAR 345-001-0010, subject to later modification in the project order.

(a) Exhibit A. Information about the applicant and participating persons, including:

(A) The name and address of the applicant including all co-owners of the proposed facility, the name, mailing address, email address and telephone number of the contact person for the application, and if there is a contact person other than the applicant, the name, title, mailing address, email address and telephone number of that person.

(B) The contact name, mailing address, email address and telephone number of all participating persons, other than individuals, including but not limited to any parent corporation of the applicant, persons upon whom the applicant will rely for third-party permits or approvals related to the facility, and, if known, other persons upon whom the applicant will rely in meeting any facility standard adopted by the Council.

(C) If the applicant is a corporation, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the officer responsible for submitting the application;

(ii) The date and place of its incorporation;

(iii) A copy of its articles of incorporation and its authorization for submitting the application; and

(iv) In the case of a corporation not incorporated in Oregon, the name and address of the resident attorney-in-fact in this state and proof of registration to do business in Oregon.

(D) If the applicant is a wholly owned subsidiary of a company, corporation or other business entity, in addition to the information required by paragraph (C), it shall give the full name and business address of each of the applicant’s full or partial owners.

(E) If the applicant is an association of citizens, a joint venture or a partnership, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the person responsible for submitting the application;

(ii) The name, business address and telephone number of each person participating in the association, joint venture or partnership and the percentage interest held by each;

(iii) Proof of registration to do business in Oregon;

(iv) A copy of its articles of association, joint venture agreement or partnership agreement and a list of its members and their cities of residence; and

(v) If there are no articles of association, joint venture agreement or partnership agreement, the applicant shall state that fact over the signature of each member.

(F) If the applicant is a public or governmental entity, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the person responsible for submitting the application; and

(ii) Written authorization from the entity’s governing body to submit an application.

(G) If the applicant is an individual, the individual shall give his or her mailing address, email address and telephone number.

(H) If the applicant is a limited liability company, it shall give:

(i) The full name, official designation, mailing address, email address and telephone number of the officer responsible for submitting the application;

(ii) The date and place of its formation;

(iii) A copy of its articles of organization and its authorization for submitting the application; and

(iv) In the case of a limited liability company not registered in Oregon, the name and address of the resident attorney-in-fact in this state and proof of registration to do business in Oregon.

(b) Exhibit B. Information about the proposed facility, construction schedule and temporary disturbances of the site, including:

(A) A description of the proposed energy facility, including as applicable:

(i) The nominal electric generating capacity and the average electrical generating capacity, as defined in ORS 469.300.

(ii) Major components, structures and systems, including a description of the size, type and configuration of equipment used to generate electricity and useful thermal energy.

(iii) A site plan and general arrangement of buildings, equipment and structures.

(iv) Fuel and chemical storage facilities, including structures and systems for spill containment

(v) Equipment and systems for fire prevention and control.

(vi) For thermal power plants:

(I) A discussion of the source, quantity and availability of all fuels proposed to be used in the facility to generate electricity or useful thermal energy.

(II) Process flow, including power cycle and steam cycle diagrams to describe the energy flows within the system.

(III) Equipment and systems for disposal of waste heat.

(IV) The fuel chargeable to power heat rate.

(vii) For surface facilities related to underground gas storage, estimated daily injection and withdrawal rates, horsepower compression required to operate at design injection or withdrawal rates, operating pressure range and fuel type of compressors.

(viii) For facilities to store liquefied natural gas, the volume, maximum pressure, liquefication and gasification capacity in thousand cubic feet per hour.

(B) A description of major components, structures and systems of each related or supporting facility.

(C) The approximate dimensions of major facility structures and visible features.

(D) If the proposed energy facility is a pipeline or a transmission line or has, as a related or supporting facility, a transmission line or pipeline that, by itself, is an energy facility under the definition in ORS 469.300, a corridor selection assessment explaining how the applicant selected the corridor(s) for analysis in the application. In the assessment, the applicant shall evaluate the corridor adjustments the Department has described in the project order, if any. The applicant may select any corridor for analysis in the application and may select more than one corridor. However, if the applicant selects a new corridor, then the applicant must explain why the applicant did not present the new corridor for comment at an informational meeting under OAR 345-015-0130. In the assessment, the applicant shall discuss the reasons for selecting the corridor(s), based upon evaluation of the following factors:

(i) Least disturbance to streams, rivers and wetlands during construction.

(ii) Least percentage of the total length of the pipeline or transmission line that would be located within areas of Habitat Category 1, as described by the Oregon Department of Fish and Wildlife.

(iii) Greatest percentage of the total length of the pipeline or transmission line that would be located within or adjacent to public roads and existing pipeline or transmission line rights-of-way.

(iv) Least percentage of the total length of the pipeline or transmission line that would be located within lands that require zone changes, variances or exceptions.

(v) Least percentage of the total length of the pipeline or transmission line that would be located in a protected area as described in OAR 345-022-0040.

(vi) Least disturbance to areas where historical, cultural or archaeological resources are likely to exist.

(vii) Greatest percentage of the total length of the pipeline or transmission line that would be located to avoid seismic, geological and soils hazards.

(viii) Least percentage of the total length of the pipeline or transmission line that would be located within lands zoned for exclusive farm use.

(E) If the proposed energy facility is a pipeline or transmission line or has, as a related or supporting facility, a transmission line or pipeline of any size:

(i) The length of the pipeline or transmission line.

(ii) The proposed right-of-way width of the pipeline or transmission line, including to what extent new right-of-way will be required or existing right-of-way will be widened.

(iii) If the proposed transmission line or pipeline corridor follows or includes public right-of-way, a description of where the transmission line or pipeline would be located within the public right-of-way, to the extent known. If the applicant proposes to locate all or part of a transmission line or pipeline adjacent to but not within the public right-of-way, describe the reasons for locating the transmission line or pipeline outside the public right-of-way. The applicant must include a set of clear and objective criteria and a description of the type of evidence that would support locating the transmission line or pipeline outside the public right-of-way, based on those criteria.

(iv) For pipelines, the operating pressure and delivery capacity in thousand cubic feet per day and the diameter and location, above or below ground, of each pipeline.

(v) For transmission lines, the rated voltage, load carrying capacity, and type of current and a description of transmission line structures and their dimensions.

(F) A construction schedule including the date by which the applicant proposes to begin construction and the date by which the applicant proposes to complete construction. Construction is defined in OAR 345-001-0010. The applicant shall describe in this exhibit all work on the site that the applicant intends to begin before the Council issues a site certificate. The applicant shall include an estimate of the cost of that work. For the purpose of this exhibit, “work on the site” means any work within a site or corridor, other than surveying, exploration or other activities to define or characterize the site or corridor, that the applicant anticipates or has performed as of the time of submitting the application.

(c) Exhibit C. Information about the location of the proposed facility, including:

(A) A map or maps showing the proposed locations of the energy facility site, all related or supporting facility sites and all areas that might be temporarily disturbed during construction of the facility in relation to major roads, water bodies, cities and towns, important landmarks and topographic features, using a scale of 1 inch = 2000 feet or smaller when necessary to show detail.

(B) A description of the location of the proposed energy facility site, the proposed site of each related or supporting facility and areas of temporary disturbance, including the total land area (in acres) within the proposed site boundary, the total area of permanent disturbance, and the total area of temporary disturbance. If a proposed pipeline or transmission line is to follow an existing road, pipeline or transmission line, the applicant shall state to which side of the existing road, pipeline or transmission line the proposed facility will run, to the extent this is known.

(C) For energy generation facilities, a map showing the approximate locations of any other energy generation facilities that are known to the applicant to be permitted at the state or local level within the study area as defined in OAR 345-001-0010 for impacts to public services.

(d) Exhibit D. Information about the organizational expertise of the applicant to construct and operate the proposed facility, providing evidence to support a finding by the Council as required by OAR 345-022-0010, including:

(A) The applicant’s previous experience, if any, in constructing and operating similar facilities.

(B) The qualifications of the applicant’s personnel who will be responsible for constructing and operating the facility, to the extent that the identities of such personnel are known when the application is submitted.

(C) The qualifications of any architect, engineer, major component vendor, or prime contractor upon whom the applicant will rely in constructing and operating the facility, to the extent that the identities of such persons are known when the application is submitted.

(D) The past performance of the applicant, including but not limited to the number and severity of any regulatory citations in constructing or operating a facility, type of equipment, or process similar to the proposed facility.

(E) If the applicant has no previous experience in constructing or operating similar facilities and has not identified a prime contractor for construction or operation of the proposed facility, other evidence that the applicant can successfully construct and operate the proposed facility. The applicant may include, as evidence, a warranty that it will, through contracts, secure the necessary expertise.

(F) If the applicant has an ISO 9000 or ISO 14000 certified program and proposes to design, construct and operate the facility according to that program, a description of the program.

(G) If the applicant relies on mitigation to demonstrate compliance with any standards of Division 22 or 24 of this chapter, evidence that the applicant can successfully complete such proposed mitigation, including past experience with other projects and the qualifications and experience of personnel upon whom the applicant will rely, to the extent that the identities of such persons are known at the date of submittal.

(e) Exhibit E. Information about permits needed for construction and operation of the facility, including:

(A) Identification of all federal, state and local government permits related to the siting of the proposed facility, a legal citation of the statute, rule or ordinance governing each permit, and the name, mailing address, email address and telephone number of the agency or office responsible for each permit.

(B) A description of each permit, the reasons the permit is needed for construction or operation of the facility and the applicant’s analysis of whether the permit should or should not be included in and governed by the site certificate.

(C) For any state or local government agency permits, licenses or certificates that are proposed to be included in and governed by the site certificate, evidence to support findings by the Council that construction and operation of the proposed facility will comply with the statutes, rules and standards applicable to the permit. The applicant may show this evidence:

(i) In Exhibit J for permits related to wetlands.

(ii) In Exhibit O for permits related to water rights.

(D) For federally-delegated permit applications, evidence that the responsible agency has received a permit application and the estimated date when the responsible agency will complete its review and issue a permit decision.

(E) If the applicant relies on a state or local government permit or approval issued to a third party, identification of any such third-party permit and for each:

(i) Evidence that the applicant has, or has a reasonable likelihood of entering into, a contract or other agreement with the third party for access to the resource or service to be secured by that permit.

(ii) Evidence that the third party has, or has a reasonable likelihood of obtaining, the necessary permit.

(iii) An assessment of the impact of the proposed facility on any permits that a third party has obtained and on which the applicant relies to comply with any applicable Council standard.

(F) If the applicant relies on a federally-delegated permit issued to a third party, identification of any such third-party permit and for each:

(i) Evidence that the applicant has, or has a reasonable likelihood of entering into, a contract or other agreement with the third party for access to the resource or service to be secured by that permit.

(ii) Evidence that the responsible agency has received a permit application.

(iii) The estimated the date when the responsible agency will complete its review and issue a permit decision.

(G) The applicant’s proposed monitoring program, if any, for compliance with permit conditions.

(f) Exhibit F. A list of the names and mailing addresses of all owners of record, as shown on the most recent property tax assessment roll, of property located within or adjacent to the site boundary as defined in OAR 345-001-0010. The applicant shall submit an updated list of property owners as requested by the Department before the Department issues notice of any public hearing on the application for a site certificate as described in OAR 345-015-0220. In addition to incorporating the list in the application for a site certificate, the applicant shall submit the list to the Department in an electronic format approved by the Department. Property adjacent to the site boundary means property that is:

(A) Within 100 feet of the site boundary where the site, corridor or micrositing corridor is within an urban growth boundary.

(B) Within 250 feet of the site boundary where the site, corridor or micrositing corridor is outside an urban growth boundary and not within a farm or forest zone.

(C) Within 500 feet of the site boundary where the site, corridor or micrositing corridor is within a farm or forest zone.

(g) Exhibit G. A materials analysis including:

(A) An inventory of substantial quantities of industrial materials flowing into and out of the proposed facility during construction and operation.

(B) The applicant’s plans to manage hazardous substances during construction and operation, including measures to prevent and contain spills.

(C) The applicant’s plans to manage non-hazardous waste materials during construction and operation.

(h) Exhibit H. Information from reasonably available sources regarding the geological and soil stability within the analysis area, providing evidence to support findings by the Council as required by OAR 345-022-0020, including:

(A) A geologic report meeting the guidance in Oregon Department of Geology and Mineral Industries open file report 00-04 “Guidelines for Engineering Geologic reports and Site-Specific Seismic Hazard Reports.”

(B) A description and schedule of site-specific geotechnical work that will be performed before construction for inclusion in the site certificate as conditions.

(C) Evidence of consultation with the Oregon Department of Geology and Mineral Industries regarding the appropriate site-specific geotechnical work that must be performed before submitting the application for the Department to determine that the application is complete.

(D) For all transmission lines, a description of locations along the proposed route where the applicant proposes to perform site specific geotechnical work, including but not limited to railroad crossings, major road crossings, river crossings, dead ends, corners, and portions of the proposed route where geologic reconnaissance and other site specific studies provide evidence of existing landslides or marginally stable slopes that could be made unstable by the planned construction.

(E) For all pipelines that would carry explosive, flammable or hazardous materials, a description of locations along the proposed route where the applicant proposes to perform site specific geotechnical work, including but not limited to railroad crossings, major road crossings, river crossings and portions of the proposed alignment where geologic reconnaissance and other site specific studies provide evidence of existing landslides or marginally stable slopes that could be made unstable by the planned construction.

(F) An assessment of seismic hazards. For the purposes of this assessment, the maximum probable earthquake (MPE) is the maximum earthquake that could occur under the known tectonic framework with a 10 percent chance of being exceeded in a 50 year period. If seismic sources are not mapped sufficiently to identify the ground motions above, the applicant shall provide a probabilistic seismic hazard analysis to identify the peak ground accelerations expected at the site for a 500 year recurrence interval and a 5000 year recurrence interval. In the assessment, the applicant shall include:

(i) Identification of the Maximum Considered Earthquake Ground Motion as shown for the site under the 2009 International Building Code.

(ii) Identification and characterization of all earthquake sources capable of generating median peak ground accelerations greater than 0.05g on rock at the site. For each earthquake source, the applicant shall assess the magnitude and minimum epicentral distance of the maximum credible earthquake (MCE).

(iii) A description of any recorded earthquakes within 50 miles of the site and of recorded earthquakes greater than 50 miles from the site that caused ground shaking at the site more intense than the Modified Mercalli III intensity. The applicant shall include the date of occurrence and a description of the earthquake that includes its magnitude and highest intensity and its epicenter location or region of highest intensity.

(iv) Assessment of the median ground response spectrum from the MCE and the MPE and identification of the spectral accelerations greater than the design spectrum provided in the 2010 Oregon Structural Specialty Code. The applicant shall include a description of the probable behavior of the subsurface materials and amplification by subsurface materials and any topographic or subsurface conditions that could result in expected ground motions greater than those characteristic of the Maximum Considered Earthquake Ground Motion identified above.

(v) An assessment of seismic hazards expected to result from reasonably probable seismic events. As used in this rule “seismic hazard” includes ground shaking, ground failure, landslide, lateral spreading, liquefaction, tsunami inundation, fault displacement and subsidence.

(G) An assessment of soil-related hazards such as landslides, flooding and erosion which could, in the absence of a seismic event, adversely affect or be aggravated by the construction or operation of the facility.

(H) An explanation of how the applicant will design, engineer and construct the facility to avoid dangers to human safety from the seismic hazards identified in paragraph (F). The applicant shall include proposed design and engineering features, applicable construction codes, and any monitoring for seismic hazards.

(I) An explanation of how the applicant will design, engineer and construct the facility to adequately avoid dangers to human safety presented by the hazards identified in paragraph (G).

(i) Exhibit I. Information from reasonably available sources regarding soil conditions and uses in the analysis area, providing evidence to support findings by the Council as required by OAR 345-022-0022, including:

(A) Identification and description of the major soil types in the analysis area.

(B) Identification and description of current land uses in the analysis area, such as growing crops, that require or depend on productive soils.

(C) Identification and assessment of significant potential adverse impact to soils from construction, operation and retirement of the facility, including, but not limited to, erosion and chemical factors such as salt deposition from cooling towers, land application of liquid effluent, and chemical spills.

(D) A description of any measures the applicant proposes to avoid or mitigate adverse impact to soils.

(E) The applicant’s proposed monitoring program, if any, for adverse impact to soils during construction and operation.

(j) Exhibit J. Information based on literature and field study, as appropriate, about waters of this state, as defined under ORS 196.800, including:

(A) A description of all areas within the site boundary that might be waters of this state and a map showing the location of these features.

(B) An analysis of whether construction or operation of the proposed facility would adversely affect any waters of this state.

(C) A description of the significance of potential adverse impacts to each feature identified in (A), including the nature and amount of material the applicant would remove from or place in the waters analyzed in (B).

(D) If the proposed facility would not need a removal-fill authorization, an explanation of why no such authorization is required for the construction and operation of the proposed facility.

(E) If the proposed facility would need a removal-fill authorization, information to support a determination by the Council that the Oregon Department of State Lands should issue a removal-fill permit, including information in the form required by the Department of State Lands under OAR Chapter 141 Division 85.

(F) A description of proposed actions to mitigate adverse impacts to the features identified in (A) and the applicant’s proposed monitoring program, if any, for such impacts.

(k) Exhibit K. Information about the proposed facility’s compliance with the statewide planning goals adopted by the Land Conservation and Development Commission, providing evidence to support a finding by the Council as required by OAR 345-022-0030. The applicant shall state whether the applicant elects to address the Council’s land use standard by obtaining local land use approvals under ORS 469.504(1)(a) or by obtaining a Council determination under ORS 469.504(1)(b). An applicant may elect different processes for an energy facility and a related or supporting facility but may not otherwise combine the two processes. Once the applicant has made an election, the applicant may not amend the application to make a different election. In this subsection, “affected local government” means a local government that has land use jurisdiction over any part of the proposed site of the facility. In the application, the applicant shall:

(A) Include a map showing the comprehensive plan designations and land use zones in the analysis area.

(B) If the applicant elects to obtain local land use approvals:

(i) Identify the affected local government(s) from which land use approvals will be sought.

(ii) Describe the land use approvals required in order to satisfy the Council’s land use standard.

(iii) Describe the status of the applicant’s application for each land use approval.

(iv) Provide an estimate of time for issuance of local land use approvals.

(C) If the applicant elects to obtain a Council determination on land use:

(i) Identify the affected local government(s).

(ii) Identify the applicable substantive criteria from the affected local government’s acknowledged comprehensive plan and land use regulations that are required by the statewide planning goals and that are in effect on the date the application is submitted and describe how the proposed facility complies with those criteria.

(iii) Identify all Land Conservation and Development Commission administrative rules, statewide planning goals and land use statutes directly applicable to the facility under ORS 197.646(3) and describe how the proposed facility complies with those rules, goals and statutes.

(iv) If the proposed facility might not comply with all applicable substantive criteria, identify the applicable statewide planning goals and describe how the proposed facility complies with those goals.

(v) If the proposed facility might not comply with all applicable substantive criteria or applicable statewide planning goals, describe why an exception to any applicable statewide planning goal is justified, providing evidence to support all findings by the Council required under ORS 469.504(2.

(D) If the proposed facility will be located on federal land:

(i) Identify the applicable land management plan adopted by the federal agency with jurisdiction over the federal land.

(ii) Explain any differences between state or local land use requirements and federal land management requirements.

(iii) Describe how the proposed facility complies with the applicable federal land management plan.

(iv) Describe any federal land use approvals required for the proposed facility and the status of application for each required federal land use approval.

(v) Provide an estimate of time for issuance of federal land use approvals.

(vi) If federal law or the land management plan conflicts with any applicable state or local land use requirements, explain the differences in the conflicting requirements, state whether the applicant requests Council waiver of the land use standard described under paragraph (B) or (C) of this subsection and explain the basis for a waiver.

(l) Exhibit L. Information about the proposed facility’s impact on protected areas, providing evidence to support a finding by the Council as required by OAR 345-022-0040, including:

(A) A list of the protected areas within the analysis area showing the distance and direction from the proposed facility and the basis for protection by reference to a specific subsection under OAR 345-022-0040(1).

(B) A map showing the location of the proposed facility in relation to the protected areas listed in OAR 345-022-0040 located within the analysis area.

(C) A description of significant potential impacts of the proposed facility, if any, on the protected areas including, but not limited to, potential impacts such as:

(i) Noise resulting from facility construction or operation;

(ii) Increased traffic resulting from facility construction or operation;

(iii) Water use during facility construction or operation;

(iv) Wastewater disposal resulting from facility construction or operation;

(v) Visual impacts of facility structures or plumes.

(vi) Visual impacts from air emissions resulting from facility construction or operation, including, but not limited to, impacts on Class 1 Areas as described in OAR 340-204-0050.

(m) Exhibit M. Information about the applicant’s financial capability, providing evidence to support a finding by the Council as required by OAR 345-022-0050(2). Nothing in this subsection shall require the disclosure of information or records protected from public disclosure by any provision of state or federal law. The applicant shall include:

(A) An opinion or opinions from legal counsel stating that, to counsel’s best knowledge, the applicant has the legal authority to construct and operate the facility without violating its bond indenture provisions, articles of incorporation, common stock covenants, or similar agreements.

(B) The type and amount of the applicant’s proposed bond or letter of credit to meet the requirements of OAR 345-022-0050.

(C) Evidence that the applicant has a reasonable likelihood of obtaining the proposed bond or letter of credit in the amount proposed in paragraph (B), before beginning construction of the facility.

(n) Exhibit N. If the proposed facility is a non-generating facility for which the applicant must demonstrate need under OAR 345-023-0005, information about the need for the facility, providing evidence to support a finding by the Council as required by OAR 345-023-0005, including:

(A) Identification of the rule in Division 23 of this chapter under which the applicant chooses to demonstrate need.

(B) If the applicant chooses to demonstrate need for the proposed facility under OAR 345-023-0020(1), the least-cost plan rule:

(i) Identification of the energy resource plan or combination of plans on which the applicant relies to demonstrate need.

(ii) The name, address and telephone number of the person responsible for preparing each energy resource plan identified in subparagraph (i).

(iii) For each plan reviewed by a regulatory agency, the agency’s findings and final decision, including:

(I) For a plan reviewed by the Oregon Public Utility Commission, the acknowledgment order; or

(II) For a plan reviewed by any other regulatory agency, a summary of the public process including evidence to support a finding by the Council that the agency’s decision process included a full, fair and open public participation and comment process as required by OAR 345-023-0020(1)(L), and the location of and means by which the Department can obtain a complete copy of the public record.

(iv) Identification of the section(s) of the short-term action plan(s) that call(s) for the acquisition of the proposed facility or, as defined in OAR 345-001-0010, a facility substantially similar to the proposed facility.

(v) The attributes of the proposed facility that qualify it as one called for in the short-term action plan of the energy resource plan or combination of plans identified in subparagraph (i) or a demonstration that, as defined in OAR 345-001-0010, a facility substantially similar to the proposed facility is called for in the plan(s).

(C) In addition to the information described in paragraph (B), if the applicant chooses to demonstrate need for the proposed facility under OAR 345-023-0020(1), the least-cost plan rule, and relies on an energy resource plan not acknowledged by the Public Utility Commission of Oregon:

(i) The names, addresses and telephone numbers of members of any public advisory groups that participated in the preparation and review of each plan identified in paragraph (B).

(ii) A discussion of how the plan or combination of plans conforms to the standards in OAR 345-023-0020(1)(a) through (L) including citations to relevant portions of the plan documents or other supporting evidence.

(iii) The expected annual emissions in tons of nitrogen oxides, PM-10 particulate, sulfur dioxide, carbon dioxide and mercury and a discussion of other environmental impacts, as compared to resources in the applicable energy resource plan.

(D) In addition to the information described in paragraphs (B) and (C), if the applicant chooses to demonstrate need for a proposed natural gas pipeline or storage facility for liquefied natural gas under OAR 345-023-0020(1), the least-cost plan rule, and relies on an energy resource plan not acknowledged by the Public Utility Commission of Oregon, the applicant shall include the information described in paragraph (G) of this subsection if the energy resource plan or combination of plans does not contain that information. If the energy resource plan or combination of plans contains the information described in paragraph (G), the applicant shall provide a list of citations to the sections of the energy resource plan(s) that contain the information;

(E) In addition to the information described in paragraphs (B) and (C), if the applicant chooses to demonstrate need for a proposed electric transmission line under OAR 345-023-0020(1), the least-cost plan rule and relies on an energy resource plan not acknowledged by the Public Utility Commission of Oregon, the applicant shall include the information described in paragraph (F) of this subsection if the energy resource plan or combination of plans does not contain that information. If the energy resource plan or combination of plans contains the information described in paragraph (F), the applicant shall provide a list of citations to the sections of the energy resource plan(s) that contain the information.

(F) If the applicant chooses to demonstrate need for a proposed electric transmission line under OAR 345-023-0030, the system reliability rule:

(i) Load-resource balance tables for the area to be served by the proposed facility. In the tables, the applicant shall include firm capacity demands and existing and committed firm resources for each of the years from the date of submission of the application to at least five years after the expected in-service date of the facility.

(ii) Within the tables described in subparagraph (i), a forecast of firm capacity demands for electricity and firm annual electricity sales for the area to be served by the proposed facility. The applicant shall separate firm capacity demands and firm annual electricity sales into loads of retail customers, system losses, reserve margins and each wholesale contract for firm sale. In the forecast, the applicant shall include a discussion of how the forecast incorporates reductions in firm capacity demand and firm annual electricity sales resulting from:

(I) Existing federal, state or local building codes, and equipment standards and conservation programs required by law for the area to be served by the proposed facility;

(II) Conservation programs provided by the energy supplier, as defined in OAR 345-001-0010;

(III) Conservation that results from responses to price; and

(IV) Retail customer fuel choice;

(iii) Within the tables described in subparagraph (i), a forecast of existing and committed firm resources used to meet the demands described in subparagraph (ii). The applicant shall include, as existing and committed firm resources, existing generation and transmission facilities, firm contract resources and committed new resources minus expected resource retirements or displacement. In the forecast, the applicant shall list each resource separately.

(iv) A discussion of the reasons each resource is being retired or displaced if the forecast described in subparagraph (iii) includes expected retirements or displacements.

(v) A discussion of the annual capacity factors assumed for any generating facilities listed in the forecast described in subparagraph (iii).

(vi) A discussion of the reliability criteria the applicant uses to demonstrate the proposed facility is needed, considering the load carrying capability of existing transmission system facilities supporting the area to be served by the proposed facility.

(vii) A discussion of reasons why the proposed facility is economically reasonable compared to the alternatives described below. In the discussion, the applicant shall include a table showing the amounts of firm capacity and firm annual electricity available from the proposed facility and each alternative and the estimated direct cost, as defined in OAR 345-001-0010, of the proposed facility and each alternative. The applicant shall include documentation of assumptions and calculations supporting the table. The applicant shall evaluate alternatives to construction and operation of the proposed facility that include, but are not limited to:

(I) Implementation of cost-effective conservation, peak load management and voluntary customer interruption as a substitute for the proposed facility.

(II) Construction and operation of electric generating facilities as a substitute for the proposed facility.

(III) Direct use of natural gas, solar or geothermal resources at retail loads as a substitute for use of electricity transmitted by the proposed facility.

(IV) Adding standard sized smaller or larger transmission line capacity.

(viii) The earliest and latest expected in-service dates of the facility and a discussion of the circumstances of the energy supplier, as defined in OAR 345-001-0010, that determine these dates.

(G) If the applicant chooses to demonstrate need for a proposed natural gas pipeline or a proposed facility for storing liquefied natural gas under OAR 345-023-0040, the economically reasonable rule:

(i) Load-resource balance tables for the area to be served by the proposed facility. In the tables, the applicant shall include firm demands and resource availability for each of the years from the date of submission of the application to at least five years after the expected in-service date of the proposed facility. In the tables, the applicant shall list flowing supply and storage supply separately.

(ii) Within the tables described in subparagraph (i), a forecast of firm capacity demands for the area to be served by the proposed facility. The applicant shall separate firm capacity demands into firm demands of retail customers, system losses and each wholesale contract for firm sale. The applicant shall accompany the tables with load duration curves of firm capacity and interruptible demands for the most recent historical year, the year the facility is expected to be placed in service and the fifth year after the expected in-service date. In the forecast of firm capacity demands, the applicant shall include a discussion of how the forecast incorporates reductions in firm capacity demand resulting from:

(I) Existing federal, state or local building codes and equipment standards and conservation programs required by law for the area to be served by the proposed facility;

(II) Conservation programs provided by the energy supplier, as defined in OAR 345-001-0010;

(III) Conservation that results from responses to price; and

(IV) Retail customer fuel choice;

(iii) Within the tables described in subparagraph (i), a forecast of existing and committed firm resources used to meet the demands described in subparagraph (ii). The applicant shall include, as existing and committed firm capacity resources, existing pipelines, storage facilities, and scheduled and budgeted new facilities minus expected resource retirements or displacement. In the forecast, the applicant shall list each committed resource separately.

(iv) A discussion of the reasons each resource is being retired or displaced if the forecast described in subparagraph (iii) includes expected retirements or displacements.

(v) A discussion of the capacity factors assumed for any storage facilities listed in the forecast described in subparagraph (iii).

(vi) A discussion of the reliability criteria the applicant uses to demonstrate the proposed facility is needed, considering the capacity of existing gas system facilities supporting the area to be served by the proposed facility;

(vii) A discussion of reasons why the proposed facility is economically reasonable compared to the alternatives described in subparagraphs (viii) or (ix). In the discussion, the applicant shall include a table showing the amounts of firm capacity available from the proposed facility and each alternative and the estimated direct cost, as defined in OAR 345-001-0010, of the proposed facility and each alternative. The applicant shall include documentation of assumptions and calculations supporting the table.

(viii) In an application for a proposed natural gas pipeline, an evaluation of alternatives to construction and operation of the proposed facility including, but not limited to:

(I) Implementation of cost-effective conservation, peak load management and voluntary customer interruption as a substitute for the proposed facility.

(II) Installation of propane storage systems, facilities to store liquefied natural gas and underground gas storage reservoirs as a substitute for the proposed facility.

(III) Direct use of electricity, solar or geothermal resources at retail loads as a substitute for use of natural gas supplied by the proposed facility.

(IV) Adding standard sized smaller or larger pipeline capacity.

(ix) In an application for a proposed liquefied natural gas storage facility, an evaluation of alternatives to construction and operation of the proposed facility including, but not limited to:

(I) Implementation of cost-effective conservation, peak load management and voluntary customer interruption as a substitute for the proposed facility.

(II) Installation of propane storage systems, natural gas pipelines and underground gas storage facilities as a substitute for the proposed facility.

(III) Direct use of electricity, solar or geothermal resources at retail loads as a substitute for use of natural gas supplied by the proposed facility.

(IV) Adding smaller or larger liquefied natural gas storage capacity; and

(x) The earliest and latest expected in-service date of the facility and a discussion of the circumstances of the energy supplier, as defined in OAR 345-001-0010, that determine these dates.

(o) Exhibit O. Information about anticipated water use during construction and operation of the proposed facility. The applicant shall include:

(A) A description of the use of water during construction and operation of the proposed facility.

(B) A description of each source of water and the applicant’s estimate of the amount of water the facility will need during construction and during operation from each source under annual average and worst-case conditions.

(C) A description of each avenue of water loss or output from the facility site for the uses described in (A), the applicant’s estimate of the amount of water in each avenue under annual average and worst-case conditions and the final disposition of all wastewater.

(D) For thermal power plants, a water balance diagram, including the source of cooling water and the estimated consumptive use of cooling water during operation, based on annual average conditions.

(E) If the proposed facility would not need a groundwater permit, a surface water permit or a water right transfer, an explanation of why no such permit or transfer is required for the construction and operation of the proposed facility.

(F) If the proposed facility would need a groundwater permit, a surface water permit or a water right transfer, information to support a determination by the Council that the Water Resources Department should issue the permit or transfer of a water use, including information in the form required by the Water Resources Department under OAR Chapter 690, Divisions 310 and 380.

(G) A description of proposed actions to mitigate the adverse impacts of water use on affected resources.

(p) Exhibit P. Information about the fish and wildlife habitat and the fish and wildlife species, other than the species addressed in subsection (q) that could be affected by the proposed facility, providing evidence to support a finding by the Council as required by OAR 345-022-0060. The applicant shall include:

(A) A description of biological and botanical surveys performed that support the information in this exhibit, including a discussion of the timing and scope of each survey.

(B) Identification of all fish and wildlife habitat in the analysis area, classified by the habitat categories as set forth in OAR 635-415-0025 and a description of the characteristics and condition of that habitat in the analysis area, including a table of the areas of permanent disturbance and temporary disturbance (in acres) in each habitat category and subtype.

(C) A map showing the locations of the habitat identified in (B).

(D) Based on consultation with the Oregon Department of Fish and Wildlife (ODFW) and appropriate field study and literature review, identification of all State Sensitive Species that might be present in the analysis area and a discussion of any site-specific issues of concern to ODFW.

(E) A baseline survey of the use of habitat in the analysis area by species identified in (D) performed according to a protocol approved by the Department and ODFW.

(F) A description of the nature, extent and duration of potential adverse impacts on the habitat identified in (B) and species identified in (D) that could result from construction, operation and retirement of the proposed facility.

(G) A description of any measures proposed by the applicant to avoid, reduce or mitigate the potential adverse impacts described in (F) in accordance with the ODFW mitigation goals described in OAR 635-415-0025 and a discussion of how the proposed measures would achieve those goals.

(H) A description of the applicant’s proposed monitoring plans to evaluate the success of the measures described in (G).

(q) Exhibit Q. Information about threatened and endangered plant and animal species that may be affected by the proposed facility, providing evidence to support a finding by the Council as required by OAR 345-022-0070. The applicant shall include:

(A) Based on appropriate literature and field study, identification of all threatened or endangered species listed under ORS 496.172(2), ORS 564.105(2) or 16 USC ¦ 1533 that may be affected by the proposed facility.

(B) For each species identified under (A), a description of the nature, extent, locations and timing of its occurrence in the analysis area and how the facility might adversely affect it.

(C) For each species identified under (A), a description of measures proposed by the applicant, if any, to avoid or reduce adverse impact.

(D) For each plant species identified under (A), a description of how the proposed facility, including any mitigation measures, complies with the protection and conservation program, if any, that the Oregon Department of Agriculture has adopted under ORS 564.105(3).

(E) For each plant species identified under paragraph (A), if the Oregon Department of Agriculture has not adopted a protection and conservation program under ORS 564.105(3), a description of significant potential impacts of the proposed facility on the continued existence of the species and on the critical habitat of such species and evidence that the proposed facility, including any mitigation measures, is not likely to cause a significant reduction in the likelihood of survival or recovery of the species.

(F) For each animal species identified under (A), a description of significant potential impacts of the proposed facility on the continued existence of such species and on the critical habitat of such species and evidence that the proposed facility, including any mitigation measures, is not likely to cause a significant reduction in the likelihood of survival or recovery of the species.

(G) The applicant’s proposed monitoring program, if any, for impacts to threatened and endangered species.

(r) Exhibit R. An analysis of significant potential impacts of the proposed facility, if any, on scenic resources identified as significant or important in local land use plans, tribal land management plans and federal land management plans for any lands located within the analysis area, providing evidence to support a finding by the Council as required by OAR 345-022-0080, including:

(A) A list of the local, tribal and federal plans that address lands within the analysis area.

(B) Identification and description of the scenic resources identified as significant or important in the plans listed in (A), including a copy of the portion of the management plan that identifies the resource as significant or important.

(C) A description of significant potential adverse impacts to the scenic resources identified in (B), including, but not limited to, impacts such as:

(i) Loss of vegetation or alteration of the landscape as a result of construction or operation; and

(ii) Visual impacts of facility structures or plumes.

(D) The measures the applicant proposes to avoid, reduce or otherwise mitigate any significant adverse impacts.

(E) A map or maps showing the location of the scenic resources described under (B).

(F) The applicant’s proposed monitoring program, if any, for impacts to scenic resources.

(s) Exhibit S. Information about historic, cultural and archaeological resources. Information concerning the location of archaeological sites or objects may be exempt from public disclosure under ORS 192.502(4) or 192.501(11). The applicant shall submit such information separately, clearly marked as “confidential,” and shall request that the Department and the Council keep the information confidential to the extent permitted by law. The applicant shall include information in Exhibit S or in confidential submissions providing evidence to support a finding by the Council as required by OAR 345-022-0090, including:

(A) Historic and cultural resources within the analysis area that have been listed, or would likely be eligible for listing, on the National Register of Historic Places.

(B) For private lands, archaeological objects, as defined in ORS 358.905(1)(a), and archaeological sites, as defined in ORS 358.905(1)(c), within the analysis area.

(C) For public lands, archaeological sites, as defined in ORS 358.905(1)(c), within the analysis area.

(D) The significant potential impacts, if any, of the construction, operation and retirement of the proposed facility on the resources described in paragraphs (A), (B) and (C) and a plan for protection of those resources that includes at least the following:

(i) A description of any discovery measures, such as surveys, inventories, and limited subsurface testing work, recommended by the State Historic Preservation Officer or the National Park Service of the U.S. Department of Interior for the purpose of locating, identifying and assessing the significance of resources listed in paragraphs (A), (B) and (C).

(ii) The results of the discovery measures described in subparagraph (i), together with an explanation by the applicant of any variations from the survey, inventory, or testing recommended.

(iii) A list of measures to prevent destruction of the resources identified during surveys, inventories and subsurface testing referred to in subparagraph (i) or discovered during construction.

(E) The applicant’s proposed monitoring program, if any, for impacts to historic, cultural and archaeological resources during construction and operation of the proposed facility.

(t) Exhibit T. Information about the impacts the proposed facility would have on important recreational opportunities in the analysis area, providing evidence to support a finding by the Council as required by OAR 345-022-0100, including:

(A) A description of the recreational opportunities in the analysis area that includes information on the factors listed in OAR 345-022-0100(1) as a basis for identifying important recreational opportunities.

(B) A description of any significant potential adverse impacts to the important opportunities identified in (A) including, but not limited to:

(i) Direct or indirect loss of a recreational opportunity as a result of facility construction or operation.

(ii) Noise resulting from facility construction or operation.

(iii) Increased traffic resulting from facility construction or operation.

(iv) Visual impacts of facility structures or plumes.

(C) A description of any measures the applicant proposes to avoid, reduce or otherwise mitigate the significant adverse impacts identified in (B).

(D) A map of the analysis area showing the locations of important recreational opportunities identified in (A).

(E) The applicant’s proposed monitoring program, if any, for impacts to important recreational opportunities.

(u) Exhibit U. Information about significant potential adverse impacts of construction and operation of the proposed facility on the ability of public and private providers in the analysis area to provide the services listed in OAR 345-022-0110, providing evidence to support a finding by the Council as required by OAR 345-022-0110. The applicant shall include:

(A) The important assumptions the applicant used to evaluate potential impacts.

(B) Identification of the public and private providers in the analysis area that would likely be affected.

(C) A description of any likely adverse impact to the ability of the providers identified in (B) to provide the services listed in OAR 345-022-0110.

(D) Evidence that adverse impacts described in (C) are not likely to be significant, taking into account any measures the applicant proposes to avoid, reduce or otherwise mitigate the impacts.

(E) The applicant’s proposed monitoring program, if any, for impacts to the ability of the providers identified in (B) to provide the services listed in OAR 345-022-0110.

(v) Exhibit V. Information about the applicant’s plans to minimize the generation of solid waste and wastewater and to recycle or reuse solid waste and wastewater, providing evidence to support a finding by the Council as required by OAR 345-022-0120. The applicant shall include:

(A) A description of the major types of solid waste and wastewater that construction, operation and retirement of the facility are likely to generate, including an estimate of the amount of solid waste and wastewater.

(B) A description of any structures, systems and equipment for management and disposal of solid waste, wastewater and storm water.

(C) A discussion of any actions or restrictions proposed by the applicant to reduce consumptive water use during construction and operation of the facility.

(D) The applicant’s plans to minimize, recycle or reuse the solid waste and wastewater described in (A).

(E) A description of any adverse impact on surrounding and adjacent areas from the accumulation, storage, disposal and transportation of solid waste, wastewater and stormwater during construction and operation of the facility.

(F) Evidence that adverse impacts described in (D) are likely to be minimal, taking into account any measures the applicant proposes to avoid, reduce or otherwise mitigate the impacts.

(G) The applicant’s proposed monitoring program, if any, for minimization of solid waste and wastewater impacts.

(w) Exhibit W. Information about site restoration, providing evidence to support a finding by the Council as required by OAR 345-022-0050(1). The applicant shall include:

(A) The estimated useful life of the proposed facility.

(B) Specific actions and tasks to restore the site to a useful, non-hazardous condition.

(C) An estimate, in current dollars, of the total and unit costs of restoring the site to a useful, non-hazardous condition.

(D) A discussion and justification of the methods and assumptions used to estimate site restoration costs.

(E) For facilities that might produce site contamination by hazardous materials, a proposed monitoring plan, such as periodic environmental site assessment and reporting, or an explanation why a monitoring plan is unnecessary.

(x) Exhibit X. Information about noise generated by construction and operation of the proposed facility, providing evidence to support a finding by the Council that the proposed facility complies with the Oregon Department of Environmental Quality’s noise control standards in OAR 340-35-0035. The applicant shall include:

(A) Predicted noise levels resulting from construction and operation of the proposed facility.

(B) An analysis of the proposed facility’s compliance with the applicable noise regulations in OAR 340-35-0035, including a discussion and justification of the methods and assumptions used in the analysis.

(C) Any measures the applicant proposes to reduce noise levels or noise impacts or to address public complaints about noise from the facility.

(D) Any measures the applicant proposes to monitor noise generated by operation of the facility.

(E) A list of the names and addresses of all owners of noise sensitive property, as defined in OAR 340-035-0015, within one mile of the proposed site boundary.

(y) Exhibit Y. If the facility is a base load gas plant, a non-base load power plant, or a nongenerating energy facility that emits carbon dioxide, a statement of the means by which the applicant elects to comply with the applicable carbon dioxide emissions standard under OAR 345-024-0560, 345-024-0600, or 345-024-0630 and information, showing detailed calculations, about the carbon dioxide emissions of the energy facility. The applicant may present the calculations in tabular form. The applicant shall include the following information and calculations:

(A) Fuel cycle and usage including the maximum hourly fuel use at net electrical power output at average annual conditions for a base load gas plant and the maximum hourly fuel use at nominal electric generating capacity for a non-base load power plant or a base load gas plant with power augmentation technologies, as applicable.

(B) The gross capacity as estimated at the generator output terminals for each generating unit. For a base load gas plant, gross capacity is based on the average annual ambient conditions for temperature, barometric pressure and relative humidity. For a non-base load plant, gross capacity is based on the average temperature, barometric pressure and relative humidity at the site during the times of year when the facility is intended to operate. For a baseload gas plant with power augmentation, gross capacity in that mode is based on the average temperature, barometric pressure and relative humidity at the site during the times of year when the facility is intended to operate with power augmentation.

(C) A table showing a reasonable estimate of all on-site electrical loads and losses greater than 50 kilowatts, including losses from on-site transformers, plus a factor for incidental loads, that are required for the normal operation of the plant when the plant is at its designed full power operation.

(D) The maximum number of hours per year and energy content (Btu per year, higher heating value) of alternate fuel use.

(E) The total gross carbon dioxide emissions for 30 years, unless an applicant for a non-base load power plant or nongenerating energy facility proposes to limit operation to a shorter time.

(F) The gross carbon dioxide emissions rate expressed as:

(i) Pounds of carbon dioxide per kilowatt-hour of net electric power output for a base load gas plant, including operation with or without power augmentation, as appropriate, or for a non-base load power plant;

(ii) Pounds of carbon dioxide per horsepower hour for nongenerating facilities for which the output is ordinarily measured in horsepower; or

(iii) A rate comparable to pounds of carbon dioxide per kilowatt-hour of net electric power output for nongenerating facilities other than those measured in horsepower.

(G) The total excess carbon dioxide emissions for 30 years, unless an applicant for a non-base load power plant or a nongenerating energy facility proposes to limit operation to a shorter time.

(H) The excess carbon dioxide emissions rate, using the same measure as required for paragraph (F).

(I) The average annual site conditions, including temperature, barometric pressure and relative humidity, together with a citation of the source and location of the data collection devices.

(J) For a non-base load power plant (or when using power augmentation), the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate, together with a citation of the source and location of the data collection devices.

(K) The annual fuel input in British thermal units, higher heating value, to the facility for each type of fuel the facility will use, assuming:

(i) For a base load gas plant, a 100-percent capacity factor on a new and clean basis and the maximum number of hours annually that the applicant proposes to use alternative fuels.

(ii) For a non-base load power plant, the applicant’s proposed annual hours of operation on a new and clean basis, the maximum number of hours annually that the applicant proposes to use alternative fuels and, if the calculation is based on an operational life of fewer than 30 years, the proposed operational life of the facility.

(iii) For a nongenerating energy facility, the reasonably likely operation of the facility based on one year, 5-year, 15-year, and 30-year averages, unless an applicant proposes to limit operation to a shorter time.

(L) For each type of fuel a base load gas plant or a non-base load power plant will use, the estimated heat rate and capacity of the facility measured on a new and clean basis with no thermal energy to cogeneration, consistent with the data supplied in Exhibit B.

(M) For each type of fuel a nongenerating energy facility will use, the estimated efficiency and capacity of the facility with no thermal energy to cogeneration.

(N) If the facility provides thermal energy for cogeneration to lower its net carbon dioxide emissions rate, the applicant shall include:

(i) The estimated annual useful thermal energy available from the facility for non-electric processes, annual useful thermal energy used by non-electric processes, and annual thermal energy rejected as waste heat.

(ii) For a base load gas plant or non-base load power plant, the estimated annual net electric power output and annual fuel input in British thermal units higher heating value for the facility for each type of fuel the facility will use and the basis of such estimates.

(iii) A description of the non-electric thermal processes, the names and addresses of the persons intending to use the non-electric thermal energy, and a description and an estimate of the fuel displaced by cogeneration, including supporting assumptions.

(iv) A description of the products produced and thermal energy needed for production of the primary products made by the persons intending to use the non-electric thermal energy produced by the proposed facility, supported by fuel use and steam production records or estimates, if the production facility is new.

(v) The efficiency of each boiler that the thermal energy will displace.

(vi) For each boiler, the annual fossil fuel displaced in million Btu, higher heating value, by type of fuel that will be displaced by the thermal energy.

(vii) The annual carbon dioxide offset by the cogeneration host, using a rate of 117 pounds of carbon dioxide per million Btu of natural gas fuel (higher heating value) and a rate of 161 pounds of carbon dioxide per million Btu of distillate fuel (higher heating value).

(viii) The cumulative carbon dioxide offset by the steam host through the thirtieth year of facility operation, or for a shorter period if an applicant for a nongenerating facility proposes a shorter operational period.

(ix) A copy of the contractual agreement between the applicant and the cogeneration host for the use of the thermal energy.

(x) A description of the guarantees of offsets that the applicant shall provide for cogeneration projects, pursuant to OAR 345-024-0560(1) and OAR 345-024-0600(1).

(xi) A proposed monitoring and evaluation plan and an independent verification plan, pursuant to subparagraphs (O)(xix) and (O)(xx).

(xii) A copy of the instrument by which the certificate holder will transfer the offsets to the Council for it to hold in trust.

(O) If the applicant proposes to offset carbon dioxide emissions as described in OAR 345-024-0550(3), 345-024-0560(2), 345-024-0590(3), 345-024-0600(2), 345-024-0620(3) or 345-024-0630(1), the applicant shall include:

(i) A description of each offset project.

(ii) A description of who will implement the offset project, including qualifications and experience.

(iii) Detailed estimates of the of carbon dioxide offset, measured in short tons, that the offset projects will achieve over the life of the project.

(iv) For each offset project, an explanation of how the applicant quantified its carbon dioxide estimates to a degree of certainty acceptable to the Council though a transparent and replicable calculation methodology.

(v) For each offset project, evidence that the offset project would not likely have been implemented if not for the applicant’s activities or funding.

(vi) For each offset project, a description of a “Baseline” projection that does not include the proposed project and a “Project Case” projection that does. The historic Baseline shall use reliable emissions data or pre-project data available for the most recent three years unless the applicant can demonstrate that a different period more closely represents historical operations or unless it can demonstrate that another method provides a more reasonable estimate. The applicant shall show how the Baseline projection changes over time if changes from business-as-usual could be reasonably anticipated during the project life.

(vii) For each offset project, a description, in a transparent and realistic manner, of the assumptions and methodologies used to quantify the Baseline and the Project Case projections, including a description of key parameters and data sources. This shall include a description of the formulae used to estimate carbon dioxide emissions or sequestration within the project boundary and a net change of carbon dioxide emissions or sequestration that occurs outside of the project boundary that is measurable and attributable to the project activity.

(viii) For projects that avoid conventional electricity generation, a description of a Baseline that calculates the carbon dioxide emissions per kilowatt hour in two steps: (1) for the first five years of operation, a description of the rate based on dispatch data or models or, absent that, a weighted average of all resources in a power pool except zero-fuel-cost or must-run facilities, and (2) a description of the rate for any subsequent years based on a group of similar facilities built within the prior five years or under construction in the electrical distribution region of the project or the three most recent plants built in the region, whichever rate is lower.

(ix) For projects that avoid conventional electricity generation, a description of avoided transmission and distribution losses, using average grid area or national losses.

(x) A description of any guarantee for offsets from projects that the applicant proposes pursuant to OAR 345-024-0560(2), 345-024-0600(2), and 345-024–630(1), if the applicant chooses to offer a guarantee.

(xi) A description of the offset project boundary. The boundary shall encompass all carbon dioxide emissions under the control of the project that are significant and reasonably attributable to the project activity. If the project is being conducted by one part of a corporation, the boundary shall include the emissions and reductions of the whole corporate entity and the carbon dioxide emissions resulting from processes and facilities that are related to the project, with identification of subsidiaries that are affected by the project.

(xii) A description of significant risks and risk mitigation strategies, including an estimate of the range of uncertainty around the expected carbon dioxide offsets.

(xiii) For biological sequestration projects, an assessment of the risk of climate change to natural systems that are sequestering the carbon dioxide, including, if appropriate, the risks from forest fires, pest and other unplanned releases of carbon from sequestration.

(xiv) A description of whether the offset project will permanently avoid or displace emissions of carbon dioxide. If a project only temporarily sequesters carbon, an indication of the duration of sequestration or storage.

(xv) A description of the amount of funding the applicant will provide for each offset project it proposes.

(xvi) If the applicant anticipates that a project will have funding sources in addition to itself, identification of the sources of those funds, the amount of other funding that is required to implement a project, the amount of funds other parties have committed, and the risks of other funds not being available.

(xvii) If the applicant proposes that a project will have funding sources in addition to itself, a description of how ownership of the offsets will be allocated among the several funding sources.

(xviii) A copy of the instrument by which the certificate holder will transfer all the offsets to the Council for it to hold in trust.

(xix) A description of a transparent and replicable methodology for the applicant’s monitoring and evaluation plan and for an independent verification plan, including (1) procedures the applicant and the independent entity will employ, (2) how the applicant will assure funds for ongoing monitoring, evaluation and verification, (3) the time frame and frequency over which the applicant will conduct monitoring and evaluation and over which the independent entity will conduct verification, including the frequency of site visits, if applicable, (4) the reporting procedures and guidelines for the plans, and (5) whether the applicant has identified the independent entity that will perform the verification.

(xx) The monitoring and evaluation plan and the verification plan shall identify the data needs and data quality with regard to accuracy, comparability, completeness and validity. It shall include methodologies to be used for data collection, monitoring, storage, reporting and management, including quality assurance and quality control provisions. It shall provide complete calculations used to calculate and estimate carbon dioxide emissions from activity within the project boundary. It shall show any formulae and assumptions the applicant used to calculate offset project leakage.

(xxi) A description of reasonably likely, significant undesirable long-term environmental impacts from the implementation of an offset project.

(P) If the applicant elects to comply with the applicable carbon dioxide emissions standard by using the monetary path under OAR 345-024-0560(3), 345-024-0600(3) or 345-024-0630(2), the applicant shall include:

(i) A statement of the applicant’s election to use the monetary path.

(ii) The amount of carbon dioxide reduction, in tons, for which the applicant is taking credit by using the monetary path.

(iii) The qualified organization to whom the applicant will provide offset funds and funds for the cost of selecting and contracting for offsets. The applicant shall include evidence that the organization meets the definition of a qualified organization under OAR 345-001-0010. The applicant may identify an organization that has applied for, but has not received, an exemption from federal income taxation, but the Council shall not find that the organization is a qualified organization unless the organization is exempt from federal taxation under section 501(c)(3) of the Internal Revenue Code as amended and in effect on December 31, 1996.

(iv) A statement of whether the applicant intends to provide a bond or letter of credit to secure the funds it must provide to the qualified organization or whether it requests the option of providing either a bond or a letter of credit.

(z) Exhibit Z. If the proposed facility has an evaporative cooling tower, information about the cooling tower plume, including:

(A) The predicted size and frequency of occurrence of a visible plume and an assessment of its visual impact.

(B) The predicted locations and frequency of occurrence of ice formation on surfaces and ground level fogging and an assessment of significant potential adverse impacts, including, but not limited to, traffic hazards on public roads.

(C) The predicted locations and rates of deposition of solids released from the cooling tower (cooling tower drift) and an assessment of significant potential adverse impacts to soils, vegetation and other land uses.

(D) Any measures the applicant proposes to reduce adverse impacts from the cooling tower plume or drift.

(E) The assumptions and methods used in the plume analysis.

(F) The applicant’s proposed monitoring program, if any, for cooling tower plume impacts;

(aa) Exhibit AA. If the proposed energy facility is a transmission line or has, as a related or supporting facility, a transmission line of any size:

(A) Information about the expected electric and magnetic fields, including:

(i) The distance in feet from the proposed center line of each proposed transmission line to the edge of the right-of-way.

(ii) The type of each occupied structure, including but not limited to residences, commercial establishments, industrial facilities, schools, daycare centers and hospitals, within 200 feet on each side of the proposed center line of each proposed transmission line.

(iii) The approximate distance in feet from the proposed center line to each structure identified in (A).

(iv) At representative locations along each proposed transmission line, a graph of the predicted electric and magnetic fields levels from the proposed center line to 200 feet on each side of the proposed center line.

(v) Any measures the applicant proposes to reduce electric or magnetic field levels.

(vi) The assumptions and methods used in the electric and magnetic field analysis, including the current in amperes on each proposed transmission line.

(vii) The applicant’s proposed monitoring program, if any, for actual electric and magnetic field levels.

(B) An evaluation of alternate methods and costs of reducing radio interference likely to be caused by the transmission line in the primary reception area near interstate, U.S. and state highways.

(bb) Exhibit BB. Any other information that the Department requests in the project order or in a notification regarding expedited review.

(cc) Exhibit CC. Identification, by legal citation, of all state statutes and administrative rules and local government ordinances containing standards or criteria that the proposed facility must meet for the Council to issue a site certificate, other than statutes, rules and ordinances identified in Exhibit E, and identification of the agencies administering those statutes, administrative rules and ordinances. The applicant shall identify all statutes, administrative rules and ordinances that the applicant knows to be applicable to the proposed facility, whether or not identified in the project order. To the extent not addressed by other materials in the application, the applicant shall include a discussion of how the proposed facility meets the requirements of the applicable statutes, administrative rules and ordinances.

(dd) Exhibit DD. If the proposed facility is a facility for which the Council has adopted specific standards, information about the facility providing evidence to support findings by the Council as required by the following rules:

(A) For wind energy facilities, OAR 345-024-0010 and -0015.

(B) For surface facilities related to underground gas storage reservoirs, OAR 345-024-0030, including information required by OAR 345-021-0020.

(C) For any transmission line under Council jurisdiction, OAR 345-024-0090.

(2) Documents prepared in connection with an environmental assessment or environmental impact statement for the proposed facility under the National Environmental Policy Act of 1970, if any, may contain some of the information required under section (1) of this rule. The applicant may copy relevant sections of such documents into the appropriate exhibits of the site certificate application. The applicant may otherwise submit full copies of those documents and include, in the appropriate exhibits of the site certificate application, cross-references to the relevant sections of those documents. The applicant may use such documents only to avoid duplication. The applicant shall include additional information in the site certificate application as needed to meet the requirements of section (1) of this rule.

(3) The applicant shall include a table of contents in the preliminary application identifying the location of each exhibit required by this rule. The applicant shall submit an original and two printed copies of the preliminary application to the Department and shall prepare and distribute additional copies of the application as required by OAR 345-021-0050. Upon a request by the Department, the applicant must submit printed copies of the preliminary application for members of the Council. In addition to the printed copies, the applicant shall submit the full preliminary application in a non-copy-protected electronic format acceptable to the Department.

[ED. NOTE: Exhibits referenced are available from the agency.]

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.350, 469.370, 469.501, 469.503 & 469.504
Hist.: EFSC 6-1980, f. & ef. 8-26-80; EFSC 7-1986, f. & ef. 9-18-86; EFSC 9-1980, f. & ef. 12-22-80; EFSC 1-1981, f. & ef. 1-19-81; EFSC 2-1981, f. & ef. 1-19-81; EFSC 4-1986, f. & ef. 9-5-86; EFSC 2-1992, f. & cert. ef. 8-28-92; EFSC 1-1993, f. & cert. ef. 1-15-93; Renumbered from 345-079-0140, 345-080-0090, 345-100-0055, 345-111-0075, 345-115-0055 & 345-125-0100; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 2-2000, f. & cert. ef. 11-20-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-021-0050

Distribution of a Preliminary Application

(1) Until the Department determines the application to be complete as described in OAR 345-015-0190 or 345-015-0310, it is a preliminary application. After receiving the preliminary application, the Department will prepare the memorandum described in 345-015-0180 and, in coordination with the applicant, determine a distribution date and compile a distribution list. The applicant shall distribute copies of the preliminary application to the persons on the distribution list on or before the distribution date. The Department shall include the reviewing agencies as defined in OAR 345-001-0010 on the distribution list and may include additional persons.

(2) If the applicant obtains written consent from the reviewing agency and provides a copy of that written consent to the Department, the applicant may send specified parts of the preliminary application or an electronic copy of all or specified parts of the preliminary application to the reviewing agency instead of sending a full printed copy.

(3) The distribution described in section (1) may be done by courier delivery or mailing of printed copies or, with the approval of the Department, any form of electronic delivery.

(4) After reviewing the preliminary application, each reviewing agency shall submit written comments or recommendations to the Department that:

(a) State whether the reviewing agency needs any additional information from the applicant to review the application under the statutes, administrative rules or ordinances administered by the reviewing agency and describe such information; and

(b) Describe the status of applications for permits, if any, that the applicant has submitted to the reviewing agency and that are necessary for the construction and operation of the proposed facility.

(5) The Department shall, as soon as practicable, send the applicant copies of all comments submitted under section (4) that identify a need for additional information.

(6)(a) If the applicant has elected to demonstrate compliance with the Council’s land use standard under ORS 469.504(1)(a), each local government with land use jurisdiction over the proposed facility shall, in the comments or recommendations submitted to the Department under section (4), describe the status of the local land use proceedings and state the date when the local government expects to issue a final land use decision.

(b) If the applicant has elected to obtain a Council determination of compliance with the Council's land use standard under ORS 469.504(1)(b), each local government with land use jurisdiction over the proposed facility shall, in the comments or recommendations submitted to the Department under section (4), include:

(A) A complete list of applicable substantive criteria from the local government's acknowledged comprehensive plan and land use regulations that are required by the statewide planning goals and that are in effect on the date the application was submitted. For the purpose of this rule, the application is submitted on the date that the Department receives the preliminary application. “Applicable substantive criteria” means the criteria and standards that the local government would apply in making all land use decisions necessary to site the proposed facility in the absence of a Council proceeding.

(B) A complete list of Land Conservation and Development Commission administrative rules, statewide planning goals and land use statutes directly applicable to the facility under ORS 197.646(3).

(C) Copies of the criteria listed in (A) and any interpretations of ambiguous terms and matters arising from the local government's land use regulations.

(c) The local government may submit its recommendations, comments and interpretations as described in subsection (b) in the form of a resolution adopted by the local governing body.

(7) The applicant shall provide additional copies of the preliminary application to the Department upon request, and copies or access to copies to any person requesting copies.

(8) After receiving the preliminary application, the Department shall post an announcement on its website to notify the public that a preliminary application has been received. The Department shall include in the announcement the addresses of locations where the public may review copies of the preliminary application. The announcement may include the preliminary application or sections of the preliminary application that may be viewed or downloaded. The announcement may include a link to the applicant’s website, if any, where the preliminary application may be viewed or downloaded.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.350
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-021-0055

Distribution of a Complete Application

(1) After receiving notification from the Department of Energy that the application is complete, the applicant shall prepare an application supplement that includes all amendments to the preliminary application and all additional information requested by the Department before the determination of completeness. The supplement may consist of a total revision of the application when necessary to provide a clear presentation of new information. The applicant shall submit an original and two printed copies of the application supplement to the Department. Upon a request by the Department, the applicant must submit printed copies of the application supplement for members of the Council. In addition to the printed copies, the applicant shall submit the full application supplement in a non-copy-protected electronic format acceptable to the Department.

(2) Except as described in OAR 345-015-0310, the applicant shall distribute copies of the supplement to persons on a mailing list provided by the Department, accompanied by the notice from the Department described in OAR 345-015-0200.

(3) If the applicant obtains written consent from a person named on the mailing list and provides a copy of that written consent to the Department, the applicant may send specified parts of the supplement or an electronic copy of all or specified parts of the supplement to that person instead of sending a full printed copy.

(4) The distribution described in section (2) may be done by courier delivery or mailing of printed copies or, with the approval of the Department, any form of electronic delivery.

(5) A “complete application” consists of the preliminary application together with the supplement described in section (1).

(6) The applicant shall provide additional copies of the complete application to the Department upon request and copies or access to copies to any person requesting copies.

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.350
Hist.: EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-021-0090

Amendment of an Application

(1) When the applicant is preparing to submit an amended application, the applicant shall notify the Department of Energy.

(2) The applicant may amend a preliminary application at any time.

(3) If the applicant submits an amended application after the date of filing as determined under OAR 345-015-0190 or 345-015-0310, the Department may withdraw the filing of the application until the Department has reviewed the amended application for completeness as described under OAR 345-015-0190 or 345-015-0310.

(4) If the applicant submits an amended application after issuance of a contested case notice under OAR 345-015-0014, the Department may, by motion, request that the contested case proceeding be terminated and the Council’s hearing officer may issue an order terminating the proceeding. Upon issuance of the order, the Department may withdraw the filing of the application until the Department has reviewed the amended application for completeness as described under OAR 345-015-0190 or 345-015-0310.

(5) The applicant shall submit the original and two printed copies of the amended application to the Department. Upon a request by the Department, the applicant must submit printed copies of the amended application for members of the Council. In addition to the printed copies, the applicant shall submit the full amended application in a non-copy-protected electronic format acceptable to the Department.

(6) The applicant shall distribute copies of the amended application in the manner described in OAR 345-021-0050.

Stat. Auth.: ORS 469.373 & 469.470
Stats. Implemented: ORS 469.350
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-022-0020

Structural Standard

(1) Except for facilities described in sections (2) and (3), to issue a site certificate, the Council must find that:

(a) The applicant, through appropriate site-specific study, has adequately characterized the site as to the Maximum Considered Earthquake Ground Motion as shown for the site in the 2009International Building Code and maximum probable ground motion, taking into account ground failure and amplification for the site specific soil profile under the maximum credible and maximum probable seismic events; and

(b) The applicant can design, engineer, and construct the facility to avoid dangers to human safety presented by seismic hazards affecting the site that are expected to result from maximum probable ground motion events. As used in this rule “seismic hazard” includes ground shaking, ground failure, landslide, liquefaction, lateral spreading, tsunami inundation, fault displacement, and subsidence;

(c) The applicant, through appropriate site-specific study, has adequately characterized the potential geological and soils hazards of the site and its vicinity that could, in the absence of a seismic event, adversely affect, or be aggravated by, the construction and operation of the proposed facility; and

(d) The applicant can design, engineer and construct the facility to avoid dangers to human safety presented by the hazards identified in subsection (c).

(2) The Council may issue a site certificate for a facility that would produce power from wind, solar or geothermal energy without making the findings described in section (1). However, the Council may apply the requirements of section (1) to impose conditions on a site certificate issued for such a facility.

(3) The Council may issue a site certificate for a special criteria facility under OAR 345-015-0310 without making the findings described in section (1). However, the Council may apply the requirements of section (1) to impose conditions on a site certificate issued for such a facility.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 1-1980, f. & ef. 2-28-80; EFSC 1-1981, f. & ef. 1-19-81; EFSC 2-1981, f. & ef. 1-19-81; EFSC 4-1982, f. & ef. 5-3-82; EFSC 4-1986, f. & ef. 9-5-86; EFSC 7-1986, f. & ef. 9-18-86; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-079-0060, 345-100-0040, 345-111-0035; 345-115-0040 & 345-125-0070; EFSC 5-1993(Temp), f. & cert. ef. 8-16-93; EFCS 1-1994, f. & cert. ef. 1-28-94; EFSC 2-1994, f. & cert. ef. 5-6-94; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-023-0005

Need for a Facility

This division applies to nongenerating facilities as defined in ORS 469.503(2)(e), except nongenerating facilities that are related or supporting facilities. To issue a site certificate for a facility described in sections (1) through (3), the Council must find that the applicant has demonstrated the need for the facility. The Council may adopt need standards for other nongenerating facilities. This division describes the methods the applicant shall use to demonstrate need. In accordance with ORS 469.501(1)(L), the Council has no standard requiring a showing of need or cost-effectiveness for generating facilities. The applicant shall demonstrate need:

(1) For electric transmission lines under the least-cost plan rule, OAR 345-023-0020(1), or the system reliability rule for transmission lines, OAR 345-023-0030, or by demonstrating that the transmission line is proposed to be located within a “National Interest Electric Transmission Corridor” designated by the U.S. Department of Energy under Section 216 of the Federal Power Act;

(2) For natural gas pipelines under the least-cost plan rule, OAR 345-023-0020(1), or the economically reasonable rule for natural gas pipelines, OAR 345-023-0040;

(3) For storage facilities for liquefied natural gas with storage capacity of three million gallons or greater under the least-cost plan rule, OAR 345-023-0020(1), or the economically reasonable rule for liquefied natural gas storage facilities, OAR 345-023-0040.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-023-0030

System Reliability Rule for Electric Transmission Lines

The Council shall find that the applicant has demonstrated need for an electric transmission line that is an energy facility under the definition in ORS 469.300 if the Council finds that:

(1) The facility is needed to enable the transmission system of which it is to be a part to meet firm capacity demands for electricity or firm annual electricity salesthat are reasonably expected to occur within five years of the facility’s proposed in-service date based on weather conditions that have at least a 5 percent chance of occurrence in any year in the area to be served by the facility;

(2) The facility is consistent with the minimum operating reliability criteria contained in the Western System Coordinating Council Bulk Power Supply Program 1997-2007, dated April 1, 1998, as it applies either internally or externally to a utility system; and

(3) Construction and operation of the facility is an economically reasonable method of meeting the requirements of sections (1) and (2) compared to the alternatives evaluated in the application for a site certificate.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 9-1980, f. & ef. 12-22-80; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-080-0043; EFCS 5-1993(Temp), f. & cert. ef. 8-16-93; EFCS 1-1994, f. & cert. ef. 1-28-94; EFCS 2-1994, f. & cert. ef. 5-6-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2012, f. & cert. ef. 5-15-12

345-023-0040

Economically Reasonable Rule for Natural Gas Pipelines or Liquified Natural Gas Storage Facilities

The Council shall find the applicant has demonstrated need for a natural gas pipeline that is an energy facility under the definition in ORS 469.300 or a facility that stores liquefied natural gas, if the Council finds that:

(1) The facility is needed to enable the natural gas supply system of which it is to be a part to meet firm capacity demands for natural gas that are reasonably expected to occur within five years following the facility’s proposed in-service date based on weather conditions that have at least a 5 percent chance of occurrence in any year in the areato be served by the proposed facility; and

(2) Construction and operation of the facility is an economically reasonable method of meeting the demands described in section (1) compared to the alternatives evaluated in the application for a site certificate.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 4-1986, f. & ef. 9-5-86; EFSC 1-1993, f. & cert. ef. 1-15-93, Renumbered from 345-125-0040; EFCS 5-1993(Temp), f. & cert. ef. 8-16-93; EFCS 1-1994, f. & cert. ef. 1-28-94; EFCS 2-1994, f. & cert. ef. 5-6-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0015

Siting Standards for Wind Energy Facilities

To issue a site certificate for a proposed wind energy facility, the Council must find that the applicant can design and construct the facility to reduce cumulative adverse environmental effects in the vicinity by practicable measures including, but not limited to, the following:

(1) Using existing roads to provide access to the facility site, or if new roads are needed, minimizing the amount of land used for new roads and locating them to reduce adverse environmental impacts.

(2) Using underground transmission lines and combining transmission routes.

(3) Connecting the facility to existing substations, or if new substations are needed, minimizing the number of new substations.

(4) Designing the facility to reduce the risk of injury to raptors or other vulnerable wildlife in areas near turbines or electrical equipment.

(5) Designing the components of the facility to minimize adverse visual features.

(6) Using the minimum lighting necessary for safety and security purposes and using techniques to prevent casting glare from the site, except as otherwise required by the Federal Aviation Administration or the Oregon Department of Aviation.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0550

Standard for Base Load Gas Plants

To issue a site certificate for a base load gas plant, the Council must find that the net carbon dioxide emissions rate of the proposed facility does not exceed 0.675 pounds of carbon dioxide per kilowatt-hour of net electric power output, with carbon dioxide emissions and net electric power output measured on a new and clean basis. For a base load gas plant designed with power augmentation technology as defined in OAR 345-001-0010, the Council shall apply the standard for a non-base load power plant, as described in OAR 345-024-0590, to the incremental carbon dioxide emissions from the designed operation of the power augmentation technology. The Council shall determine whether the base load carbon dioxide emissions standard is met as follows:

(1) The Council shall determine the gross carbon dioxide emissions that are reasonably likely to result from the operation of the proposed energy facility. The Council shall base such determination on the proposed design of the energy facility. The Council shall adopt site certificate conditions to ensure that the predicted carbon dioxide emissions are not exceeded on a new and clean basis.

(2) For any remaining emissions reduction necessary to meet the applicable standard, the applicant may elect to use any of the means described in OAR 345-024-0560, or any combination thereof. The Council shall determine the amount of carbon dioxide or other greenhouse gas emissions reduction that is reasonably likely to result from the applicant’s offsets and whether the resulting net carbon dioxide emissions meet the applicable carbon dioxide emissions standard. The amount of greenhouse gas emissions means the pounds of carbon dioxide and the carbon dioxide equivalent of other greenhouse gases. For methane, one pound of methane is equivalent to 23 pounds of carbon dioxide. For nitrous oxide, one pound of nitrous oxide is equivalent to 296 pounds of carbon dioxide.

(3) If the applicant elects to comply with the standard using the means described in OAR 345-024-0560(2), the Council shall determine the amount of greenhouse gas emissions reduction that is reasonably likely to result from each of the proposed offsets. In making this determination, the Council shall not allow credit for offsets that have already been allocated or awarded credit for greenhouse gas emissions reduction in another regulatory setting. The fact that an applicant or other parties involved with an offset may derive benefits from the offset other than the reduction of greenhouse gas emissions is not, by itself, a basis for withholding credit for an offset. The Council shall base its determination of the amount of greenhouse gas emission reduction on the following criteria and as provided in OAR 345-024-0680:

(a) The degree of certainty that the predicted quantity of greenhouse gas emissions reduction will be achieved by the offset.

(b) The ability of the Council to determine the actual quantity of greenhouse gas emissions reduction resulting from the offset, taking into consideration any proposed measurement, monitoring and evaluation of mitigation measure performance.

(c) The extent to which the reduction of greenhouse gas emissions would occur in the absence of the offsets.

(4) Before beginning construction, the certificate holder shall notify the Department of Energy in writing of its final selection of a gas turbine vendor and shall submit a written design information report to the Department sufficient to verify the facility’s designed new and clean heat rate and its nominal electric generating capacity at average annual site conditions for each fuel type. In the report, the certificate holder shall include the proposed limits on the annual average number of hours of facility operation on distillate fuel oil, if applicable. In the site certificate, the Council may specify other information to be included in the report. The Department shall use the information the certificate holder provides in the report as the basis for calculating, according to the site certificate, the amount of greenhouse gas emissions reductions the certificate holder must provide under OAR 345-024-0560.

Stat. Auth.: ORS 469.470 & 469.503
Stats. Implemented: ORS 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0560

Means of Compliance for Base Load Gas Plants

The applicant may elect to use any of the following means, or any combination thereof, to comply with the carbon dioxide emissions standard for base load gas plants. For a base load gas plant designed with power augmentation technology, the applicant shall comply with the standard for a non-base load power plant in the manner as described in OAR 345-024-0600 for the incremental carbon dioxide emissions from the designed operation of the power augmentation technology.

(1) Designing and operating the facility to produce electrical and thermal energy sequentially from the same fuel source and using the thermal energy to displace another source of carbon dioxide emissions from fossil fuel that would have otherwise continued to occur. The Council shall adopt site certificate conditions ensuring that the carbon dioxide emissions reduction will be achieved.

(2) Implementing offset projects directly or through a third party, pursuant to OAR 345-024-0680. The Council may adopt site certificate conditions ensuring that the proposed offset projects are implemented by the date specified in the site certificate, but shall not require that predicted levels of avoidance, displacement or sequestration of greenhouse gas emissions be achieved.

(3) Providing offset funds, directly or through a third party, in an amount deemed sufficient to produce the reduction in greenhouse gas emissions necessary to meet the applicable carbon dioxide emissions standard. The applicant or third party shall use the funds as specified in OAR 345-024-0710. The Council shall deem the payment of the monetary offset rate, pursuant to OAR 345-024-0580, to result in a reduction of one ton of carbon dioxide emissions. The Council shall determine the offset funds using the monetary offset rate and the level of emissions reduction required to meet the applicable standard. If the Council issues a site certificate based on this section, the Council may not adjust the amount of the offset funds based on the actual performance of offsets.

(4) Any other means that the Council adopts by rule for demonstrating compliance with the carbon dioxide emissions standard.

(5) If the Council or a court on judicial review concludes that the applicant has not demonstrated compliance with the applicable carbon dioxide emissions standard under sections (1), (2) or (4) of this rule, or any combination thereof, and the applicant agrees to meet the requirements of section (3) for any deficiency, the Council or a court shall find compliance based on such agreement.

Stat. Auth.: ORS 469.470 & 469.503
Stats. Implemented: ORS 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2000, f. & cert. ef. 9-17-01; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0570

Modification of the Standard for Base Load Gas Plants

The Council may by rule modify the carbon dioxide emissions standard for base load gas plants in OAR 345-024-0550 if the Council finds that the most efficient stand alone combined cycle, combustion turbine, natural gas fired energy facility that is commercially demonstrated and operating in the United States has a net heat rate of less than 6,955 Btu per kilowatt hour higher heating value adjusted to ISO conditions. In modifying the carbon dioxide emission standard, the Council shall determine the rate of carbon dioxide emissions per kilowatt hour of net electric output of such energy facility, adjusted to ISO conditions and reset the carbon dioxide emissions standard at 17 percent below this rate.

Stat. Auth.: ORS 469.470 & 469.503
Stats. Implemented: ORS 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0590

Standard for Non-Base Load Power Plants

To issue a site certificate for a non-base load power plant, the Council must find that the net carbon dioxide emissions rate of the proposed facility does not exceed 0.675 pounds of carbon dioxide per kilowatt-hour of net electric power output, with carbon dioxide emissions and net electric power output measured on a new and clean basis. For a base load gas plant designed with power augmentation technology as defined in OAR 345-001-0010, the Council shall apply this standard to the incremental carbon dioxide emissions from the designed operation of the power augmentation technology. The Council shall determine whether the carbon dioxide emissions standard is met as follows:

(1) The Council shall determine the gross carbon dioxide emissions that are reasonably likely to result from the operation of the proposed energy facility. The Council shall base such determination on the proposed design of the energy facility, the limitation on the hours of generation for each fuel type and the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate. For a base load gas plant designed with power augmentation technology, the Council shall base its determination of the incremental carbon dioxide emissions on the proposed design of the facility, the proposed limitation on the hours of generation using the power augmentation technology and the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate with power augmentation technology. The Council shall adopt site certificate conditions to ensure that the predicted carbon dioxide emissions are not exceeded on a new and clean basis; however, the Council may modify the parameters of the new and clean basis to accommodate average conditions at the times when the facility is intended to operate and technical limitations, including operational considerations, of a non-base load power plant or power augmentation technology or for other cause.

(2) For any remaining emissions reduction necessary to meet the applicable standard, the applicant may elect to use any of the means described in OAR 345-024-0600 or any combination thereof. The Council shall determine the amount of carbon dioxide or other greenhouse gas emissions reduction that is reasonably likely to result from the applicant’s offsets and whether the resulting net carbon dioxide emissions meet the applicable carbon dioxide emissions standard. The amount of greenhouse gas emissions means the pounds of carbon dioxide and the carbon dioxide equivalent of other greenhouse gases. For methane, one pound of methane is equivalent to 23 pounds of carbon dioxide. For nitrous oxide, one pound of nitrous oxide is equivalent to 296 pounds of carbon dioxide.

(3) If the applicant elects to comply with the standard using the means described in OAR 345-024-0600(2), the Council shall determine the amount of greenhouse gas emissions reduction that is reasonably likely to result from each of the proposed offsets. In making this determination, the Council shall not allow credit for offsets that have already been allocated or awarded credit for greenhouse gas emissions reduction in another regulatory setting. The fact that an applicant or other parties involved with an offset may derive benefits from the offset other than the reduction of greenhouse gas emissions is not, by itself, a basis for withholding credit for an offset. The Council shall base its determination of the amount of greenhouse gas emission reduction on the following criteria and as provided in OAR 345-024-0680:

(a) The degree of certainty that the predicted quantity of greenhouse gas emissions reduction will be achieved by the offset.

(b) The ability of the Council to determine the actual quantity of greenhouse gas emissions reduction resulting from the offset, taking into consideration any proposed measurement, monitoring and evaluation of mitigation measure performance.

(c) The extent to which the reduction of greenhouse gas emissions would occur in the absence of the offsets.

(4) Before beginning construction, the certificate holder shall notify the Department of Energy in writing of its final selection of an equipment vendor and shall submit a written design information report to the Department sufficient to verify the facility’s designed new and clean heat rate and its nominal electric generating capacity at average annual site conditions for each fuel type. For a base load gas plant designed with power augmentation technology, the certificate holder shall include in the report information sufficient to verify the facility’s designed new and clean heat rate, tested under parameters the Council orders pursuant to section (1), and the nominal electric generating capacity at average site conditions during the intended use for each fuel type from the operation of the proposed facility using the power augmentation technology. The certificate holder shall include the proposed limit on the annual average number of hours for each fuel used, if applicable. The certificate holder shall include the proposed total number of hours of operation for all fuels, subject to the limitation that the total annual average number of hours of operation per year is not more than 6,600 hours. In the site certificate, the Council may specify other information to be included in the report. The Department shall use the information the certificate holder provides in the report as the basis for calculating, according to the site certificate, the gross carbon dioxide emissions from the facility and the amount of greenhouse gas emissions reductions the certificate holder must provide under OAR 345-024-0600.

(5) Every five years after commencing commercial operation, the certificate holder shall report to the Council the facility’s actual annual hours of operation by fuel type. If the actual gross carbon dioxide emissions, calculated using the new and clean heat rate and the actual hours of operation on each fuel during the five-year period, exceed the projected gross carbon dioxide emissions for the five-year period calculated under section (4), the certificate holder shall offset any excess emissions for that period and shall offset estimated future excess carbon dioxide emissions using the monetary path as described in OAR 345-024-0600(3) and (4) or as approved by the Council.

(6) For a base load gas plant designed with power augmentation technology, every five years after commencing commercial operation, the certificate holder shall report to the Council the facility’s actual hours of operation using the power augmentations technology for each fuel type. If the actual gross carbon dioxide emissions, calculated using the new and clean heat rate, tested under parameters the Council orders pursuant to section (1), and the actual hours of operation using the power augmentation technology on each fuel during the five-year period exceed the projected gross carbon dioxide emissions for the five-year period calculated under section (4), the certificate holder shall offset any excess emissions for that period and shall offset estimated future excess carbon dioxide emissions using the monetary path as described in OAR 345-024-0600(3) and (4) or as approved by the Council.

Stat. Auth.: ORS 469.470 & 469.503
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2009, f. & cert. ef. 11-24-09; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0600

Means of Compliance for Non-Base Load Power Plants

The applicant may elect to use any of the following means, or any combination thereof, to comply with the carbon dioxide emissions standard for non-base load power plants or for the incremental carbon dioxide emissions from the operation of a base load gas plant with power augmentation technology:

(1) Designing and operating the facility to produce electrical and thermal energy sequentially from the same fuel source and using the thermal energy to displace another source of carbon dioxide emissions from fossil fuels that would have otherwise continued to occur. The Council shall adopt site certificate conditions ensuring that the carbon dioxide emissions reduction will be achieved.

(2) Implementing offset projects directly or through a third party, pursuant to OAR 345-024-0680. The Council may adopt site certificate conditions ensuring that the proposed offset projects are implemented by the date specified in the site certificate, but shall not require that predicted levels of avoidance, displacement or sequestration of greenhouse gas emissions be achieved.

(3) Providing offset funds, directly or through a third party, in an amount deemed sufficient to produce the reduction in greenhouse gas emissions necessary to meet the applicable carbon dioxide emissions standard. The applicant or third party shall use the funds as specified in OAR 345-024-0710. The Council shall deem the payment of the monetary offset rate, pursuant to OAR 345-024-0580, to result in a reduction of one ton of carbon dioxide emissions. The Council shall determine the offset funds using the monetary offset rate and the level of emissions reduction required to meet the applicable standard. If the Council issues a site certificate based on this section, the Council may not adjust the amount of the offset funds based on the actual performance of offsets.

(4) Notwithstanding sections (1), (2) or (3), if the certificate holder exceeds the projected gross carbon dioxide emissions calculated under OAR 345-024-0590(4) during any five-year reporting period described in OAR 345-024-0590(5) and (6), the certificate holder shall offset excess emissions for the specific reporting period according to subsection (a) and shall offset the estimated future excess emissions according to subsection (b). The certificate holder shall offset excess emissions using the monetary path as described in subsection (c) and OAR 345-024-0710 or as approved by the Council.

(a) In determining the excess carbon dioxide emissions that the certificate holder must offset for a five-year period, the Council shall credit the certificate holder with offsets equal to the difference between the carbon dioxide emissions allowed by the site certificate in previous periods and actual emissions, if actual emissions were lower than allowed. Once a certificate holder has used a credit, the certificate holder shall not use it again.

(b) The Council shall specify in the site certificate a methodology for estimating future excess carbon dioxide emissions. The Department of Energy shall calculate estimated future excess emissions. To estimate excess emissions for the remaining period of the deemed life of the facility, the Department shall use the annual average number of hours of operation during the five-year period in which the certificate holder exceeded the estimated gross carbon dioxide emissions described in OAR 345-024-0590(5) and the new and clean heat rate and capacity for the facility, adjusted for the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate. If the annual average hours exceed 6,600, the Department shall estimate emissions at 100 percent capacity for the remaining period of a deemed 30-year life of the facility. At the request of the certificate holder, the Council may, by amendment of the site certificate, use an alternative methodology to estimate future excess carbon dioxide emissions.

(c) The certificate holder shall pay for the net excess carbon dioxide emissions calculated pursuant to subsections (a) and (b) at the monetary path offset rate in real dollars for the quarter and year in which the Council issued the final order that applied the carbon dioxide standard. The Council shall specify in the site certificate the methodology for calculating the real dollar value of the monetary offset rate. The Department shall calculate the net excess carbon dioxide emissions and notify the certificate holder of the amount of the monetary path payment required to offset them. The certificate holder shall pay fully the required amount to the qualified organization within 60 days of notification by the Department of the amount. The certificate holder shall not be eligible for a refund of any monetary path payments due to the calculations in this rule.

(5) Any other means that the Council adopts by rule for demonstrating compliance with the carbon dioxide emissions standard.

(6) If the Council or a court on judicial review concludes that the applicant has not demonstrated compliance with the applicable carbon dioxide emissions standard under sections (1), (2) or (5) of this rule, or any combination thereof, and the applicant agrees to meet the requirements of sections (3) and (4) for any deficiency, the Council or a court shall find compliance based on such agreement.

Stat. Auth.: ORS 469.470 & 469.503
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 3-2001, f. & cert. ef. 9-17-01; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0610

Modification of the Standard for Non-Base Load Power Plants

The Council may by rule modify the carbon dioxide emissions standard for non-base load power plants in OAR 345-024-0590 so that the standard remains equivalent to the standard for the net carbon dioxide emissions rate of a base load gas plant, subject to the principles described in OAR 345-024-0510.

Stat. Auth.: ORS 469.470 & 469.503
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0620

Standard for Nongenerating Energy Facilities

To issue a site certificate for a nongenerating energy facility that emits carbon dioxide, the Council must find that the net carbon dioxide emissions rate of the proposed facility does not exceed 0.504 pounds of carbon dioxide per horsepower hour. The Council shall determine whether the carbon dioxide emissions standard is met as follows:

(1) The Council shall determine the gross carbon dioxide emissions that are reasonably likely to result from the operation of the proposed energy facility. The Council shall base such determination on the proposed design of the energy facility. In determining gross carbon dioxide emissions for a nongenerating facility, the Council shall calculate carbon dioxide emissions for a 30-year period unless the applicant requests, and the Council adopts in the site certificate, a different period. The Council shall determine gross carbon dioxide emissions based on its findings of the reasonably likely operation of the energy facility. The Council shall use a rate of 117 pounds of carbon dioxide per million Btu of natural gas fuel (higher heating value) and a rate of 161 pounds of carbon dioxide per million Btu of distillate fuel (higher heating value), if the applicant proposes to use such fuel. If the applicant proposes to use any other fossil fuel, the Council shall adopt by rule an appropriate carbon dioxide content rate for the fuel.

(2) For any remaining emissions reduction necessary to meet the applicable standard, the applicant may elect to use any of the means described in OAR 345-024-0630 or any combination thereof. The Council shall determine the amount of carbon dioxide or other greenhouse gas emissions reduction that is reasonably likely to result from the applicant’s offsets and whether the resulting net carbon dioxide emissions meet the applicable carbon dioxide emissions standard. The amount of greenhouse gas emissions means the pounds of carbon dioxide and the carbon dioxide equivalent of other greenhouse gases. For methane, one pound of methane is equivalent to 23 pounds of carbon dioxide. For nitrous oxide, one pound of nitrous oxide is equivalent to 296 pounds of carbon dioxide.

(3) If the applicant elects to comply with the standard using the means described in OAR 345-024-0630(1), the Council shall determine the amount of greenhouse gas emissions reduction that is reasonably likely to result from each of the proposed offsets. In making this determination, the Council shall not allow credit for offsets that have already been allocated or awarded credit for greenhouse gas emissions reduction in another regulatory setting. The fact that an applicant or other parties involved with an offset may derive benefits from the offset other than the reduction of greenhouse gas emissions is not, by itself, a basis for withholding credit for an offset. The Council shall base its determination of the amount of greenhouse gas emission reduction on the following criteria and as provided in OAR 345-024-0680:

(a) The degree of certainty that the predicted quantity of greenhouse gas emissions reduction will be achieved by the offset.

(b) The ability of the Council to determine the actual quantity of greenhouse gas emissions reduction resulting from the offset, taking into consideration any proposed measurement, monitoring and evaluation of mitigation measure performance.

(c) The extent to which the reduction of greenhouse gas emissions would occur in the absence of the offsets.

(4) Before beginning construction, the certificate holder shall notify the Department of Energy in writing of its final selection of an equipment manufacturer and shall submit a written design information report to the Department sufficient to verify the facility’s designed rate of fuel use and its nominal capacity for each fuel type. In the site certificate, the Council may specify other information to be included in the report. The Department shall use the information the certificate holder provides in the report as the basis for calculating, according to the site certificate, the amount of greenhouse gas emissions reductions the certificate holder must provide under OAR 345-024-0630.

(5) In the site certificate, the Council shall specify the schedule by which the certificate holder shall provide offsets. In the schedule, the Council shall specify the amount and timing of offsets the certificate holder must provide to an offset credit account. In determining the amount and timing of offsets, the Council may consider the estimate of total offsets that may be required for the facility and the minimum amount of offsets needed for effective offset projects. The Department shall maintain the record of the offset credit account.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0630

Means of Compliance for Nongenerating Energy Facilities

The applicant may elect to use any of the following means, or any combination thereof, to comply with the carbon dioxide emissions standard for nongenerating energy facilities:

(1) Implementing offset projects directly or through a third party, pursuant to OAR 345-024-0680. The Council may adopt site certificate conditions ensuring that the proposed offset projects are implemented by the date specified in the site certificate, but shall not require that predicted levels of avoidance, displacement or sequestration of greenhouse gas emissions be achieved.

(2) Providing offset funds, directly or through a third party, in an amount deemed sufficient to produce the reduction in greenhouse gas emissions necessary to meet the applicable carbon dioxide emissions standard according to the schedule set forth pursuant to OAR 345-024-0620(5). The applicant or third party shall use the funds as specified in OAR 345-024-0710. The Council shall deem the payment of the monetary offset rate, pursuant to OAR 345-024-0580, to result in a reduction of one ton of carbon dioxide emissions. The Council shall determine the offset funds using the monetary offset rate and the level of emissions reduction required to meet the applicable standard. If the Council issues a site certificate based on this section, the Council may not adjust the amount of the offset funds based on the actual performance of offsets.

(3) Any other means that the Council adopts by rule for demonstrating compliance with the carbon dioxide emissions standard.

(4) Each year after beginning commercial operation, the certificate holder shall report to the Department of Energy data showing the amount and type of fossil fuels used by the facility and its horsepower-hours of operation. The Council shall specify in the site certificate how the Department shall use those data to calculate the gross carbon dioxide emissions from the facility during the report year and the net emissions in excess of the carbon dioxide emissions standard. The Department shall then subtract excess emissions from the offset credit account. The Council shall specify in the site certificate the minimum amount of offset credits that a certificate holder shall provide to establish the offset credit account. The Council may specify an amount of offset credits equal to the total offsets required for the facility. The Council shall specify the minimum amount of offset credits that a certificate holder must maintain in the account and the minimum amount of offset credits the certificate holder shall provide to replenish the account. The Department shall notify the certificate holder when it must replenish its offset credit account according to the conditions in the site certificate. The certificate holder shall maintain a positive balance in the offset credit account for 30 years, unless the Council specifies a different period in the site certificate.

(5) If the certificate holder is replenishing its offset credit account by meeting the monetary path payment requirement described in OAR 345-024-710, the certificate holder may replenish its offset credit account without amending the site certificate by using the calculation methodology detailed in conditions that the Council adopts in the site certificate.

(6) If the certificate holder proposes to replenish the offset credit account under OAR 345-024-0630(1), the Council may amend the site certificate conditions to ensure that the proposed offset projects are implemented.

(7) If the Council or a court on judicial review concludes that the applicant has not demonstrated compliance with the applicable carbon dioxide emissions standard under sections (1), (3) or (6) of this rule, or any combination thereof, and the applicant agrees to meet the requirements of section (2) for any deficiency, the Council or a court shall find compliance based on such agreement.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 3-2001, f. & cert. ef. 9-17-01; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0640

Modification of the Standard for Nongenerating Energy Facilities

The Council may by rule modify the carbon dioxide emissions standard for nongenerating energy facilities in OAR 345-024-0620 so that it remains equivalent to the standard for the net carbon dioxide emissions rate of a base load power plant.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0680

Carbon Dioxide Offset Projects

This rule applies if the applicant elects to meet the applicable carbon dioxide emissions standard in whole or in part under OAR 345-024-0550(3), OAR 345-024-0560(2), OAR 345-024-0590(3), OAR 345-024-0600(2), OAR 345-024-0620(3), or OAR 345-024-0630(1).

(1) Types of offset projects include, but are not limited to: energy efficiency, including demand-side management measures for electricity and natural gas; electricity generation from renewable energy; fuel switching; carbon dioxide sequestration through afforestation, reforestation, forest management and forest conservation; flue gas carbon dioxide sequestration; methane capture and destruction from landfill and biogas methane (animal waste and waste water) or from fugitive methane emissions from existing or abandoned coal mines; nitrogen fertilizer management in agricultural applications; and vehicle carbon dioxide emissions reductions.

(2) In order to approve an offset project, the Council must find that:

(a) The offset project is likely to result in an avoidance, reduction or displacement of actual greenhouse gas emissions from fossil fuels or the sequestration of greenhouse gas emissions resulting from specific and identifiable actions;

(b) The Council can quantify the amount of greenhouse gas offsets, taking into consideration any proposed measurement, monitoring, evaluation and verification of offset project measure performance;

(c) The offsets are not susceptible to double-counting. For offsets from demand-side management measures reducing use of utility-provided electricity or natural gas, it may suffice that the certificate holder or its agent notify the utility that the certificate holder claims ownership of the greenhouse gas reductions;

(d) The applicant will own all greenhouse gas offsets that it proposes to provide;

(e) The applicant has provided a form of the instrument, satisfactory to the Council, through which the applicant will transfer all offsets from a project that an applicant will own to the Council for the Council to hold in trust;

(f) The applicant has the financial and institutional capability to deliver the project for its duration; and

(g) The applicant has provided an adequate monitoring and evaluation plan and an adequate plan for independent verification of the offsets. The monitoring and evaluation plan and the verification plan shall detail the record-keeping, data collection, data storage, data management program, and reporting guidelines and procedures.

(3) If the applicant proposes to implement a project in partnership with other parties or through contracts with other parties, the Council must find that:

(a) The other parties have the financial and institutional capability to deliver the project; and

(b) The applicant has a firm commitment from the other parties to participate in the project.

(4) If the applicant is proposing an offset project in another country, the Council must find that the host country has approved the transfer of the ownership of the greenhouse gas offsets to the applicant for the Council to hold in trust.

(5) The Council shall adjust its estimates of offsets to account for leakage, which is the extent to which events occurring outside the offset project boundary affect an offset project’s total greenhouse gas emissions.

(6) The Council shall not approve any offsets related to nuclear power.

(7) The Council may reject an offset project based on undesirable long-term environmental impacts from the implementation of the offset project that the Council considers to be significant and reasonably likely to occur.

(8) The applicant may propose offset projects that provide offsets for up to 30 years after beginning commercial operation of a facility, or if an applicant proposes to provide offsets for more than 30 years after the beginning of commercial operation of a facility, the Council must find that:

(a) There will be a viable organization that will continue to manage an offset project for a longer period than the duration of the site certificate;

(b) The Council can maintain oversight of the project and hold the responsible organization to the requirements of the site certificate; and

(c) The responsible organization will transfer offsets to the Council after the certificate holder retires the energy facility.

(9) The certificate holder shall begin implementation of projects approved in the site certificate before beginning construction of its facility, and:

(a) The certificate holder shall provide the Council copies of executed contracts or binding agreements with offset providers, including steam hosts for cogeneration if proposed, before beginning construction of its facility, and

(b) The certificate holder shall ensure that offset project implementation begins immediately upon execution of a contract or binding agreement with an offset provider and that the measures are fully implemented within five years, unless the Council approves a longer implementation period through a site certificate condition.

(10) The certificate holder shall not sell or trade its offsets or allow any other entity to report or use the offsets.

(11) The Council shall hold the offsets in trust for the benefit of the State of Oregon.

(12) If the Council approves, a certificate holder may use offsets in a future national regulatory regimen if the Council determines that such use does not undermine the integrity of the Council’s carbon dioxide standard. Such approval shall not require an amendment of the site certificate.

(13) The site certificate holder shall report to the Council annually on the performance of offset projects, pursuant to the monitoring and evaluation plan and to the verification plan, and shall explain changes from the offset benefits projected in the Council’s analysis of the offset projects.

(14) The certificate holder shall provide copies of all monitoring and evaluation reports and any verification reports from the independent entity to the Department of Energy.

(15) The certificate holder shall provide any raw data upon the request of the Department.

(16) The site certificate holder shall make its offset project financial records available for the life of the facility for auditing by the Council or by a party that the Council designates.

Stat. Auth.: ORS 469.470 & 469.501
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0710

Monetary Path Payment Requirement

(1) If the applicant elects to meet the applicable carbon dioxide emissions standard in whole or in part under OAR 345-024-0560(3), OAR 345-024-0600(3) or OAR 345-024-0630(2), (4) and (5), the applicant shall provide a bond or letter of credit in a form reasonably acceptable to the Council to ensure the payment of the offset funds and the additional funds required under section (4) of this rule. The applicant shall provide such security by the date specified in the site certificate. In the site certificate, the Council shall specify a date no later than the commencement of construction of the facility for base load gas plants and non-base load power plants. For nongenerating facilities, the Council shall specify a date no later than the commencement of construction of the facility for providing the initial bond or letter of credit, and the Council shall specify conditions for providing subsequent incremental payments to meeting the monetary path payment requirement. The certificate holder for a nongenerating facility must meet its incremental monetary path payment requirements before exhausting its offset credit account, as described in OAR 345-024-0630(4). In no case shall the applicant diminish the bond or letter of credit or receive a refund from a qualified organization based on the calculations of the facility’s emissions on a new and clean basis for a fossil-fueled power plant or any other measure for a nongenerating energy facility. A qualified organization shall not refund any offset funds to a certificate holder based on the operation or performance of a non-base load power plant during any five-year period reported under OAR 345-024-0590(5) or, for a nongenerating facility, on any offset credits the certificate holder provided under OAR 345-024-0620(5).

(2) In the site certificate, the Council shall require the certificate holder to disburse the offset funds and other funds required as specified in sections (3) and (4), unless the Council finds that no qualified organization exists, in which case the Council shall require the certificate holder to disburse the offset funds as specified in OAR 345-024-0720(2).

(3) When the certificate holder receives written notice from the qualified organization certifying that the qualified organization is contractually obligated to pay any funds to implement offsets using the offset funds, the certificate holder shall make the requested amount available to the qualified organization unless the total of the amount requested and any amounts previously requested exceeds the offset funds, in which case the certificate holder shall make available only the remaining amount of the offset funds. The qualified organization shall use at least 80 percent of the offset funds for contracts to implement offsets. The qualified organization shall assess offsets for their potential to qualify in, generate credits in or reduce obligations in other regulatory settings. The qualified organization may use up to 20 percent of the offset funds for monitoring, evaluation, administration and enforcement of contracts to implement offsets.

(4) At the request of the qualified organization and in addition to the offset funds, the certificate holder shall pay the qualified organization an amount equal to 10 percent of the first $500,000 of the offset funds and 4.286 percent of any offset funds in excess of $500,000. The certificate holder for a base load gas plant shall pay not less than $50,000, unless the Council specifies a lesser amount in the site certificate. In the site certificate, the Council may specify a minimum amount that other fossil-fueled power plants or nongenerating energy facilities must pay. This payment compensates the qualified organization for its costs of selecting offsets and contracting for the implementation of offsets.

(5) Notwithstanding any provision to the contrary, a certificate holder subject to this rule has no obligation with regard to offsets, the offset funds or the funds required by section (4) other than to make available to the qualified organization the total amount required under OAR 345-024-0560(3), OAR 345-024-0600(3) and (4), OAR 345-024-0630(2), (4) and (5), and section (4) of this rule. The Council shall not base a revocation of the site certificate or any other enforcement action with respect to the certificate holder on any nonperformance, negligence or misconduct by the qualified organization.

(6) For monetary path payments a certificate holder must make before beginning construction, the certificate holder shall make all offset fund payments and all payments required by section (4) to the qualifying organization in real dollars of the year in which the Council issues a final order applying the carbon dioxide emissions standard to the energy facility. In the site certificate, the Council shall specify an appropriate inflation index for calculating real dollars. For a non-base load power plant, if a certificate holder must make a payment as described in OAR 345-024-0600(4), the certificate holder shall make a payment that has the same present value per ton of carbon dioxide as the monetary path offset rate of the year in which the Council issued the final order applying the carbon dioxide standard. In the site certificate, the Council shall specify the methodology for calculating present value. If the certificate holder of a nongenerating facility must make payments as described in OAR 345-024-0630(4) and (5), the Council shall specify in the site certificate the method for calculating the rate for the dollar value per ton of carbon dioxide required according to subsection (a) or (b) below:

(a) Unless the applicant and the Council agree to the methodology in subsection (b), the certificate holder shall make payments that have the same present value per ton of carbon dioxide as the monetary path offset rate of the year in which the Council issued the final order applying the carbon dioxide standard. The Council shall set an appropriate discount rate for calculating the present value, using the cost of capital most recently approved by a state utility regulatory commission for that utility or a similar utility as a guide; or

(b) If the applicant requests and the Council agrees, the certificate holder shall make payments at the monetary path offset rate in effect on the date the certificate holder makes the payment.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2012, f. & cert. ef. 5-15-12

345-024-0720

Qualified Organization

(1) If the applicant elects to meet the applicable carbon dioxide emissions standard in whole or in part under OAR 345-024-0560(3), 345-024-0600(3) and (4), or 345-024-0630(2), (4) and (5), the applicant shall identify the qualified organization. The applicant may identify an organization that has applied for, but has not received, an exemption from federal income taxation, but the Council may not find that the organization is a qualified organization unless the organization is exempt from federal taxation under section 501(c)(3) of the Internal Revenue Code as amended and in effect on December 31, 1996.

(2) If the Council finds there is no qualified organization, the certificate holder shall disburse the offset funds according to one or more contracts for implementation of offsets as determined by the following process:

(a) The Council shall establish criteria for selection of offsets, based on the reduction of net carbon dioxide emissions and the criteria set forth in OAR 345-024-0550(3) for base load plants, OAR 345-024-0590(3) for non-base load power plants and OAR 345-024-0620(3) for nongenerating facilities. The Council may consider the costs of particular types of offsets in relation to the expected benefits of such offsets. In establishing criteria, the Council shall not require the certificate holder to select particular offsets and shall allow the certificate holder a reasonable range of choices in selecting offsets.

(b) Based on the criteria established by the Council, the certificate holder shall select one or more offsets. The certificate holder shall give written notice of its selections to the Council and to any person requesting notice. For the purposes of this rule, the date of notice is the date the certificate holder places the notice in the United States mail, with first-class postage prepaid.

(c) On petition by the Department of Energy or by any person adversely affected or aggrieved by the certificate holder’s selection of offsets, or on the Council’s own motion, the Council may review the selection. The petition must be received by the Council within 30 days of the date of notice.

(d) The Council shall approve the certificate holder’s selection unless it finds that the selection is not consistent with criteria established under subsection (a).

(e) The certificate holder shall execute one or more contracts to implement the selected offsets within 18 months after commencing construction of the facility unless the Council allows additional time based on a showing of good cause by the certificate holder. If a certificate holder would have made a payment to a qualified organization as described in OAR 345-024-0600(4) or OAR 345-024-0630(4) or (5), the certificate holder shall instead execute one or more contracts to implement the selected offsets, by a method acceptable to the Council, within 18 months after reporting to the Council as described in OAR 345-024-0590(5) or within 18 months after the Department notifies the certificate holder that the certificate holder must replenish the offset credit account as described in OAR 345-024-0630(4). The certificate holder shall, under such contracts, obligate the expenditure of at least 85 percent of the offset funds for the implementation of offsets. The certificate holder may spend no more than 15 percent of the offset funds on monitoring, evaluation and enforcement of such contracts.

(f) The certificate holder’s financial liability for implementation, monitoring, evaluation and enforcement of offsets under this subsection (2) is limited to the amount of any offset funds not already contractually obligated. The Council shall not base a revocation of the site certificate or any other enforcement action with respect to the certificate holder on any nonperformance, negligence or misconduct by the entity or entities implementing, monitoring or evaluating the selected offsets.

(3) Every qualified organization that has received funds under this rule shall, at five-year intervals beginning on the date of receipt of such funds, provide the Council with the information the Council requests about the qualified organization’s performance. The Council shall evaluate the information requested and, based on such information, shall make recommendations to the Legislative Assembly that the Council deems appropriate.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.501 & 469.503
Hist.: EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-026-0080

Reporting Requirements for Energy Facilities

(1) General reporting obligation for energy facilities under construction or operating:

(a) Within six months after beginning construction, and every six months thereafter during construction of the energy facility and related or supporting facilities, the certificate holder shall submit a semiannual construction progress report to the Department of Energy. In each construction progress report, the certificate holder shall describe any significant changes to major milestones for construction. The certificate holder shall report on the progress of construction and shall address the subjects listed in subsections (2)(a), (d), (f) and (g). When the reporting date coincides, the certificate holder may include the construction progress report within the annual report described in this rule.

(b) After January 1 but no later than April 30 of each year after beginning operation of the facility, the certificate holder shall submit an annual report to the Department addressing the subjects listed in subsection (2). For the purposes of this rule, the beginning of operation of the facility means the date when construction of a significant portion of the facility is substantially complete and the certificate holder begins commercial operation of the facility as reported by the certificate holder and accepted by the Department. The Council Secretary and the certificate holder may, by mutual agreement, change the reporting date.

(c) To the extent that information required by this rule is contained in reports the certificate holder submits to other state, federal or local agencies, the certificate holder may submit excerpts from such other reports to satisfy this rule. The Council reserves the right to request full copies of such excerpted reports.

(2) In the annual report, the certificate holder shall include the following information for the calendar year preceding the date of the report:

(a) Facility Status: An overview of site conditions, the status of facilities under construction and a summary of the operating experience of facilities that are in operation. The certificate holder shall describe any unusual events, such as earthquakes, extraordinary windstorms, major accidents or the like that occurred during the year and that had a significant adverse impact on the facility.

(b) Reliability and Efficiency of Power Production: For electric power plants, the plant availability and capacity factors for the reporting year. The certificate holder shall describe any equipment failures or plant breakdowns that had a significant impact on those factors and shall describe any actions taken to prevent the recurrence of such problems.

(c) Fuel Use: For thermal power plants:

(A) The efficiency with which the power plant converts fuel into electric energy. If the fuel chargeable to power heat rate was evaluated when the facility was sited, the certificate holder shall calculate efficiency using the same formula and assumptions, but using actual data; and

(B) The facility’s annual hours of operation by fuel type and, every five years after beginning operation, a summary of the annual hours of operation by fuel type as described in OAR 345-024-0590(5).

(d) Status of Surety Information: Documentation demonstrating that bonds or letters of credit as described in the site certificate are in full force and effect and will remain in full force and effect for the term of the next reporting period.

(e) Monitoring Report: A list and description of all significant monitoring and mitigation activities performed during the previous year in accordance with site certificate terms and conditions, a summary of the results of those activities and a discussion of any significant changes to any monitoring or mitigation program, including the reason for any such changes.

(f) Compliance Report: A report describing the certificate holder’s compliance with all site certificate conditions that are applicable during the reporting period. For ease of review, the certificate holder shall, in this section of the report, use numbered subparagraphs corresponding to the applicable sections of the site certificate.

(g) Facility Modification Report: A summary of changes to the facility that the certificate holder has made during the reporting period without an amendment of the site certificate in accordance with OAR 345-027-0050.

(h) Nongenerating Facility Carbon Dioxide Emissions: For nongenerating facilities that emit carbon dioxide, a report of the annual fuel use by fuel type and annual hours of operation of the carbon dioxide emitting equipment as described in OAR 345-024-0630(4).

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.310, 469.410, 469.430, 469.501 & 469.507
Hist.: NTEC 9, f. 2-13-75, ef. 3-11-75; EFSC 1-1985, f. & ef. 1-7-85; EFSC 3-1994, f. & cert. ef. 6-28-94; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-026-0170

Notification of Incidents

(1) The certificate holder shall notify the Department of Energy within 72 hours of any occurrence involving the facility if:

(a) There is an attempt by anyone to interfere with its safe operation.

(b) There is a significant natural event such as a fire, earthquake, flood, tsunami or tornado, or human-caused event such as a fire or explosion.

(c) There is any fatal injury at the facility.

(2) For the Trojan Independent Spent Fuel Storage Installation:

(a) In the event of incidents or accidents requiring notification of the Nuclear Regulatory Commission by telephone, the certificate holder also shall notify the Department on the same time schedule.

(b) The certificate holder shall notify the Department of all incidents in accordance with the Emergency Plan, Security Plan, and other agreements as established.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.310, 469.410, 469.430, 469.507 & 469.530
Hist.: NTEC 9, f. 2-13-75, ef. 3-11-75; EFSC 1-1985, f. & ef. 1-7-85; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2005, f. & cert. ef. 5-23-05; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0020

Mandatory Conditions in Site Certificates

The Council shall impose the following conditions in every site certificate. The Council may impose additional conditions.

(1) The Council shall not change the conditions of the site certificate except as provided for in OAR Chapter 345, Division 27.

(2) The certificate holder shall submit a legal description of the site to the Department of Energy within 90 days after beginning operation of the facility. The legal description required by this rule means a description of metes and bounds or a description of the site by reference to a map and geographic data that clearly and specifically identify the outer boundaries that contain all parts of the facility.

(3) The certificate holder shall design, construct, operate and retire the facility:

(a) Substantially as described in the site certificate;

(b) In compliance with the requirements of ORS Chapter 469, applicable Council rules, and applicable state and local laws, rules and ordinances in effect at the time the site certificate is issued; and

(c) In compliance with all applicable permit requirements of other state agencies.

(4) The certificate holder shall begin and complete construction of the facility by the dates specified in the site certificate.

(5) Except as necessary for the initial survey or as otherwise allowed for wind energy facilities, transmission lines or pipelines under this section, the certificate holder shall not begin construction, as defined in OAR 345-001-0010, or create a clearing on any part of the site until the certificate holder has construction rights on all parts of the site. For the purpose of this rule, “construction rights” means the legal right to engage in construction activities. For wind energy facilities, transmission lines or pipelines, if the certificate holder does not have construction rights on all parts of the site, the certificate holder may nevertheless begin construction, as defined in OAR 345-001-0010, or create a clearing on a part of the site if the certificate holder has construction rights on that part of the site and:

(a) The certificate holder would construct and operate part of the facility on that part of the site even if a change in the planned route of a transmission line or pipeline occurs during the certificate holder’s negotiations to acquire construction rights on another part of the site; or

(b) The certificate holder would construct and operate part of a wind energy facility on that part of the site even if other parts of the facility were modified by amendment of the site certificate or were not built.

(6) If the certificate holder becomes aware of a significant environmental change or impact attributable to the facility, the certificate holder shall, as soon as possible, submit a written report to the Department describing the impact on the facility and any affected site certificate conditions.

(7) The certificate holder shall prevent the development of any conditions on the site that would preclude restoration of the site to a useful, non-hazardous condition to the extent that prevention of such site conditions is within the control of the certificate holder.

(8) Before beginning construction of the facility, the certificate holder shall submit to the State of Oregon, through the Council, a bond or letter of credit in a form and amount satisfactory to the Council to restore the site to a useful, non-hazardous condition. The certificate holder shall maintain a bond or letter of credit in effect at all times until the facility has been retired. The Council may specify different amounts for the bond or letter of credit during construction and during operation of the facility.

(9) The certificate holder shall retire the facility if the certificate holder permanently ceases construction or operation of the facility. The certificate holder shall retire the facility according to a final retirement plan approved by the Council, as described in OAR 345-027-0110. The certificate holder shall pay the actual cost to restore the site to a useful, non-hazardous condition at the time of retirement, notwithstanding the Council’s approval in the site certificate of an estimated amount required to restore the site.

(10) The Council shall include as conditions in the site certificate all representations in the site certificate application and supporting record the Council deems to be binding commitments made by the applicant.

(11) Upon completion of construction, the certificate holder shall restore vegetation to the extent practicable and shall landscape all areas disturbed by construction in a manner compatible with the surroundings and proposed use. Upon completion of construction, the certificate holder shall remove all temporary structures not required for facility operation and dispose of all timber, brush, refuse and flammable or combustible material resulting from clearing of land and construction of the facility.

(12) The certificate holder shall design, engineer and construct the facility to avoid dangers to human safety presented by seismic hazards affecting the site that are expected to result from all maximum probable seismic events. As used in this rule “seismic hazard” includes ground shaking, landslide, liquefaction, lateral spreading, tsunami inundation, fault displacement and subsidence.

(13) The certificate holder shall notify the Department, the State Building Codes Division and the Department of Geology and Mineral Industries promptly if site investigations or trenching reveal that conditions in the foundation rocks differ significantly from those described in the application for a site certificate. After the Department receives the notice, the Council may require the certificate holder to consult with the Department of Geology and Mineral Industries and the Building Codes Division and to propose mitigation actions.

(14) The certificate holder shall notify the Department, the State Building Codes Division and the Department of Geology and Mineral Industries promptly if shear zones, artesian aquifers, deformations or clastic dikes are found at or in the vicinity of the site.

(15) Before any transfer of ownership of the facility or ownership of the site certificate holder, the certificate holder shall inform the Department of the proposed new owners. The requirements of OAR 345-027-0100 apply to any transfer of ownership that requires a transfer of the site certificate.

(16) If the Council finds that the certificate holder has permanently ceased construction or operation of the facility without retiring the facility according to a final retirement plan approved by the Council, as described in OAR 345-027-0110, the Council shall notify the certificate holder and request that the certificate holder submit a proposed final retirement plan to the Office within a reasonable time not to exceed 90 days. If the certificate holder does not submit a proposed final retirement plan by the specified date, the Council may direct the Department to prepare a proposed final retirement plan for the Council’s approval. Upon the Council’s approval of the final retirement plan, the Council may draw on the bond or letter of credit described in section (8) to restore the site to a useful, non-hazardous condition according to the final retirement plan, in addition to any penalties the Council may impose under OAR Chapter 345, Division 29. If the amount of the bond or letter of credit is insufficient to pay the actual cost of retirement, the certificate holder shall pay any additional cost necessary to restore the site to a useful, non-hazardous condition. After completion of site restoration, the Council shall issue an order to terminate the site certificate if the Council finds that the facility has been retired according to the approved final retirement plan.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.401 & 469.501
Hist.: NTEC 9, f. 2-13-75, ef. 3-11-75; EFSC 6-1980, f. & ef. 8-26-80; EFSC 1-1985, f. & ef. 1-7-85; EFSC 4-1986, f. & ef. 9-5-86; EFSC 1-1993, f. & cert. ef. 1-15-93; Renumbered from 345-026-0035, 345-026-0040, 345-026-0130, 345-026-0180; 345-079-0011, 345-100-0011, 345-111-0010, 345-115-0040, 345-125-0060 & 345-125-0065; EFSC 5-1994, f. & cert. f. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0023

Site-Specific Conditions

The Council may include the following conditions, as appropriate, in the site certificate:

(1) If the facility uses coal, the certificate holder shall take all necessary steps to ensure that surface and groundwater are not contaminated by run off or seepage associated with coal or ash storage, transport or disposal. The certificate holder shall handle coal and ash so as to minimize the likelihood of coal dust and ash being windblown and causing an environmental or public health problem. If the certificate holder permanently disposes of ash on the facility site, the certificate holder shall cover the ash with a layer of topsoil and revegetate the area.

(2) If the energy facility or related or supporting facility is a natural gas pipeline, the certificate holder shall submit to the Department copies of all incident reports involving the pipeline required under 49 CFR ¦191.15.

(3) If the facility includes any pipeline under Council jurisdiction:

(a) The certificate holder shall design, construct and operate the pipeline in accordance with the requirements of the U.S. Department of Transportation as set forth in Title 49, Code of Federal Regulations, Part 192, in effect as of the date of this rule; and

(b) The certificate holder shall develop and implement a program using the best available practicable technology to monitor the proposed pipeline to ensure protection of public health and safety.

(4) If the facility includes any transmission line under Council jurisdiction:

(a) The certificate holder shall design, construct and operate the transmission line in accordance with the requirements of the National Electrical Safety Code (American National Standards Institute, Section C2, 1997 Edition); and

(b) The certificate holder shall develop and implement a program that provides reasonable assurance that all fences, gates, cattle guards, trailers, or other objects or structures of a permanent nature that could become inadvertently charged with electricity are grounded or bonded throughout the life of the line.

(5) If the proposed energy facility is a pipeline or a transmission line or has, as a related or supporting facility, a pipeline or transmission line, the Council shall specify an approved corridor in the site certificate and shall allow the certificate holder to construct the pipeline or transmission line anywhere within the corridor, subject to the conditions of the site certificate. If the applicant has analyzed more than one corridor in its application for a site certificate, the Council may, subject to the Council’s standards, approve more than one corridor.

(6) If the facility is a surface facility related to an underground gas storage reservoir, the Council shall, in the site certificate, specify the site boundary and total permitted daily throughput of the facility.

(7) If the facility is subject to a carbon dioxide emissions standard adopted by the Council or enacted by statute, the Council shall include in the site certificate appropriate conditions as described in OAR 345-024-0550, 345-024-0560, 345-024-0590, 345-024-0600, 345-024-0620, 345-024-0630 and 345-024-0710.

[Publications: Publications referenced are available from the agency.]

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.401, 469.501 & 469.503
Hist.: EFSC 5-1994, f. & cert. f. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0028

Monitoring Conditions

In the site certificate, the Council shall include conditions that address monitoring and mitigation to ensure compliance with the standards contained in OAR Chapter 345, Division 22 and Division 24. The site certificate applicant, or for an amendment, the certificate holder, shall develop proposed monitoring and mitigation plans in consultation with the Department and, as appropriate, other state agencies, local governments and tribes. Monitoring and mitigation plans are subject to Council approval. The Council shall incorporate approved monitoring and mitigation plans in applicable site certificate conditions.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.401, 469.501, 469.503 & 469.507
Hist.: EFSC 5-1994, f. & cert. f. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0030

Amendment to Extend Construction Beginning and Completion Deadlines

(1) The certificate holder may request an amendment to extend the deadlines for beginning or completing construction of the facility that the Council has specified in a site certificate or an amended site certificate. The certificate holder shall submit a request that includes an explanation of the need for an extension and that conforms to the requirements of 345-027-0060 no later than six months before the date of the applicable deadline, or, if the certificate holder demonstrates good cause for the delay in submitting the request, no later than the applicable deadline.

(2) A request within the time allowed in section (1) to extend the deadlines for beginning or completing construction suspends those deadlines until the Council acts on the request.

(3) The Council shall review the request for amendment as described in OAR 345-027-0070.

(4) If the Council grants an amendment under this rule, the Council shall specify new deadlines for beginning or completing construction that are not more than two years from the deadlines in effect before the Council grants the amendment.

(5) To grant an amendment extending the deadline for beginning or completing construction of an energy facility subject to OAR 345 024 0550, 345 024 0590, or 345 024 0620, the Council must find that the facility complies with the carbon dioxide standard in effect at the time of the Council’s order on the amendment.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370, 469.405 & 469.503
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0050

When an Amendment is Required

(1) Except as allowed under sections (2) and (6), the certificate holder must submit a request to amend the site certificate to design, construct or operate a facility in a manner different from the description in the site certificate if the proposed change:

(a) Could result in a significant adverse impact that the Council has not addressed in an earlier order and the impact affects a resource protected by Council standards;

(b) Could impair the certificate holder’s ability to comply with a site certificate condition; or

(c) Could require a new condition or a change to a condition in the site certificate.

(2) A site certificate amendment is not required if a proposed change in the design, construction or operation of a facility is in substantial compliance with the terms and conditions of the site certificate and is a change:

(a) To an electrical generation facility that would increase the electrical generating capacity and would not increase the number of electric generators at the site, change fuel type, increase fuel consumption by more than 10 percent or enlarge the facility site;

(b) To the number or location of pipelines for a surface facility related to an underground gas storage reservoir that would not result in the facility exceeding permitted daily throughput or enlarge the facility site;

(c) To the number, size or location of pipelines for a geothermal energy facility that would not enlarge the facility site;

(d) To a pipeline or transmission line that is a related or supporting facility that would extend or modify the pipeline or transmission line or expand the right-of-way, when the change is to serve customers other than the energy facility; or

(e) To an aspect or feature of the facility, operating procedures or management structures not addressed in the site certificate.

(3) If the certificate holder concludes that a proposed change does not require a site certificate amendment under section (1), the certificate holder shall, nevertheless, complete an investigation sufficient to demonstrate that the proposed change in the design, construction or operation of the facility would comply with applicable Council standards. The certificate holder shall complete the investigation before implementing the proposed change. The certificate holder shall prepare a written evaluation describing the investigation and shall make the evaluation available to the Department for inspection at any time.

(4) In the annual reports and semiannual construction progress reports required by OAR 345-026-0080, the certificate holder shall describe all significant changes made during the reporting period to the design, construction and operation of the facility without an amendment of the site certificate. The certificate holder shall keep a written record of the basis for concluding that an amendment of the site certificate was not required. The Department, at any time, may inspect the changes made to the facility and may inspect the certificate holder’s written record of the basis for concluding that an amendment of the site certificate was not required.

(5) A certificate holder may submit a change request in writing to the Department for a determination whether a proposed change requires a site certificate amendment. In the change request, the certificate holder must describe the proposed change, explain the basis for the certificate holder’s conclusion that an amendment is not required under section (1), and provide the written evaluation described in section (3). The Department shall respond in writing as promptly as possible. The Department may refer its determination to the Council for concurrence, modification or rejection. At the request of the certificate holder or a Council member, the Department must refer its determination to the Council for concurrence, modification or rejection.

(6) A site certificate amendment is not required for the construction of a pipeline less than 16 inches in diameter and less than five miles in length that is proposed to be constructed to test or maintain an underground gas storage reservoir. If the proposed pipeline would connect to a surface facility related to an underground gas storage reservoir for which the Council has issued a site certificate or to a gas pipeline for which the Council has issued a site certificate, the certificate holder must obtain, prior to construction, the approval of the Department for the construction, operation and retirement of the proposed pipeline. To obtain Department approval, the certificate holder shall submit a request as described in OAR 345-027-0210 through 345-027-0240.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.405
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 3-1995, f. & cert. ef. 11-16-95; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0060

Request to Amend Certificate

(1) To request an amendment of a site certificate, the certificate holder shall submit a written request to the Department of Energy that includes the information described in section (2) and the following:

(a) The name and mailing address of the certificate holder and the name, mailing address, email address and phone number of the individual responsible for submitting the request.

(b) A description of the facility including its location and other information relevant to the proposed change.

(c) A detailed description of the proposed change and the certificate holder’s analysis of the proposed change under the criteria of OAR 345-027-0050(1).

(d) The specific language of the site certificate, including affected conditions, that the certificate holder proposes to change, add or delete by an amendment.

(e) A list of the Council standards relevant to the proposed change.

(f) An analysis of whether the facility, with the proposed change, would comply with the requirements of ORS Chapter 469, applicable Council rules, and applicable state and local laws, rules and ordinances if the Council amends the site certificate as requested. For the purpose of this rule, a law, rule or ordinance is “applicable” if the Council would apply or consider the law, rule or ordinance under OAR 345-027-0070(10).

(g) An updated list of the owners of property located within or adjacent to the site of the facility, as described in OAR 345-021-0010(1)(f).

(2) In a request to amend a site certificate, the certificate holder shall provide the information described in applicable subsections of OAR 345-021-0000 and OAR 345-021-0010. The certificate holder may incorporate by reference relevant information that the certificate holder has previously submitted to the Department or that is otherwise included in the Department’s administrative record on the facility.

(3) Before submitting a request to amend a site certificate, the certificate holder may prepare a draft request and may confer with the Department about the content of the request. Although the Council does not require the certificate holder to prepare a draft request and confer with the Department, the Council recommends that the certificate holder follow this procedure.

(4) The certificate holder shall submit an original and two printed copies of the amendment request to the Department. Upon a request by the Department, the certificate holder must submit printed copies of the amendment request for members of the Council. In addition to the printed copies, the certificate holder shall submit the full amendment request in a non-copy-protected electronic format acceptable to the Department. The certificate holder shall provide additional copies of the amendment request to the Department upon request and copies or access to copies to any person requesting copies. If requested by the Department, the certificate holder shall send copies of the request to persons on a mailing list provided by the Department.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.405
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0070

Review of a Request for Amendment

Except as specified in OAR 345-027-0080, the Council shall review a request for amendment of a site certificate as follows:

(1) Within 15 days after receiving a request to amend a site certificate, the Department of Energy shall determine whether the amendment requires extended review based on the criteria in section (2) and:

(a) Send copies of the request, or instruct the certificate holder to send copies of the request, to the reviewing agencies as defined in OAR 345-001-0010 and ask those agencies to comment on the request by a specified date;

(b) Send a notice of the amendment request to all persons on the Council’s general mailing list as defined in OAR 345-011-0020, to any special list established for the facility and to the most recently received list of property owners or the updated list supplied by the certificate holder under OAR 345-027-0060(1)(g) and specify a date by which comments on the request are due; and

(c) Send a notice to the certificate holder specifying a date for issuance of a proposed order. The Department shall specify a date that is no later than 60 days after the date of the notice unless the Department has determined that the amendment requires extended review. For extended review, the Department shall explain the basis of its determination and specify a date that is not more than 180 days after the date of the notice. Within 10 days after the Department sends notification that an amendment requires extended review, the certificate holder may request Council review of the determination. Upon a request for Council review, the Department shall refer its determination to the Council for concurrence, modification or rejection.

(2) The Department may determine that an amendment requires extended review if:

(a) The certificate holder requests extended review;

(b) The Department finds that the amendment request does not contain the information required by OAR 345-027-0060 or does not contain information sufficient for the Department to prepare a proposed order;

(c) The Department needs to hire a consultant to assist in reviewing the request;

(d) The amendment:

(A) Would require construction on land zoned residential or exclusive farm use;

(B) Would require construction in a zone for which the use is not permitted;

(C) Would require construction on land that may qualify as Habitat Category 1 or 2 land as described in OAR 635-415-0025;

(D) Would result in incremental carbon dioxide emissions that the certificate holder elects to offset, in compliance with the applicable carbon dioxide emissions standard, by a means other than by payments described under OAR 345-024-0560(3), 345-024-0600(3) and (4) or 345-024-0630(2), (4) and (5); or

(E) Could require the Council to determine, according to OAR 345-022-0000(2), that the overall public benefits of the facility outweigh the damage to the resource that is protected by a standard the facility would not meet if the amendment is approved; or

(e) The Department anticipates a high volume of public comment.

(3) The Office may hold one or more public meetings during the review of a request for amendment of the site certificate.

(4) Except as otherwise provided in this section, no later than the date the Department has specified in the notice described in subsection (1)(c), the Department shall issue a proposed order, recommending approval, modification or disapproval of the requested amendment. If the Department needs additional time to prepare the proposed order, the Department may issue the proposed order at a later date, but the Department shall, no later than the date the Department has specified in the notice, notify the certificate holder in writing of the circumstances that justify the delay.

(5) After issuing the proposed order, the Department shall send a notice of the proposed order to the persons on the Council’s general mailing list as defined in OAR 345-011-0020, to any special list established for the facility and to the most recently received list of property owners or the updated list supplied by the certificate holder under OAR 345-027-0060(1)(g). In the notice, the Department shall specify a deadline for submission of written public comments that is at least 30 days from the date of the notice.

(6) Any person may, by written request submitted to the Department no later than the deadline described in section (5), ask the Council to hold a contested case proceeding on the proposed order. For the purpose of this rule, the request is submitted when it is received by the Department. In the request, the person shall provide a description of the issues to be contested, a statement of the facts believed to be at issue and the person’s mailing address.

(7) To determine that an issue justifies a contested case proceeding under section (8), the Council must find that the request raises a significant issue of fact or law that may affect the Council’s determination that the facility, with the change proposed by the amendment, meets an applicable standard. If the Council finds that the request would not affect the Council’s determination if the alleged facts were found to be true but that those facts could affect a site certificate condition, the Council may deny the request and may adopt appropriate conditions. If the Council does not have jurisdiction over the issue raised in the request, the Council must deny the request.

(8) The Council shall determine whether any issue identified in a request for a contested case proceeding justifies a contested case proceeding, and:

(a) If the Council finds that the request identifies one or more issues that justify a contested case proceeding, the Council shall conduct a contested case proceeding according to the applicable provisions of OAR 345-015-0012 to 345-015-0085 limited to the issues that the Council found sufficient to justify the proceeding.

(b) If the Council finds that the request identifies one or more issues that an amendment of the proposed order would settle in a manner satisfactory to the Council, the Council may deny the request as to those issues and direct the Department to amend the proposed order and send a notice of the amended proposed order to the persons described in section (5). Any person may, by written request submitted to the Department within 30 days after the Department issues the notice of the amended proposed order, ask the Council to hold a contested case proceeding limited to issues raised by the amendment to the proposed order. For the purpose of this rule, the request is submitted when it is received by the Department. In the request, the person shall provide a description of the issues to be contested, a statement of the facts believed to be at issue and the person’s mailing address. As described in this section, the Council shall determine whether any issue identified in the request for a contested case proceeding justifies a contested case proceeding.

(c) If the Council finds that the request does not identify any issue that justifies a contested case proceeding, the Council shall deny the request. In a written order denying the request, the Council shall state the basis for the denial. The Council shall then adopt, modify or reject the proposed order based on the considerations described in section (10). In a written order, the Council shall either grant or deny issuance of an amended site certificate. If the Council grants issuance of an amended site certificate, the Council shall issue an amended site certificate, which is effective upon execution by the Council Chair and by the applicant.

(9) If there is no request for a contested case proceeding as described in section (6) or subsection (8)(b), the Council, may adopt, modify or reject the proposed order based on the considerations described in section (10). In a written order, the Council shall either grant or deny issuance of an amended site certificate. If the Council grants issuance of an amended site certificate, the Council shall issue an amended site certificate, which is effective upon execution by the Council Chair and by the applicant.

(10) In making a decision to grant or deny issuance of an amended site certificate, the Council shall apply the applicable substantive criteria, as described in OAR 345-022-0030, in effect on the date the certificate holder submitted the request for amendment and all other state statutes, administrative rules, and local government ordinances in effect on the date the Council makes its decision. The Council shall consider the following:

(a) For an amendment that would change the site boundary or the legal description of the site, the Council shall consider, for the area added to the site by the amendment, whether the facility complies with all Council standards;

(b) For an amendment that extends the deadlines for beginning or completing construction, the Council shall consider:

(A) Whether the Council has previously granted an extension of the deadline;

(B) Whether there has been any change of circumstances that affects a previous Council finding that was required for issuance of a site certificate or amended site certificate; and

(C) Whether the facility complies with all Council standards, except that the Council may choose not to apply a standard if the Council finds that:

(i) The certificate holder has spent more than 50 percent of the budgeted costs on construction of the facility;

(ii) The inability of the certificate holder to complete the construction of the facility by the deadline in effect before the amendment is the result of unforeseen circumstances that are outside the control of the certificate holder;

(iii) The standard, if applied, would result in an unreasonable financial burden on the certificate holder; and

(iv) The Council does not need to apply the standard to avoid a significant threat to the public health, safety or the environment;

(c) For any amendment not described above, the Council shall consider whether the amendment would affect any finding made by the Council in an earlier order.

(d) For all amendments, the Council shall consider whether the amount of the bond or letter of credit required under OAR 345-022-0050 is adequate.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.405
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 2-2000, f. & cert. ef. 11-20-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0080

Review of a Request by a Certificate Holder for Expedited Amendment

(1) A certificate holder may ask the Council Chair to grant expedited review of an amendment request. The certificate holder shall submit a request for expedited review to the Department of Energy in writing and, in addition, the certificate holder shall submit the full amendment request in a non-copy-protected electronic format acceptable to the Department. The certificate holder shall include in the request:

(a) The information listed in OAR 345-027-0060(1) and (2), and

(b) Reasons why the certificate holder needs expedited review of its request and an explanation of why the need for expedited review arose and could not have reasonably been foreseen by the certificate holder.

(2) The Chair may grant a request for expedited review if the Chair finds that a delay would unduly harm the certificate holder and if the facility, with the proposed change, would not likely result in a significant new adverse impact. If the Chair decides not to grant the request for expedited review, the Chair shall issue a written decision as soon as is reasonably practicable. In a written decision denying the request, the Chair shall give an explanation of the reasons for the denial.

(3) Within 7 days after the Chair grants expedited review, the Department shall:

(a) Send copies of the amendment request by mail or email to the reviewing agencies as defined in OAR 345-001-0010 and ask those agencies to comment on the request within not more than 21 days after the date of the notice.

(b) Send a notice of the amendment request by mail or email to all persons on the Council’s general mailing list as defined in OAR 345-011-0020, to any special list established for the facility and to the updated property owner listsupplied by the certificate holder under OAR 345-027-0060(1)(g) specifying a date, not more than 21 days after the date of the notice, by which comments are due.

(c) Post an announcement of the amendment request on its website.

(4) Within 60 days after the Chair grants expedited review, the Department shall issue a proposed order, recommending approval, modification or disapproval of the requested amendment. If the Department recommends approval, the Department shall include in the proposed order any new or modified conditions it recommends and shall explain why expedited Council action was warranted.

(5) The Department shall send a notice of the proposed order by mail or email to the persons on the Council’s general mailing list, to any special list established for the facility and to the updated property owner list supplied by the certificate holder under OAR 345-027-0060(1)(g). In addition, the Department shall post the notice on its website. In the notice, the Department shall include information on the availability of the proposed order, the date of the Council meeting when the Council will consider the proposed order and issue a temporary order as described in section (5), a date by which comments on the proposed order are due and the deadline for any person to request a contested case proceeding on the Council’s temporary order.

(6) After considering the proposed order, the Council may issue an order temporarily amending the site certificate. In making a decision whether to issue a temporary order under this rule, the Council shall consider the factors listed in OAR 345-027-0070(10). The Council shall apply the applicable substantive criteria, as described in OAR 345-022-0030, in effect on the date the certificate holder submitted the request for amendment and all other state statutes, administrative rules, and local government ordinances in effect on the date the Council issues the temporary order.

(7) Before implementing any change approved by the Council’s temporary order, the certificate holder must submit an authorized acknowledgement that the certificate holder accepts all terms and conditions of the temporary order. The acknowledgement may be submitted to the Department by fax or email if the certificate holder promptly submits a signed original to the Department by mail or hand delivery.

(8) Any person may, by written request submitted to the Department within 15 days after the date the Council issues the temporary order described in section (5), ask the Council to hold a contested case proceeding on the temporary order. For the purpose of this rule, the request is submitted when it is received by the Department. In the request, the person shall provide a description of the issues to be contested, a statement of the facts believed to be at issue and the person’s mailing address and email address.

(9) The Council shall determine whether any issue identified in a request for a contested case proceeding justifies a contested case proceeding.

(a) If the Council finds that the request identifies one or more issues that justify a contested case proceeding, the Council shall conduct a contested case proceeding according to the applicable provisions of OAR 345-015-0012 to OAR 345-015-0085 limited to the issues that the Council found sufficient to justify the proceeding.

(b) If the Council finds that the request does not identify any issue that justifies a contested case proceeding, the Council shall deny the request. In a written order denying the request, the Council shall state the basis for the denial. The Council shall adopt the temporary order as a final order. In the final order, the Council may modify the language of the temporary order, consistent with due process. In the final order, the Council shall either grant or deny issuance of an amended site certificate. If the Council grants issuance of an amended site certificate, the Council shall issue an amended site certificate, which is effective upon execution by the Council Chair and by the applicant.

(10) If there is no request for a contested case proceeding as described in section (8), the Council shall adopt the temporary order as a final order. In the final order, the Council may modify the language of the temporary order, consistent with due process. In the final order, the Council shall either grant or deny issuance of an amended site certificate. If the Council grants issuance of an amended site certificate, the Council shall issue an amended site certificate, which is effective upon execution by the Council Chair and by the applicant.

(11) The certificate holder shall not abuse this rule by failing to make timely application for an amendment and thus creating the need for expedited review.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.405
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0090

Request by Any Person for Amendment to Apply Subsequent Laws or Rules

(1) Any person may submit to the Department of Energy a request for an amendment of a site certificate to apply a local government ordinance, statute or Council rule adopted after the date the site certificate was executed. The Department itself may initiate such a request.

(2) In an amendment request under this rule, the person shall include the following:

(a) The name, mailing address, email address and telephone number of the person submitting the request;

(b) The name and address of the certificate holder;

(c) Identification of the facility for which the site certificate in question was granted and its location;

(d) Identification of the local government ordinance, statute or Council rule that the person seeks to apply to the facility;

(e) The particular facts that the person believes demonstrate that failure to apply the ordinance, statute or rule identified in subsection (d) presents a significant threat to the public health or safety or to the environment; and

(f) The specific language of the site certificate that the person proposes to change, delete or add by an amendment.

(3) If the Department receives a request to amend a site certificate as described in this rule from any person other than the certificate holder, the Department shall send a copy of the request to the certificate holder with a notice stating the date by which the certificate holder must submit a response.

(4) The Council shall review the request for amendment as described in OAR 345-027-0070, except that:

(a) After receiving the certificate holder’s response as requested under (3), the Department may ask the Council to determine whether the request demonstrates that failure to apply the ordinance, statute or rule identified in subsection (2)(d) presents a significant threat to the public health or safety or to the environment. If the Council determines that applying the ordinance, statute or rule is not justified by a significant threat to the public health or safety or to the environment, then the Council may deny the amendment request.

(b) Within 15 days after receiving the certificate holder’s response as requested under (3) or within 15 days after a Council determination under (a) that applying the ordinance, statute or rule is justified by a significant threat to the public health or safety or to the environment, the Department shall determine whether the amendment request requires expedited review, based on the criteria in OAR 345-027-0070(2), and shall send the notices described in OAR 345-027-0070(1)(a), (b) and (d).

(c) If the Department recommends approval or modification of the requested amendment, the Department shall include in the proposed order described in OAR 345-027-0070(4) any new or modified site certificate conditions necessary to assure compliance with the statutes, Council rules, and local government ordinances applied to the facility under the proposed order;

(d) If the Department in its proposed order recommends approval or modification of the requested amendment, the certificate holder may, by written request submitted to the Department within 30 days after the Department issues the proposed order, ask the Council to hold a contested case proceeding on the proposed order. For the purpose of this rule, the request is submitted when it is received by the Department. In the request, the certificate holder shall provide a description of the issues to be contested and a statement of the facts believed to be at issue. If the site certificate holder requests a contested case proceeding, the Council shall conduct a contested case proceeding according to the applicable provisions of OAR 345-015-0012 to 345-015-0085 limited to the issues stated by the certificate holder; and

(e) The Council shall include new conditions in a site certificate amended under this rule only if the certificate holder agrees to the new conditions or the Council finds that the conditions are necessary based upon a clear showing of a significant threat to the public health, safety or the environment.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.401 & 469.405
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0100

Transfer of a Site Certificate

(1) For the purpose of this rule:

(a) A transfer of ownership requires a transfer of the site certificate when the person who will have the legal right to possession and control of the site or the facility does not have authority under the site certificate to construct, operate or retire the facility;

(b) “Transferee” means the person who will become the new applicant and site certificate holder.

(2) When a certificate holder has knowledge that any transfer of ownership of the facility that requires a transfer of the site certificate is or may be pending, the certificate holder shall notify the Department of Energy. In the notice, the certificate holder shall include, if known, the name, mailing address and telephone number of the transferee and the date of the transfer of ownership. If possible, the certificate holder shall notify the Department at least 60 days before the date of the transfer of ownership.

(3) The transferee is not allowed to construct or operate the facility until an amended site certificate as described in section (10) or a temporary amended site certificate as described in section (11) becomes effective.

(4) To request a transfer of the site certificate, the transferee shall submit a written request to the Department that includes the information described in OAR 345-021-0010(1)(a), (d), (f) and (m), a certification that the transferee agrees to abide by all terms and conditions of the site certificate currently in effect and, if known, the date of the transfer of ownership. If applicable, the transferee shall include in the request the information described in OAR 345-021-0010(1)(y)(O)(iv).

(5) The Department may require the transferee to submit a written statement from the current certificate holder, or a certified copy of an order or judgment of a court of competent jurisdiction, verifying the transferee’s right, subject to the provisions of ORS Chapter 469 and the rules of this chapter, to possession of the site or the facility.

(6) Within 15 days after receiving a request to transfer a site certificate, the Department shall send a notice of the request by mail or email to the reviewing agencies as defined in OAR 345-001-0010, to all persons on the Council’s general mailing list as defined in OAR 345-011-0020, to any special list established for the facility and to the updated property owner list submitted by the transferee under subsection (4). In the notice, the Department shall describe the transfer request, specify a date by which comments are due and state that the date of the Council’s informational hearing will be announced on the Department’s website.

(7) Before acting on the transfer request, the Council shall hold an informational hearing. The Council shall hold the informational hearing during a Council meeting and shall provide notice of the hearing on its meeting agenda, which will be sent by mail or email to the Council’s general mailing list in advance of the meeting. The informational hearing is not a contested case hearing.

(8) At the conclusion of the informational hearing or at a later meeting, the Council may issue an order approving the transfer request if the Council finds that:

(a) The transferee complies with the standards described in OAR 345-022-0010, 345-022-0050 and, if applicable, OAR 345-024-0710(1); and

(b) The transferee is or will be lawfully entitled to possession or control of the site or the facility described in the site certificate.

(9) Except as described in section (12), the Council shall not otherwise change the terms and conditions of the site certificate in an order approving the transfer request.

(10) Upon issuing the order described in section (8), the Council shall issue an amended site certificate that names the transferee as the new certificate holder. The amended site certificate is effective upon execution by the Council chair and the transferee. The Council shall issue the amended site certificate in duplicate counterpart originals and each counterpart, upon signing, will have the same effect.

(11) If the Council chair determines that special circumstances justify emergency action, the Council chair may, upon a written request from the transferee that includes a showing that the transferee can meet the requirements of section (8), issue a temporary amended site certificate that names the transferee as the new certificate holder. The temporary amended site certificate is effective upon execution by the Council chair and the transferee. The temporary amended site certificate expires when an amended site certificate as described in section (10) becomes effective or as the Council otherwise orders.

(12) The Council may act concurrently on a request to transfer a site certificate and any other amendment request subject to the procedures described in this rule for the transfer request and:

(a) The procedures described in OAR 345-027-0030 for an amendment to extend construction beginning and completion deadlines.

(b) The procedures described in OAR 345-027-0090 for an amendment to apply subsequent laws or rules.

(c) The procedures described in OAR 345-027-0060 and 345-027-0070 for any amendment request not described in (a) or (b).

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.401 & 469.405
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0110

Termination of a Site Certificate

(1) A certificate holder may apply to the Council to terminate a site certificate at any time, subject to the requirements of this rule.

(2) A certificate holder must apply to the Council to terminate a site certificate within two years following cessation of construction or operation of the facility.

(3) If the certificate holder fails to apply to the Council to terminate the site certificate and the Council finds that the certificate holder has permanently ceased construction or operation of the facility, then the Council may terminate the site certificate according to the procedure described in OAR 345-027-0020(16).

(4) In an application for termination of the site certificate, the certificate holder shall include a proposed final retirement plan for the facility and site. The certificate holder shall submit an original and two printed copies of the application for termination and the proposed final retirement plan to the Department. Upon a request by the Department, the certificate holder must submit printed copies of the application for termination and the proposed final retirement plan for members of the Council. In addition to the printed copies, the certificate holder shall submit the full copies of the application for termination and the proposed final retirement plan in a non-copy-protected electronic format acceptable to the Department.

(5) In the proposed final retirement plan, the certificate holder shall include:

(a) A plan for retirement that provides for completion of retirement without significant delay and that protects public health, safety and the environment.

(b) A description of actions the certificate holder proposes to take to restore the site to a useful, non-hazardous condition, including information on how impacts to fish, wildlife and the environment would be minimized during the retirement process.

(c) A current detailed cost estimate and a plan for ensuring the availability of adequate funds for completion of retirement.

(d) An updated list of the owners of property located within or adjacent to the site of the facility, as described in OAR 345-021-0010(1)(f).

(6) Within 15 days after receiving an application for termination of a site certificate, the Department of Energy shall:

(a) Send a notice of the application by mail or email to all persons on the Council’s general mailing list as defined in OAR 345-011-0020, to any special list established for the facility and to the updated property owner list submitted by the certificate holder under subsection (5) specifying a date by which comments on the application are due.

(b) Send copies of the application for termination by mail or email to the reviewing agencies as defined in OAR 345-001-0010 and shall ask those agencies to comment by a specified date.

(c) Post an announcement of the application for termination on the Department’s website.

(7) The Council shall review the proposed final retirement plan and shall consider any comments received from the public and the reviewing agencies. The Council may approve the proposed final retirement plan or modify the plan to comply with the rules of this chapter and applicable conditions in the site certificate. The Council shall issue an order authorizing retirement according to the approved or modified final retirement plan and subject to any conditions the Council finds appropriate. The Council’s order may be appealed as described in ORS 183.480.

(8) When the Council finds that the certificate holder has completed the retirement of the facility according to the Council’s order authorizing retirement, the Council shall issue an order terminating the site certificate.

(9) When the Council finds that the site certificate has expired as described in OAR 345-027-0000, the Council shall issue an order terminating the site certificate.

Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.405 & 469.501
Hist.: EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2003, f. & cert. ef. 9-3-03; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0210

General

(1) A person shall not construct a gas storage testing pipeline unless the certificate holder of the Council certified facility to which the pipeline would connect obtains, before construction, the approval of the Department of Energy for the construction, operation and retirement of the proposed pipeline as required under ORS 469.405(3).

(2) For the purposes of OAR 345-027-0210 through OAR 345-027-0240:

(a) “Gas storage testing pipeline” means a pipeline, but not a temporary pipeline, that is less than 16 inches in diameter and less than five miles in length, that is used to test or maintain an underground gas storage reservoir and that would connect to a Council certified facility if the storage reservoir proves feasible for operational use;

(b) “Temporary pipeline” means a pipeline that has no potential for operational use;

(c) “Council certified facility” means an energy facility for which the Council has issued a site certificate that is either a surface facility related to an underground gas storage reservoir or a gas pipeline;

(d) “Connect” means join for the purpose of operational use;

(e) “Test or maintain” means transporting gas to an underground gas storage reservoir for the purposes of determining whether the reservoir is feasible for operational use or maintaining the gas storage capacity of the reservoir but does not include operational use;

(f) “Operational use” means transporting gas to an underground gas storage reservoir for the purpose of storing gas until it is needed for sale or for withdrawing gas from an underground gas storage reservoir for the purpose of sale;

(g) “Council substantive standards” means the following standards:

(A) Structural Standard, OAR 345-022-0020;

(B) Soil Protection, OAR 345-022-0022;

(C) Protected Areas, OAR 345-022-0040(1) but excluding (2) and (3);

(D) Retirement and Financial Assurance, OAR 345-022-0050;

(E) Fish and Wildlife Habitat, OAR 345-022-0060;

(F) Threatened and Endangered Species, OAR 345-022-0070

(G) Scenic Resources, OAR 345-022-0080;

(H) Historic, Cultural and Archaeological Resources, OAR 345-022-0090;

(I) Recreation, 345-022-0100;

(J) Public Services, OAR 345-022-0110;

(K) Waste Minimization, OAR 345-022-0120; and

(L) Public Health and Safety, OAR 345-024-0030(2), (3) and (4);

(h) “Information requirements” means information that would support the findings described in OAR 345-024-0030(2) and the information described in OAR 345-021-0010(1)(h), (i), (j), (L), (m), (p), (q), (r), (s), (t), (u), (v), and (w).

Stat. Auth.: ORS 469.405
Stats. Implemented: ORS 469.405
Hist.: EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0220

Request for Approval

(1) Before submitting a request for approval to construct, operate and retire a gas storage testing pipeline, the certificate holder shall:

(a) Inform the Department of Energy of the proposed pipeline, including its diameter, length, location, capacity and maximum operating pressure; and

(b) Provide to the Department a map showing the location of the proposed pipeline.

(2) After receiving the information described in section (1), the Department shall confer with the certificate holder about the Council substantive standards and information requirements that might apply to the proposed pipeline and any extraordinary circumstances that might affect the time requirements for completing the approval process. Within 7 days after conferring with the certificate holder, the Department shall send a letter to the certificate holder that includes the following:

(a) Identification of the Council substantive standards that are applicable to the request for approval of the proposed pipeline;

(b) Identification of the information requirements that are applicable to the request for approval of the proposed pipeline;

(c) The time requirements for the approval process, if different from the time requirements described in OAR 345-027-0230.

(3) The certificate holder shall submit to the Department a written request for approval to construct, operate and retire a gas storage testing pipeline with the fee required by the fee schedule established under ORS 469.441. The certificate holder shall submit the original and two paper copies of the request to the Department. The certificate holder shall provide additional copies to the Department upon request and copies or access to copies to any person requesting copies. In addition to the printed copies of the request for approval, the certificate holder shall submit the full request in a non-copy-protected electronic format acceptable to the Department.

(4) In a request for approval, the certificate holder shall include:

(a) The name and mailing address of the certificate holder and the name, mailing address, email address and phone number of the individual responsible for submitting the request;

(b) A description of the purpose and operation of the proposed pipeline and a discussion of whether the use of the gas storage testing pipeline for reservoir testing or maintenance will require an increase in the compression available in the Council certified facility to which the proposed pipeline would connect in addition to the compression that is permitted under the site certificate;

(c) Identification of the Council certified facility to which the proposed pipeline would connect;

(d) A description of the proposed pipeline, including its diameter, length, location, capacity and maximum operating pressure;

(e) A map showing the location of the proposed pipeline;

(f) A list of the names and mailing addresses of all owners of record, as shown on the most recent property tax assessment role, of property where the proposed pipeline is located and within 500 feet of the location of the proposed pipeline;

(g) The information that the Department has identified in the letter described in section (2); and

(h) Any other information that the Department requests as needed to make the findings described in the applicable standards.

Stat. Auth.: ORS 469.405
Stats. Implemented: ORS 469.405, 469.421 & 469.441
Hist.: EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

345-027-0230

Review of a Request for Approval

(1) Within 7 days after receiving a request for approval to construct, operate and retire a gas storage testing pipeline, the Department of Energy shall:

(a) Send copies of the request by mail, email or any other form of electronic delivery to the following agencies with a notice asking the agencies to submit written comments on the request within 14 days from the date of the notice:

(A) Oregon Department of Fish and Wildlife;

(B) Oregon Department of Geology and Mineral Industries;

(C) Oregon Public Utility Commission;

(D) Oregon Department of Agriculture;

(E) Division of State Lands; and

(F) State Historic Preservation Office.

(b) Send a notice of the request, including a map showing the location of the proposed pipeline, by mail, email or any other form of electronic delivery to the following stating that the agencies and planning authority may submit written comments on the request within 14 days from the date of the notice:

(A) Oregon Department of Forestry;

(B) Oregon Department of Environmental Quality; and

(C) The planning authority of the county or counties where the proposed pipeline is located

(c) Send a notice of the request, including a map showing the location of the proposed pipeline, by mail or email to the property owners the certificate holder has listed in the request stating that property owners may submit written comments on the request within 14 days from the date of the notice.

(d) Post an announcement of the request on the Department’s website.

(2) Within 21 days from the deadline for comments described in section (1) or such longer period as the Department has specified in the letter described in OAR 345-027-0220(2), the Department shall issue a final order stating its findings on the applicable Council substantive standards and its approval or disapproval of the request. In an order approving a request, the Department shall include conditions that the Department finds necessary to ensure compliance with the applicable standards and conditions required by OAR 345-027-0240.

(3) The Department shall send a notice of the final order to the certificate holder, to the property owners the certificate holder listed in the request and to any person who commented on the request. In the notice, the Department shall state that judicial review of the order is as provided in ORS 469.403.

(4) The Department may amend an order approving the construction, operation and retirement of a gas storage testing pipeline.

(5) Notwithstanding ORS 469.503(3), the Department shall not review the proposed pipeline for compliance with other state standards.

(6) Notwithstanding ORS 469.401(3), the approval of a gas storage testing pipeline by the Department does not bind any state or local agency.

Stat. Auth.: ORS 469.405
Stats. Implemented: ORS 469.405 & 469.992
Hist.: EFSC 1-2000, f. & cert. ef. 2-2-00; EFSC 1-2002, f. & cert. ef. 4-3-02; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12

Notes
1.) This online version of the OREGON BULLETIN is provided for convenience of reference and enhanced access. The official, record copy of this publication is contained in the original Administrative Orders and Rulemaking Notices filed with the Secretary of State, Archives Division. Discrepancies, if any, are satisfied in favor of the original versions. Use the OAR Revision Cumulative Index found in the Oregon Bulletin to access a numerical list of rulemaking actions after November 15, 2011.

2.) Copyright 2012 Oregon Secretary of State: Terms and Conditions of Use

Oregon Secretary of State • 136 State Capitol • Salem, OR 97310-0722
Phone: (503) 986-1523 • Fax: (503) 986-1616 • oregon.sos@state.or.us

© 2013 State of Oregon All Rights Reserved​